Professional Documents
Culture Documents
"HMS, HWS, Ma-1 & LPS" AT Diesel Locomotive Works, Varanasi: Alok Gupta
"HMS, HWS, Ma-1 & LPS" AT Diesel Locomotive Works, Varanasi: Alok Gupta
This is to certify that Training report entitled, “HMS, HWS, MA-1 & LPS”
which is submitted by Alok Gupta in partial fulfillment of the requirement
for the award of degree B. Tech in department of Mechanical engineering
of AKTU University, is a record of the candidate own work carried out by
him under supervision. The matter in embodied in this summer training is
original and has not been submitted for the award of BTech degree.
Date:- A K Singh
HOD of Mechanical Engineering
Examiner-1 Examiner-11
DECLARATION
Signature
ALOK GUPTA
ROLL NO: -1638240003
ACKNOWLEDGEMENT
I would sincerely like to thank the employees and the officers of DLW,
Varanasi for their help and support during summer training. Despite their
busy schedule, they took out time for us and explained us the various aspects
of working of the plant from the production shops.
i
PREFACE
ii
CONTENT
ACKNOWLODGEMENT i
PREFACE ii
CHAPTER 1 INTRODUCTION 1
CHAPTER 7 CONCLUSION 23
CHAPTER 9 REFERENCES 25
CHAPTER -1
INTRODUCTION
ISO 14001
1
• Diesel Locomotive Works is production unit under the ministry of
railway. This was setup in collaboration with American locomotive
company (ALCO) USA in 1961 & the first locomotive was rolled out
in 1964.
• This unit products diesel electronic locomotive & DG sets for Indian
railways & other customers in India Abroad. Subsequently a contract
for transfer of technology of 4000HP Microprocessor Controlled
AC/AC Freight (GT 46 MAC) / passenger (GT 46 PAC)locomotive
& family of 710 engines has been signed with electromotive division
of GM of USA for manufacture in DLW is the only manufacture of
Diesel Electric locomotive with both ALCO & GM technologies in
the world.
2
CHAPTER -2
HISTORY OF DLW
3
CHAPTER - 3
This shop carries out the machining of Cycle BLOCK (M.G. & B.G.)
main base, saddler Main bearing caps, Splines, Turbo Super Charger,
Lube Oil, Fuel Oil & Water header) cam bearing housing.
3.1 OPERATION: -
4
3.3 TOOLS USE: -
4. Vernier callipers
5
3.6 H.M.T. ANGULAR BORING MACHINE: -
Fig: - 3.1
6
3.6.1 Main dimension of cycle Block.
7
3.6.2 Main parts of the Cycle Block (B.G.)
Fig: - 3.2
3.7.1 Method: -
Load the block on fixture.For checking weather there is any gap Or
not put the filler of size 0.001” to 0.0015” in side location pad. If there
is No gap then start work otherwise tight .The fixture and recheck till
no gap situation.
9
3.Finish Boring: -
10
3.7.4 Tool: -
Two tools are used for boring both tools are fixed in slot of boring
bar. Due to spindle rotation boring is done. Tool movement and
machine action is governed by G Code and M Code respectively.
Absolute mode and incremental modes are used for tool movement.
Single point cutting tool (two) is first fitted in devise block then in
boring bar.
Crank: -
Rough Boring : 8.880”
Semi Finish Boring : 8-997”
Finish Boring : 9.035”
Cam: -
Rough Boring : 4.700”
Semi Finish Boring : 4.720”
Finish Boring : 4.750”
11
Maximum removal of metal takes place in rough boring.
For making thrust (Cutting)
Tool Size : 10”
R.P.M. : 14
Feed : 22.86 mm/min
(.09”/min)
Tool material used in rough and semi finish boring is high speed steel
and in finish boring amended carbide.
3.8.1 Method: -
3.8.2 Tool: -
There are 18 tools are used. I tool in each side. Each are adjusted
automatically for rough cut and finish cut. During rough cut, finish
tool remains idle and during finish cut, rough tool remains idle. 7
12
tools are fixed in each side in boring bar and two are replaced
according to demand of boring.
