Professional Documents
Culture Documents
Apply Problem Solving Techniques in The Work Site
Apply Problem Solving Techniques in The Work Site
Analyses construction
– Environmental management,
– Energy conservation problems
– Applies appropriate and
– compliant remedial solutions
Ensures processes that identify faults and required remedial action
– Develops strategies to address project delays
– Performs various complex calculations relating to cost-benefit analysis,
– Rise and fall amounts,
– pessimistic overdraft requirements,
– statistical analysis,
– costs,
– set out of construction work,
– structural analysis and service installations
Analyses reasons for cost variations and takes remedial action
– Establishes and implements dispute resolution procedures
– Maintains site safety and manages risks
– Provides advice on dispute resolution
– Uses and analyses data in decision making
Negotiation
– Marketing and/or contract administration organizations distribute copies of
customer
Specifications
– subsequent changes regarding technical, administrative, and
– quality requirements to appropriate functional groups for review and
– Comment prior to proposal submittal.
– This review is performed to ensure that customer requirements are
adequately defined and understood,
– That the capability exists to meet these requirements.
During the review,
– Marketing and/or contract administration organizations coordinate all
communication with the customer. A record of the review is maintained.
Lo 1. Identify the problem
1. Construction Claims
Claim is legally defined as an assertion to right.
The nature of right may relate to time, financial, or other remedies.
Claim is therefore a substantive demand, for example, by the Contractor against the
Employer.
The Employer may have its own substantive demand against the Contractor.
1
Claims under the Contract
These are of two types:
Claims as a result of certain specified events.
Claims as a result of an event where a certain term of the contract is breached.
In both cases, the remedy is provided under the contract.
However, the first related to non-breach of the contract, whereas, the second does.
The remedies in both cases may relate to financial compensation, time extension.
1. Financial compensation:
With respect to Variation;
Measurement Changes
Adverse Physical Conditions
The Employer’s Risks
Compliance with statutes, regulations, price fluctuations
Delay in certifying payments; etc.
2. Time Extension
Delay in supply of documents or drawings.
Fossils & articles of value or antiquity.
Tests required but not provided
Suspension of the progress of the works.
Failure to give possession of site.
3. Other Benefits or Remedies
Termination of contract under the contract and/or the applicable law.
Suspension of the execution of works.
Reduction of the progress of the execution of works.
4. Remedy under the Law
Under this circumstance, if the claim is valid, the remedy lies under the provisions
of the applicable law.
This is specially related to the assessment of damages or specific performance or
others.
2
In such a situation, the Engineer is not empowered to assess & determine any
damages or order specific performance of the construction contract under the
applicable law.
The remedy would be sought through adjudication, arbitration or litigation unless
the claim is settled amicably.
• completion time;
• construction cost;
• quality performance; and
• Safety requirements.
The following categories of factors may also contribute to the emergence of claims.
– Changed conditions;
– Additional works;
– For the claim to be successful, it has to fulfill certain valid requirements. These
requirements are related to:
3
A. Substantive requirements;
B. Procedural requirements; and
C. Proof requirements;
Substantive Requirements
• The provisions of contract mean the relevant clause in the contract, which has been
signed between the parties.
• The provisions of the applicable law means the relevant article of the law, which is
applicable to the contract, for ex. The Civil Code.
• Submitting a claim, without first establishing its legitimacy, under the Contract and/or
under the applicable law is a futile exercise with no guaranteed return.
Procedural Requirements
• By procedural requirement we mean the serving of the required prior written notice to the
designated party under the contract.
• This is called intention to claim.
• This prior written notice shall also be given within the contractually designated time
scale.
• The time scale might be specific or reasonable
• The contract under consideration may specify such time scale in either way.
• The non-observance of the procedural requirement may result whole or partial loss of the
substantive claim.
Proof Requirements
4
• variations claims; and
• In case of disputes the proof requirement, in addition to the relevant documentation, may
also include:-
Factual Witnesses;
Expert Opinion;
3. Process of Claims
Claim Submittal;
Claim Processing;
Claim Enforcement;
Claim Submittal
obliged to claim within a reasonable period of time ( 28-30 days in most contracts)
followed by the claimant’s preparation for all substantial documents
Claim Preparation & Claim Submittal are fully undertaken by the claimant.
Claim Processing
Claim Handling;
Dispute Resolution;
Claim Approval;
A. The Claim Handling, this sub-process initiates checking of the claim whether,
• It is legally or contractually supported or not,
• documents provided are valid and reliable to substantiate the claim for
consideration or not,
5
• And overall procedural requirements have been followed or not.
