Scaffolding Details: Project Name: Wing No.: Lift No.
Scaffolding Details: Project Name: Wing No.: Lift No.
300 300
900mm
900mm
900mm
900mm
900mm
Fig. C
1. Diameter of the bamboo should not be less than 75 mm.
2. Maintain the distances given above.
3. Before starting the scaffolding, pit should be clean,water proofed and pit depth should be ………..mm
from bottom finished floor level.
4. Scaffolding should be tied firmely.Binding should not be loose.
5. Distance between 2 horizontal bamboos should be 900 mm.
6. Depthwise support is needed on every landing for steadiness of scaffolding as shown in Fig. C
7. Use horizontal firm support after every 30 meters height by using m.s. channels or solid wood pieces.
8. Earthing connection is provided in case of steel scaffolding at two places.
Name and signeture of TKE Representative Name and signeture of Client 's representative
Doc No. 00950P999901360 Page 7