VISAKH REFINERY

FORMAT OF INSPECTION WORK LIST


TECHNICAL DEPARTMENT Doc. No. OCP/TSD/FR/305/Rev.2
Rev. Date : 16-Jan-02
(Ref. Pro.:OCP/TSD/PR/204)
Page 1 of 1

WORK LIST No. : 18-912594 IWL.DESC.: NHT: T&I-2019 - IWL for Piping Loop #68 Date: 10/06/2018 15:32
LOCATION : NHT_PIPING LOC.DESC.: NHT Unit piping INSP. BY: B M JEELANI
Equipment : REF:
Visual Inspection and UTG of Piping loop # 68 (3"/2" from 72-V-06 to 72-LIC-1801 I/L
& CBD ) was carried out. The following are the observations and recommendations.

Sl No. LOCATION/ITEM OBSERVATION RECOMMENDATION

10 Piping Loop #68 from 72-V-06 to Visual Inspection and UTG of Piping loop was carried out. General 1.Carry out hydro test of the line @ 36
72-LIC-1801 I/L & CBD line condition of pipeline was found satisfactory. kg/cm2 pressure

____________________________
HEAD-INSPECTION

Page 1 of 1 Saturday, October 06, 2018