Wave-2 Makkah-RABIGH1-306 Villas

Activity ID Activity Name Original Start Finish Total 2020 2021


Duration Float Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Wave-2 Makkah-RABIGH1-306 Villas 288 01-Feb-20 31-Dec-20 0 31-Dec-20, Wave-2 Makkah-RABIGH1-306 Villas

General 288 01-Feb-20 31-Dec-20 0 31-Dec-20, General


A1020 Ph 1 -Design Mockup & Sample Approvals (90 calendar days) 79 01-Feb-20 02-May-20 1 Ph 1 -Design Mockup & Sample Approvals (90 calendar days)

A1010 Award of Contract (Issue of NTP1) 0 01-Feb-20* 1 Award of Contract (Issue of NTP1)

A1040 Ph 2 -Procurement, Mobilisation, Establishing Factory / V.O works (2 months) 52 03-May-20 01-Jul-20 1 Ph 2 -Procurement, Mobilisation, Establishing Factory / V.O works (2 months)

A1030 Approval on Ph-1 (Issue of NTP2) 0 03-May-20 1 Approval on Ph-1 (Issue of NTP2)

A1050 Access of Contractor to site (Issue of NTP3)-Construction Start 0 02-Jul-20 1 Access of Contractor to site (Issue of NTP3)-Construction Start

Contract Milestones 104 01-Sep-20 31-Dec-20 0 31-Dec-20, Contract Milestones


W1080 Completion of 10% Units --31 in 60 days 0 01-Sep-20* 0 Completion of 10% Units --31 in 60 days

W1090 Completion of 20% Units --61 in 30 days 0 01-Oct-20* 0 Completion of 20% Units --61 in 30 days

W1100 Completion of 30% Units --92 in 30 days 0 01-Nov-20* 0 Completion of 30% Units --92 in 30 days

W1110 Completion of 40% Units --122 in 60 days 0 31-Dec-20* 0 Completion of 40% Units --122 in 60 days

Engineering 45 01-Feb-20 23-Mar-20 155 23-Mar-20, Engineering


A1060 Dwgs Submission & Approvals 45 01-Feb-20 23-Mar-20 155 Dwgs Submission & Approvals

Procurement 88 24-Mar-20 04-Jul-20 155 04-Jul-20, Procurement


A1070 Procurement of Civil & MEP items 88 24-Mar-20 04-Jul-20 155 Procurement of Civil & MEP items

Construction 182 02-Jun-20 30-Dec-20 1 30-Dec-20, Construction


1BHK-195 120 02-Jun-20 19-Oct-20 1 19-Oct-20, 1BHK-195
A1120 20 villas @22 days per 2 villas 32 02-Jun-20 08-Jul-20 1 20 villas @22 days per 2 villas

A1130 20 villas @22 days per 2 villas 32 14-Jun-20 20-Jul-20 1 20 villas @22 days per 2 villas

A1140 20 villas @22 days per 2 villas 32 25-Jun-20 01-Aug-20 1 20 villas @22 days per 2 villas

A1150 20 villas @22 days per 2 villas 32 07-Jul-20 12-Aug-20 1 20 villas @22 days per 2 villas

A1160 20 villas @22 days per 2 villas 32 19-Jul-20 24-Aug-20 1 20 villas @22 days per 2 villas

A1170 20 villas @22 days per 2 villas 32 30-Jul-20 05-Sep-20 1 20 villas @22 days per 2 villas

A1180 20 villas @22 days per 2 villas 32 11-Aug-20 16-Sep-20 1 20 villas @22 days per 2 villas

A1260 20 villas @22 days per 2 villas 32 23-Aug-20 28-Sep-20 1 20 villas @22 days per 2 villas

A1270 20 villas @22 days per 2 villas 32 03-Sep-20 10-Oct-20 1 20 villas @22 days per 2 villas

A1190 15 villas @22 days per 2 villas 30 15-Sep-20 19-Oct-20 1 15 villas @22 days per 2 villas

2BHK-74 61 23-Sep-20 02-Dec-20 1 02-Dec-20, 2BHK-74


A1200 20 villas @24 days per 2 villa 34 23-Sep-20 01-Nov-20 1 20 villas @24 days per 2 villa

A1210 20 villas @24 days per 2 villa 34 05-Oct-20 12-Nov-20 1 20 villas @24 days per 2 villa

A1280 20 villas @24 days per 2 villa 34 17-Oct-20 24-Nov-20 1 20 villas @24 days per 2 villa

A1220 14 villas @24 days per 2 villa 31 28-Oct-20 02-Dec-20 1 14 villas @24 days per 2 villa

3BHK-34 41 05-Nov-20 22-Dec-20 1 22-Dec-20, 3BHK-34


A1230 20 villas @ 26 days per 2 villa 36 05-Nov-20 16-Dec-20 1 20 villas @ 26 days per 2 villa

A1240 14 villas @ 26 days per 2 villa 31 17-Nov-20 22-Dec-20 1 14 villas @ 26 days per 2 villa

4BHK-3 31 25-Nov-20 30-Dec-20 1 30-Dec-20, 4BHK-3


A1110 3 villas @ 28 days per villa 31 25-Nov-20 30-Dec-20 1 3 villas @ 28 days per villa

Project Closeout 0 30-Dec-20 30-Dec-20 1 30-Dec-20, Project Closeout


A1250 Closing of Project 0 30-Dec-20 1 Closing of Project

Remaining Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 1
Actual Work Critical Remaini...