MS-Project LAB 1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

ID TaskTask Name DurationStart Finish

Mode E M B
Dec 2, '20 Dec 9, '20 Dec 16, '20 Dec 23, '20 Dec 30, '20
M W F S T T S M W F S T T S M W
1 Start the Project 0 days Wed 1/1/20 Wed 1/1/20 1/1
2 RD-Road Works 16 days Wed 1/1/20 Fri 1/24/20
3 RD-10 7 days Wed 1/1/20 Fri 1/10/20
4 RD-20 4 days Mon 1/13/20 Thu 1/16/20
5 RD-30 4 days Wed 1/15/20 Mon 1/20/20
6 RD-40 1 day Mon 1/20/20 Mon 1/20/20
7 RD-50 2 days Tue 1/21/20 Wed 1/22/20
8 RD-60 2 days Thu 1/23/20 Fri 1/24/20
9 FW-Finishing Works 2 days Thu 1/23/20 Fri 1/24/20
10 FW-10 1 day Thu 1/23/20 Thu 1/23/20
11 FW-20 1 day Fri 1/24/20 Fri 1/24/20
12 LS-Land scaping 4 days Mon 1/27/20 Fri 1/31/20
13 LS-20 2 days Mon 1/27/20 Tue 1/28/20
14 LS-10 4 days Mon 1/27/20 Thu 1/30/20
15 End the Project 0 days Fri 1/31/20 Fri 1/31/20

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Summary Manual Task Critical
Date: Sat 12/28/19
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 1
B E M
Dec 30, '20 Jan 6, '20 Jan 13, '20 Jan 20, '20 Jan 27, '20 Feb 3, '20 Feb 10, '20 Feb 17, '20 Feb 24, '20
W F S T T S M W F S T T S M W F S T T S M W F S T T S M W
1/1

Dozzer,Forman
Dozzer,Forman,Gravel[1 m3]

Excavator,Forman,Signs[1]
Forman,Marker Machine,Paint[1 Galon]

Forman,Seeder,Seeds[1 Pcs]

1/31

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Summary Manual Task Critical
Date: Sat 12/28/19
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 2
B E M
Feb 24, '20 Mar 2, '20 Mar 9, '20 Mar 16, '20 Mar 23, '20 Mar 30, '20 Apr 6, '20 Apr 13, '20 Apr 20, '20
W F S T T S M W F S T T S M W F S T T S M W F S T T S M W

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Summary Manual Task Critical
Date: Sat 12/28/19
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 3