Fig: - 3.3
13
CHAPTER - 4
This shop mainly deals with fabrication of the engine block and base (B.G & M.G)
Turbo support after cooler housing items. The engine block is structural member of the
diesel engine. It is composite weldment with heavy plates thickness varying from16
mm to 75 mm & steel forgives conforming to specification is 2062.The spine being
the most highly stressed item as we can say spine of the cylinder block is made out of
one piece bitted 5” * 7” thickness conforming to be 1895.
Fig: - 4.1
Joining of two components by gas electric arc or forge of same or different material
homogeneous and dense joint is called welding.
14
4.2 B l o c k s i n D L W - H W S -
A. Saddle
No. of use width
Intermediate Saddle 07 4.5”
Center Saddle 01 6.75”
T Saddle 01 4.625”
C. S p i n e s
L 20mm
R 20mm
15
E. Middle deck Width
L 40mm
R 40mm
G. Top deck
L
R
In spine welding root run takes place from 1, 3, 5, 7, 9 and then 2, 4, 6, 8.In root
run,4.5 to 5mm electrode is used for welding. After root welding 6.5mm electrode
isused. X-ray quality joints are produced in ALCO.
4.3 W e l d i n g t y p e s i n H W S
5. Tandem welding: -
Used for heavy metal deposition. Use A.C. and D.C. current both for welding. DC
arc lead AC arc transition welding process. Heat input is very low. Good penetration
is obtained. It is one time welding process while in internal and external submerged
welding the process can be repeated several times.
16
Fig: - 4.2
After complete block fabrication heat treatment is done. We put block into diesel
furnace for 28hours.Temprature arises into diesel furnace. At rate 0f 50’per hour and
reach up to 450’C and then rises at the rate of 30’c per hour up to 640’c. At 640’cblock
is kept in furnace for 10 hours and its temp. Reaches at range of 250-280’c.
4.5 Coating: -
- Electrode is coated by iron dust and other filler material. Coating is done
for shielding of welding process.
17
Fig: - 4.3
18
CHAPTER - 5
MAINTENANCE AREA – 1
Maintenance is the action associated with equipment declared after its broken and also
maintenance follows the work of keeping something in proper condition .This implies
that maintenance should be a action that taken to prevent a device of component from
failing or to repair normal equipment degradation process with the operation of the
device.
To keep it in proper working order in DLW maintenance areas it is divided into two
section based on machine work as: -LMS and HMS
5.1 Type of maintenance
It is basically divided into two parts as follows; -
1. Breakdown maintenance
2. Preventive maintenance
19
“planned maintenance” or “systematic maintenance” an extremely important function
production of maintenance cost and to keep the good operational condition of
equipment.
20
CHAPTER - 6
DLW has state of art modern Paint Booth having automated technology for
PU painting of the locomotive. The Paint booth provides safe & better
working environment for operators in Paint booth through clean air supply,
efficient exhaust systems, maintaining the temperature in comfortable range
(25-30°C) with R.H. (60-80 %) of spraying booth.
Paint booth can be operated in both Auto & Manual mode with operating
panel. Paint booth equipped with 2k spray painting equipment to enhance
the painting quality. It is also equipped with three dimensionally operated
man lift, to make it easier for the operator to approach locomotive sides &
roof areas to be painted in the booth.
Drying oven provides hot air circulation in close loop cycle, bearing
temperature 70-80°C in a close surrounding. Close loop cycle prevent heat
losses of circulating hot air & consume less fuel (Diesel).
21
To transport locomotive between heating oven and paint booth, a pit type
traverser of carrying capacity of 150 T has been installed. It facilitates
shifting of locomotive between Paint Booth to Drying Oven.
Fig: - 6.1
22
CHAPTER -7
CONCLUSION
23
CHAPTER - 8
FUTURE SCOPE
295 locos (1070 hhp diesel and 15 locos for NCR ) have been planned
to manufacture in FY 2018-19 as per Railway board mendate.
24
CHAPTER – 9
REFERENCES
1. www.dlw.indianrailways.gov.in
2. http://trainweb.org/railworld/DLW/
3. http://www.scribd.com/doc/64559155/Report-on-Summer-Training-
at-Dlw-Varanasi
4. http://www.scribd.com/doc/54456974/Summer-Traning-DLW-
Report
5. http://www.scribd.com/doc/45187594/Summer-Training-Diesel-
Locomotive-Works-Ppt
25