Work Instructionfor Roll Assembly 9980
Work Instructionfor Roll Assembly 9980
4 Mount both side chocks on the robot operator side chock placed towards PPC yard and drive side chock placed towards ECR Building..
5 Set jack bolt of robot for alignment of non drive side chock.
6 Lock both side chocks with Chock clamping bracket and ensure robot is in fully open condition.
7 Put roll on robot by EOT crane and ensure the alignment of roll with respect to Chocks.
10 Put the lock ring towards drive side chock and lock it with spacers & fastners.
13 Tight operator sides thrust locking fastners at 435 N-M using torque wrench.
15 Take out assemble roll by EOT and put it on roll basket and assemble strippers.