Costing-Landscaping Works (Example)
Costing-Landscaping Works (Example)
Costing-Landscaping Works (Example)
A Cultivating soil by hand, surface ground, 150mm deep, evenly graded to finish levels to a fine tilt.
B Surface application by hand, approved brand commercial fertilizer, general surfaces of cultivated
soil at a rate of 800gm/m2.
C Spot turfing; axonopus compressus; size 150mm x 150mm x 50mm thick, 300mm centres;
horizontal surfaces; pegged with wooden pegs where necessary; watering, weeding, cutting, and
additional fertilizer; maintaining for the whole of the contract period after turfing.
Price Data
Material
-Commercial fertilizer – RM75/bag (Weight per bag = 50kg)
-150mm x 150mm x 50mm thick, axonopus compressus – RM0.50/pc
-Wooden peg– RM0.50/bundle (200 nr/bundle)
Labour output
-Cultivating soil (150mm thick.) – 50m2/hr
-Unloading fertilizer -120bags/hr
-Laying turf (spot) – 33.33m2/hr
-Spreading fertilizer – 100m2/hr
Labour Wages
-Skilled labour – RM8.00/hr
-Unskilled labour – RM6.00/hr
-Gang ratio: 1:2
Maintenance items
-Rubber hose–700m/hectare @RM70/roll [30m per roll].
-Additional fertilizer: 2500kg/hectare/cycle [Frequency = once a month]
-Remove weed growth– 100m2/hr [frequency = once a month]
-Cutting turves by machine-70m2/hr [frequency = once month]
-Hire grass cutting machine (including operator and fuel): 100m 2/hr
-Labour for spreading fertilizer –200m2/hr [Frequency: once a month]
-Labour for watering turves –200m2/hr [Frequency: twice daily]
A. Material
C. Labour
A. Material
C. Labour
[Take area of turfing 100m2 – Construction period 8 months, DLP 6 months, turfing
commence 2 months before completion date].
A. Material
C. Labour
Material
i. Rubber hose
Labour
Allow
Overheads – 8% RM2.01