What to check?
Structural steel
- Approved make.
- Verification of mill TC for correlation (or) test w.r.t. Code / specification
contractually agreed.
- Visual inspection –pits, corrosion, cracks on the surface, deformities
- Dimensional inspection- Size, thickness, comparing w.r.t. Rolling margin.
- Colour coding of materials (if required).
- Test certificates for special tests (Other than routine tests), if contracted.
Fasteners
-Approved make
- Verification of MTC for correlation (or) test w.r.t. code / specification contractually
agreed.
- Dimensional inspection- Size, Thread Quality, Crack by visual.
Paint
- Contracts review: - whether the purpose of paint will solve the purpose?
e.g. Heat resistant, acid resistant paints are required?
-Primer –approved brand, Conformity to contractual / code provision
- Paint (Finish coats)-Approved brand, Conformity to contractual / code provision,
Approved shade.
- Check expiry dates for NDT liquids
- Verify the TC for Electrodes.
Identification and preparing NDT requirements and approval from customer, if contractually
agreed upon.
Fabrication inspection reports
Straightness, bending in linear & lateral defect free due to cutting & welding process (with in
tolerance limits).
Pre-heat temperature, inter-pass cleaning.
Welding inspection like thickness of welding, length of welding.
Free form Blow holes, under cuts, cracks, etc.
Welding joints check as per customer specification.
NDT records.
Identification marks of structures and match marks, if any.
Final dimensions
Fabricated section size, length w.r.t. Acceptable limits.
Positions & size of holes (for bolting) in base plate, gusset plates, brackets and any other
connecting member in particular structures.
Visual appearance
Cut portions in gas cutting.
Welding appearance.
Edge finishing.
Free for Temporary tack welding during fabrication.
Drill hole appearance & Finishing.
Bracket & Gusset angles and finish.
Surface preparation for painting
Surface preparation method approval (Using wire brush by manual, mechanical brushes using
buffing machine, sand blasting, etc.).
Checklist before applying primer.
Records as per approved methods (It may be clubbed in painting records)
Priming coat
Painting of approved paint as per contract review.
Thickness of primer.
No of coats (If two or more coats).
Foundation clearance (post concrete scheme)
Receiving post-concrete survey schemes from civil department.
Checking the same before erection.
Erection schemes and methodology
Preparing method statement and taking approval from customer, if contracted.
Preparing checklist during and after erection.
Following schemes & Erection records
An erection record includes guy rope arrangements, checking safe working loads of slings, D-
shackles, temporary supports, jigs, etc.
Keeping guy ropes up to proper bracing of permanent structures.
Keeping some guys up to Grouting.
Bolt tightness to avoid shear in any members.
Page 3 of 3
PRODUCT QUALITY CHECK
Quality Management STEEL STRUCTURES