Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Stage 1B Side CWT

ThyssenKrupp Elevator ( India ) Guide Rail Alignment Report Job No.

Layout Drawing No.:


Project Name and Location :
Wing No. Lift No.
BRACKET DBG Landing sill Rail twist
Rail Diagonal CTL CTC Fixing of Smoothn
Floor Name / diagonal
No. from Car Cwt Car Cwt car / cwt ess of rail
Nos.
pit A B B3 B4 C D E F A1 A2 Left Right Left Right bracket joints
Reading as per GAD

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Name & signature of Contractor with Date Name & signature of NI Engineer with Date Name & signature of FQA-in-charge with Date
Doc. No. : 0095OP999901360 Page 23

Stage 1B Side CWT Date :


ThyssenKrupp Elevator ( India )
Guide Rail Alignment Report Job No.

Layout Drawing No.:


Project Name and Location :
Wing No. Lift No.

BRACKET DBG Landing sill Rail twist


Rail Diagonal CTL CTC Fixing of Smoothn
Floor Name / Car Cwt diagonal Car Cwt
No. from car / cwt ess of rail
Nos.
pit A B B3 B4 C D E F A1 A2 Left Right Left Right bracket joints

Reading as per GAD

21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Name & signature of Contractor with Date Name & signature of NI Engineer with Date Name & signature of FQA-in-charge with Date

Doc. No. : 0095OP999901360 Page 24