Game plan

ADC-12 @ SHYB-479 16” Hole 06/20/2014

1. P/U 16” BIT # (SMITH, GS18VEJ3, S/N PZ6713 WITH 3X14 & 3X16 NOZZLES ), AND DIR BHA
M.MOTOR/MWD /GR AS PER SCHLUMBERGER DIRECTIONS & BHA SHEET. (WITH FLOAT).
2. BHA: BIT+SDM MOTOR+FLEX JT W/ FLOAT+14 ½” STRING STAB+PONY NMDC+NM SAVER
SUB+POWER PULSE+NM SAVER SUB+NMDC+FILTER SUB+3 X 9 ½” DC+XO+SUMMIT PBL SUB+9 X 8
½” DC+DRILLING JAR+2 X 8 ½” DC+XO+15 X 5” HWDP+5” DP TO SURFACE.
3. INSTALL PBL SUB AS PER BHA. TEST SAME AS PER SUMMIT HAND. RECOVER BALLS. .
4. SHALLOW TEST FOR MWD AS PER SDM INSTRUCTIONS.
5. RIH W/ 16” BHA AND TAG CMT.
6. CHC.CONDITION MUD IN AND OUT.PRESSURE TEST CSG TO 400 PSI W/ 70 PCF MUD.
7. DRILL OUT CMT AND SHOE.
8. LOAD ACTIVE MUD WITH 40 PPB OF LCM TO CONTROL LOSSES WHILE DRILLING THIS
SECTION.
9. ONCE DRILLING AT ARUMA FORMATION(+/- 3777’)TREATING MUD SYSTEM WITH 3%
MAXGAURD AND STARCH TO REDUCE FILTERATE API BELOW 5 CC/30 MIN.

10. DRILL 16” VERTICALE HOLE TO KOP ( ± 2100’). CONT. DRILL TO CP( ± 3948’) W/ 68-
PCF SPUD MUD. DO NOT BACK REAM UNLESS IT IS NECESSARY !!!

11. LOSSES ARE EXPECTED IN THIS HOLE SECTION. PLEASE PAY ATTENTION

NOTES:
- KEEP ROP @ 30-35 FPH. PUMP RATE = 800-1000 GPM.
- RPM = 90-110 BIT WEIGHT = 25-30 K OR ACCORDING TO SLB DD.
- SWEEP HOLE W/ 30 BBLS HI-VIS EVERY 45 FT DRILLED.

*** IF TOTAL LOSSES ARE ENCOUNTERED. PICK UP ONE STD OFF BTM. KEEP PUMP MUD CAP OF 30
BBLS/ 80 PCF EVERY 30 MIN FROM ANNULUS. DROP BALL. OPEN PBL.PUMP (100 BBLS) @ 150 PPB LCM
PILL***.WAIT FOR LCM TO SOAK MEANWHILE KEEP PUMPING MUD CAP FROM ANNULUS (30 BBLS
OF 80 PCF EVERY 30 MIN )

(PREPARE 250 BBL LCM PILL @ 150 PPB READY).


-- HAVE 250 BBL 80-PCF MUD AS MUD CAP READY.

12. PUMP 30 BBLS LO/VIS 80 BBLS WT HI-VIS (MARKER PILL) & CIRC HOLE CLEAN ( MIN 2 HOLE
VOLUME)
13. POOH FOR WIPER TRIP. PUMP OUT FIRST 5 STANDS. FLOW CHECK.PUMP SLUG.. CONT. POOH TO
18-5/8” SHOE.
14. RIH TO BTM. IF HOLE PROBLEMS ARE ENCOUNTER (CONTACT COMPANY MAN)
15. PUMP 30 LO/80 WT HI VIS & CIRCULATE HOLE CLEAN HOLE VOLUME.
16. SPOT 250 BBLS HI VIS PILL MUD INTO OPEN HOLE.
17. POOH TO RUN CASING.
NOTE: PLEASE PREPARE 13-3/8” CASING & TALLY ON RACKS.
HOUSEKEEPING OF RIG.
THANKS
ARAMCO TEAM