Professional Documents
Culture Documents
GOAL Charity: Water School Sustainable Water, Sanitation and Hygiene Project 2020
GOAL Charity: Water School Sustainable Water, Sanitation and Hygiene Project 2020
GOAL Charity: Water School Sustainable Water, Sanitation and Hygiene Project 2020
Summary
1.0 Total for General Items -
2.0 Total for Earth Works and Substructure inc slab -
3.0 Total for Superstructure inc roof -
4.0 Total for doors -
5.0 Total for Finishing -
SubTotal
18% VAT -
Total for 1 block (Sub-Total+18% VAT) -
Earth works
Excavate trenches for screen wall foundations: commencing
m3 4.9
2.1 from reduced levels : not exceeding 1.5m deep . -
2.2 Return, fill and ram selected excavated material to void m 3
1.9 -
2.3 Remove surplus excavated material from site m3 3.0 -
Excavate pit for latrine (7.2x2.46m) commencing from stripped
m3 24.0
2.4 level n.e 1.5m deep -
2.5 Ditto commencing 1.5m and n.e 3.0m deep m3 26.0 -
2.6 Ditto commencing 3.0m deep n.e 3.5m deep m3 9.0 -
Return, fill and ram selected excavated material to void for
m3 13.0
2.7 working space -
2.8 Remove surplus excavated material from site m 3
49.0 -
Allow for preparing surface below corridor, ramming hard and
Item 1.0
2.9 levelling -
Substructural foundations and walling -
230mm thick mass concrete 1:3:6/40mm aggregate in
m3 2.1
2.10 foundations trenches -
200mm thick hardcore bed under floor of corridor room
m 2
13.2
2.11 rammed hard with a metal rammer -
2.12 Place 50mm thick sand blinding over hardcore bed m2 13.2 -
1000G Polythen Damp Proof Membrane over sand blinding
m2 13.2
2.13 including 150mm end and side laps -
100mm thick mass concrete 1:3:6/40mm aggregate to bottom of
m 3
1.8
2.14 latrine pit -
Finish surface of concrete in cement/sand 1:4 mortar and 4mm
m 2
10.7
2.15 thick cement skim coat -
230mm thick substructural brickwall to screen wall in
cement/sand 1:4 mortar bonding m 2
7.8
2.16 -
230mm thick substructural brick lining to latrine pit in
cement/sand 1:4 mortar m2 58.0
2.17 -
30mm thick cement/sand 1:3 plaster to internal face of pit
lining finished smooth in cement/sand skim coat m 2
55.0
2.18 -
Apply 30mm thick cement/sand rendering (1:3) to external
faces of substructural brick wall commencing from top of slab m2 6.4
to a level 500mm below
2.19 -
Ditto to latrine pit skin wall half way round pit wall at back m2 5.1
2.20 -
Apply bituminous black paint to item 2.18 & 2.19 m2 11.5
2.21 -
Support beam -
2.16 Place 150mm thick x 230mm wide reinforced concrete beam
Grade 25 1:2:4/20mm aggregate midway between bottom of m³ 0.7
latrine and slab & ring beam mid level of pit brick wall lining
-
2.17 R-12 twisted steel bars 4 nr in beams. Allow for binding wire kg 103.0 -
2.18 R-06 tying wire at 200c/c kg 31.0 -
2.19 sawn timber formwork to beam m2 9.4 -
Page 1 of 4
GOAL charity: water School Sustainable Water, Sanitation and Hygiene Project 2020
Page 2 of 4
GOAL charity: water School Sustainable Water, Sanitation and Hygiene Project 2020
Page 3 of 4
GOAL charity: water School Sustainable Water, Sanitation and Hygiene Project 2020
5.20 Allow for excavation of soak pit 1.0m diameterx 1.5m deep,
filling with hardcore or broken bricks and other granular
material to 300mm from ground level, provision with a 1000G
polythene cover at top before placement of vegetable soil. Item 1
Allow also for the removal of extra excavated soils from site
-
Total for finishings -
Page 4 of 4