• After verifying the validity of the claim proper computations & evaluations
B. Dispute Resolution, the contractual parties will pass through different dispute
resolution system depending on their acceptance over the proposed
These are
C. Claim Approval, once the contractual parties agree on the final outcome of the claim
process, then they have reached in to a stage where the claim is approved.
Claim Enforcement
– Claim Enforcement;
– Claim Closure;
• The claim enforcement sub-process will entertain the inclusion of the approved claim in
to payment certificates where their enforcement is due.
• Once this compensation or entitlement is due in accordance with the approved claim and
its enforcement requirements, then it is concluded for its closure.
• In order to account for such an administration process contracts provide claim clauses
within their provisions in their conditions of contract.
4. Construction Disputes
Construction dispute may take different forms: dispute in relation to time or cost, time &
cost or otherwise.
6
Disputes relative to Time
With respect to dispute relative to time or delay the following aspects shall be considered.
With respect to delay the contractor or the employer may have their own respective
claims
The employer’s claim is related to liquidated damages.
The contractor’s claim mostly related to prolongation and/or disruption claims.
These are referred to as site over heads & consist of the costs of an administrative & supervisory
staff including but not limited to:
• Site staff, Trades foremen, Plant & tools, Welfare including cleaning…,Lighting &
power, Storage, workshops, temporary works, Contractor’s site office including its
equipment & communication charges;
• Sanitary accommodation;
• Scaffolding;
• Transport;
Off-site Overhead:
The off-site overheads cover contributions by individual contracts to the cost of
maintaining the contractor’s head office..
Adverse weather conditions:
A claim may arise if as a result of a change in the timing of the execution of the works
attributable to the employer, adverse weather conditions are encountered.
Increased costs of labor, materials or equipment;
Finance charges & interest;
Profit on direct costs;
7
Loss of profit;
Interest on late payment
Disruption may be defined as the effect of an event or
A number of events on the efficiency of execution of the works, irrespective of whether
or not there had been a delay to a critical activity.
An identification & analysis of each of the operations claimed to have been disrupted..
The cause & the manner in which disruption has occurred should be established.
The resources planned & the time required to achieve the completion of the disrupted
operations as calculated in the tender have to be shown to be achievable.
The works should be properly calculated & its effect included in the calculations of
disruption suffered.
The number of hours actually logged in the time sheets for the disrupted operation has to
be shown to be accurate.
– When records are available & are correct,
When acceleration of the progress of the works is required, the cost may include the
expense of,
Programming
In relation to monitoring the progress of the works, program is an indispensable guiding
tool.
Programming involves introducing the parameters of time & resources into the work
activities & ultimately into the project itself.
The traditional method of presenting a programmer for the construction contract has been
through a bar chart.
8
For the purpose of project control,
Planning phase
- Where a network of all activities necessary for the completion of a
project is planned & drawn up. An activity is an operation where
time & resources are consumed.
Project timing
- Where estimates of duration of activities are calculated to
determine as accurately as possible the project duration & to
identify the activities which may prove to be critical.
Resource allocation
- Where information is added to each activity duration to show the
resources required to complete that activity within the projected
duration.
Allocation of work to sub-contractors & a programmer
- Of appointment to be followed with a schedule for production &
approval of sub-contractors’ design, if any, and drawings.
Pricing of the various elements of the works.
Procurement of materials.
Commencement of works on site.
Project control
- Where the actual progress on site is periodically measured against
the network plan.
- The network must then be updated in accordance with the actions
taken, and a report can be periodically compiled to highlight the
status of each activity at the particular time.The report may show:
Delay in an activity & its effect on other activities & on the time for completion;
New activities due to variation & the effect on others & on the time for completion;
Resources which must be drafted to redress any new situations;
Any other change in the critical path network;
9
Network analysis is, therefore, critical in delay claims of the contractor.
1. The following are some of the internationally recognized dispute prevention systems.
1.4 Partnering;
1.5 Others;
10
1.1 Dispute Potential Index
The Construction Industry Institute, as the result of a study into the causes of construction
disputes DPI.
DPI identifies the presence of dispute-prone characteristics on a project, evaluates them,
and reports the results to project team members
The results of such analysis can be used to take action to eliminate potential problems &
to design
1.2. Intelligent Allocation of Risks
– The most efficient & cost-effective way to structure project relationship is to assign each
risk to the party who is best able to manage or control the risk..
1.4. Partnering
11
2.1 Negotiation
A. Direct negotiation is held directly between (own internal) the very parties to the dispute.
Negotiation requires two qualities or skills:
12
– Based on a standard of legitimacy that is fair, persuasive for you, and the other
negotiator;
– One that has been achieved through effective communication,
– One where the relationship has been maintained, if not improved, and certainly not
destroyed; and
– One where the appropriate level of commitment is made at the end of the negotiation, not
at the beginning;
• Negotiation helps to save time & money for the parties in dispute.
