Professional Documents
Culture Documents
06 Chapter1 PDF
06 Chapter1 PDF
CHAPTER 1
INTRODUCTION
1.1 GENERAL
accidents and loss of human lives. Level crossings are the major contributor
to Railway accidents in India next only to derailments. Between the years
2009 – 2015, there were about 349 accidents at level crossings in India.
(Dubbudu 2016).
(2) Near railway stations where detentions to road traffic are very
high on account of either shunting operations or multi-
directional receipt/despatch of trains or stabling of trains, etc.,
approval so that the project could be taken up jointly with the Central
government on cost sharing basis.
ROBs are constructed over railway level crossings (LCs). They are
constructed over the boundary controlled by the Department of Railways. The
railway portion of the ROB is usually constructed at a height of 6.525m
(Bottom of deck) from the highest rail level and is also called railway span of
an ROB. Railway span is normally flat without any gradient. The Overall
height from the proposed sill level to the proposed road level on the railway
span varies from 9m–11m. The span depends upon the width of railway
boundary available at a particular LC location. This width normally varies
from 30–100m. Railway span is constructed using composite girder deck slab
and circular or wall type column piers.
4. LS items - Rs 7500000
0.50 1% 3%
% 5% DPR
Investigation charges
Variation in depth of
foundation ,escalation and
QC charges
LS items
91%
ROB
Time delay also called timed overrun is the excess of actual time
over the estimated time of the project.
Several studies have been carried out all over the world on time
delay and cost overrun of infrastructure projects. ROB project is also a key
infrastructure project, planned to alleviate the traffic bottlenecks at the LC’s.
The studies carried out in India on time delay and cost overrun of
infrastructure projects is minimum and there are no studies carried out in
India on the time delay and cost overrun of ROB projects in India.
Within Within
Total No. Within Time Cost With Time
Category of
of Time and but with but with and Cost
Project Cost
Projects Cost Time Overrun
Overrun Overrun
Mega (` 1000
crores and - - - - -
above)
Major
(` 100 –
202 30 21 133 18
` 1000 crores
)
Medium
(` 20 –`100 22 5 0 15 2
crores )
Total 224 35 21 148 20
The above factors tend to affect the GDP of a fast growing Indian
economy.
(1) To identify and rank the factors causing time delay and cost
overrun in ROB construction projects in the Indian context.
(2) To estimate the frequency of cost overrun and the time delay
of ROB construction projects in India.
This thesis has been organised into five chapters. Chapter 1 outlines
the objectives and the need for the research. Chapter 2 provides a detailed
review of literature relating to time delay and cost overrun of infrastructure
projects and examines approaches to model development for this research
work. Chapter 3 presents the methodology of the study. Chapter 4 deals with
the data base development for this study. Chapter 5 describes the analysis of
data for quantitative and qualitative analysis. Chapter 6 presents the summary
of the research work, conclusions, limitations and scope for further research
on this area of study.