Professional Documents
Culture Documents
Tracking Formulas
Tracking Formulas
Tracking Formulas
ETC = EAC - AC
When Original Estimates are flawed.
Estimate to complete (ETC) : From this point on, how much Reestimate
more do we expect it to cost to finish the project (a forecast)?
Three variations of this formula are based on conditions the
project may be experiencing ETC = (BAC - EV)/CPI
When Estimates are typical
ETC = BAC - EV
When Estimates are atypical
1.60
1.40
1.20
1.00
0.80
Cost performance
0.60 Schedule perform
0.40 index
0.20
0.00
Variances
90,000
80,000
70,000
60,000
50,000
Cost varia
40,000
Schedule
30,000
20,000
10,000
0
exes
ances
Cost variance
Schedule variance
Sr No. Program/Project Tower Region IBS Owner/PM
CPI 1 = Good. We are getting 1$ for every 1$ spent. Funds are used as planned.
CPI >1 = Good. We are getting >1$ for every 1$ spent. Funds are used better than planned.
CPI <1 = Bad. We are getting <1$ for every 1$ spent. Funds are not used as planned.
Project completion TGM Adoption
er than planned.
TGM Completeness