• It creates a win-win-situation.
2.2. Mediation
B. Story Telling;
C. Determining Interests;
E. Brainstorming Options;
G. Closure;
13
A. Setting the Table
• Under this step the following actions are undertaken by the mediator.
• explain their right to use their own advisor (ex. Legal advisor);
• explain the right of the parties to walk out from the mediation process at any stage of the
mediation;
B. Story Telling
At this stage the parties are encouraged directly to tell to the mediator about the
background & contents of the dispute.
C. Determining Interest,
At this stage the mediator asks the parties more about the contents of their dispute to
determine their interests.
D. Setting out the Issue,
The role of the mediator is carefully framing the very issues to the dispute.
E. Brainstorming Options,
14
At this stage of the mediation process the parties to the dispute brainstorming possible
options to resolve the dispute.
Construction Mediation
The construction sector/industry fully shares the basic framework of the mediation
process.
The construction mediation has its own peculiarities, however.
The peculiarity may emerge due to:-
– multitude of stakeholders;
– the multi-dimensionality of the issues involved;
– the specificity of the legal & contractual framework
During the conciliation process, it is necessary for each party carefully to prepare a
document containing the following material.
15
The Facts:
• The facts mean the factual narrative of the events leading to the issues in the conciliation.
• One of the parties, usually the party initiating the process, should prepare a bundle
containing documents which can be submitted jointly, such as
The Issues:
• The legal basis supporting the case made by each of the parties should be set out in as
clear a language as possible.
• What to demand from the other party at the end of the process.
• Others;
16
• There is also a fee to be paid by the parties to the Conciliator.
3. Judgmental Dimension
– The very feature of judgmental form of dispute resolution is that the third party known as
the court judge, the arbitrator or the adjudicator decides the case before him for the
parties.
– The parties to the dispute shall have no control over the process (especially in case of the
court system) and/or the outcome of same in all the three cases.
– Under the judgmental forms of dispute resolution the following are recognized.
3.1. Adjudication
3.3. Litigation;
3.1. Adjudication
A. sole member; or
B. Three members;
The DB (Dispute Board) shall always inform itself about every development of the project in
terms of:
• Contract documentation;
• Correspondences;
17
• Project site visit;
• Periodic meetings;
3.2. Arbitration
Agree to submit the matter in dispute to the decision of a person or persons in whom they
have confidence & trust & undertake to abide by that decision.
The arbitral submission is the contract whereby the parties to a dispute entrust its solution
to a third party
Arbitration is based on contract between the parties to the construction contract & the
dispute:
The contract to resolve a construction dispute is known as agreement to arbitrate.
Advantages of Arbitration
• Procedural flexibility; (the parties in dispute are capable of designing their own process)
• Expert arbitrators;
• Multi-party disputes; (no joinder & no consolidation of third parties without their
express consent)
• Others;
18
– Institutional
– International ,Binding
The following six points constitute the framework of (international & institutional)
arbitration.
• These are:
• The court;
3.3. Litigation
Litigation takes place at the court of law having jurisdiction over the case.
The courts play here their dispute resolution role.
The procedure before the court is so rigid & not tailor made to the construction dispute
resolution.
The advantages of arbitration are all missing under litigation.
The clear disadvantage of litigation is that it being the most time consuming.
The clear advantage of litigation is that the court itself enforces its own orders &
judgments.
The role of courts, however, very important in terms of:
Enforcing an agreement to arbitrate;
Recognizing & enforcing domestic arbitral award;
Recognizing & enforcing foreign arbitral award;
Rendering judicial assistance to the arbitration process or to the settlement
agreement;
Hearing appeals against the arbitral award, if not final & appeal able; and
Setting aside of an arbitral award, if, legally qualified to be set asid
19
Self-check
1. In case of disputes the proof requirement, in addition to the relevant documentation, may also
include:-
a. Factual Witnesses;
b. Expert Opinion;
c. a &b
D. none
3. The clear disadvantage of----------- is that it being the most time consuming.
A. arbitration
b. Litigation
c. Negotiation
D. all
a. Claim
B. time extensions
C. cost overrun
D. all
20
5. The Requirements for Claim are related to:
A. Substantive requirements;
C. Proof requirements
d.all
6. Which one of the ff are the internationally recognized dispute prevention systems.
c. Partnering;
d. all
a. Arbitration; and
b. Litigation;
c. Negotiation;
d. none
a. Adjudication
b. Negotiation
c. Litigation;
d.a&c
21
11. State and explain the three phases of Claim Process?
22