VISAKH REFINERY

FORMAT OF INSPECTION WORK LIST


TECHNICAL DEPARTMENT Doc. No. OCP/TSD/FR/305/Rev.2
Rev. Date : 16-Jan-02
(Ref. Pro.:OCP/TSD/PR/204)
Page 1 of 1

WORK LIST No. : 18-912597 IWL.DESC.: NHT: T&I-2019 - IWL for Piping Loop #67 Date: 10/06/2018 15:31
LOCATION : NHT_PIPING LOC.DESC.: NHT Unit piping INSP. BY: B M JEELANI
Equipment : REF:
Visual Inspection and UTG of Piping loop # 67 (2" from 72-V-08 to CBD & OWS ) was
carried out. The following are the observations and recommendations.

Sl No. LOCATION/ITEM OBSERVATION RECOMMENDATION

10 Piping Loop #67 from 72-V-08 to a) Paint failure was observed on the 2" dia line. 1.Carry out painting of the 2" dia line
CBD /OWS line over approx. 4mt length.
2.Carry out hydro test of the line @ 4
kg/cm2 pressure

____________________________
HEAD-INSPECTION

Page 1 of 1 Saturday, October 06, 2018