Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

1.

0 SCOPE
Establishes the Project Quality plan, required to achieve the Quality requirements as per Project
requirements with in scope of work applicable to all works undertaken for “EPC WORKS OF LIGHT
GAUGE STRUCTURE OF FIRE STATION, STORE AND WORKSHOP BUILDING AND OFFICE BUILDING
AND PRAYER HALL BUILDING”.

2.0 PURPOSE
To ensure that Quality Assurance and Quality Control activities are Planned and established to meet the
requirements of the company’s Quality Policy, Quality objectives and Customer/Project requirements and
to verify that the project team is performing its task in accordance with,

a) Contract scope of work,


b) regulatory requirements (if applicable) and codes of practice,
c) Specific project procedures/Specification.

3.0 REFERENCES
3.1 QMS Manual – MNT/QSM/01

3.2 ISO 9001:2015: Quality Management Systems-Requirement

4.0 QUALITY MANAGEMENT SYSTEM

4.1 ISO Certification

MNT’s Quality Management System was audited and originally certified in 2018 by BUREAU VERITAS
certifications, to comply with the quality assurance requirements of ISO 9001: 2015

The scope of MNT’s accreditation covers: ‘For CIVIL CONSTRUCTION WORKS’.

4.2 Quality Management System

MNT’s Quality System is developed around a Quality Assurance Manual is based on ISO 9001:2015,
which addresses the relevant elements of ISO 9002. This Quality Assurance Manual is supported by
detailed Departmental Quality System Procedures are intended to comply with all the prescriptions of
ISO 9001:2015. In turn these Quality System Procedures are supported by Operating Quality Procedures
required for different activities in the process control.

MNT has developed Operating Quality Procedures for all essential activities involved in “Civil Construction
Works” and these operating procedures will be modified, if and as required, to meet the specification
requirements of particular projects.
4.3 Project Quality Management

The Project Manager is the functional head of QA/QC Department. He has overall responsibility for:

 Coordinating and harmonizing quality efforts between operating entities.


 Representing the company regarding quality matters.
 Participating in Quality Management Steering Committee activities.
 Verifying that the quality system is applied to work performed and that personnel are
trained in its use.

Inspections, audits, checks and testing is handled by the Project Manager /QA QC Engineer. He has the
responsibility on the project level to:

 Aid in the development of systems that:


 Identify and record quality problems
 Control further processing, delivery, or installation of non-conforming product
until the deficiency or unsatisfactory condition has been corrected.
 Initiate, recommend, or provide solutions through designated channels.
 Verify the implementation of solutions.
 Take action, as deemed appropriate, in the event of serious deviations from specified
quality requirements. The assurance and control of essential activities are carried out by
MNT’s Project Manager or QA QC Engineer with the assistance of QC Engineer(s) from
either MNT or their subcontractors, depending on project scope of work.

4.4 Quality Control

MNT’s approach to quality control is summarized as follows:

 Acceptable levels of quality are to be clearly established Through ITP before the start of
Construction Works and are to be consistently applied throughout the project.
 Project Management and Production department will fully support the principles of
quality control and will ensure that quality levels are maintained.
 Project supervision will understand and accept the philosophy and techniques of quality
control and will be dedicated to achieve the quality levels established for the Project.

Quality control will not be restricted to supervision and monitoring of the Project and performance only.
As consumable materials are received in MNT ware house prior to commencement of project activities,
receiving inspection will be conducted to ensure that the items received conform to specification, Delivery
Note and Purchase Order requirements. Any discrepancies discovered in the inspection will be referred
back to the Procurement dept., personnel for follow-up and resolution with the sub vendor.

The project team management will bear primary responsibility for ensuring that quality control is
maintained during Construction of the Project. They will be responsible for receiving, handling and
interpreting all of the engineering drawings, specifications and for monitoring construction work for
compliance to the intent. Project’s entire team will share this responsibility during the daily monitoring of
the work under each individual’s direction, through visual inspection to ensure quality workmanship and
through observation and confirmation that work forces are applying appropriate construction methods.
5.0 PROJECT MANAGEMENT / PROJECT CONTROL
5.1 The concept for project control is a planned, controlled and disciplined approach, which
emphasizes and requires the following actions:

 Early and timely decisions on specific project requirements


 Critical path planning and schedules based on plan of construction and equipment and
materials availability.
 Early and continuous construction involvement.
 All equipment and materials needed are identified, scheduled and controlled.
 Firm control of changes
 Prompt and effective reporting on all aspects of the Project for management analysis of
performance and the initiation of action where required.

5.2 Schedule Planning and Control

a) Major Objectives

The objective of the schedule planning and control will be to meet the contractual time limits and
to move the Project as rapidly as possible. Namely, the major objectives of the schedule control
function will be to:

 Establish and maintain the Project Master Schedule, highlighting the key project
milestones and project parameters necessary to attain the overall project schedule
objectives.
 Ensure that the Project Master Schedule and other control scheduled are effectively
communicated throughout project organization in a timely manner.
 Identify and predict adverse schedule situations as far in advance of the occurrence as
possible to allow corrective action to be taken.
 Provide a basis for sound project management decisions, which will enable timely
execution of the Project and maintain it continuously with fabrication and construction
requirements.

b) Basic Philosophy

Schedule control will be developed in a step wise manner, parallel with the development of the
project scope definition. The schedule control approach will be broken down into the following
three distinct phases:

 Overall Planning
 Detailed planning
 Monitoring, reporting and control.

The objective of overall planning phase will be to establish an overall time schedule, which clearly
establishes project key milestones (hard and soft) as specified by and agreed to with the
Company.
The objective of the second phase will be to develop the detailed work plan, which will be
adequate for controlling and tracking the progress of the Project. This will also match the release
of drawings and delivery of materials to the required path of construction. Once the planning
work has been completed, control will be maintained by monitoring and comparing actual
accomplishment against the plan, making adjustments and forecasts. It will be vital to successful
completion of the Project to identify potential problem areas as early as possible by close
monitoring so that corrective action can be taken before a problem becomes serious .

c) Organization

The schedule planning and control function will be under the control of the Project Manager who
will be staff to the COO operation. Regarding this function, the Project Manager will:

 Prepare the schedule control plan and schedules


 Provide day-to-day monitoring\ reporting and coordination among disciplines.
 Coordinate with Company on schedule and progress matters through the COO
operations.
 Track and report the status of problem areas until they have been resolved.
 Provide Company and COO-operations with accurate and timely report.

Monitoring, Reporting and Control:--

As soon as the detailed schedule planning is completed, the schedule control operation will switch to the
monitoring, reporting and control phase. This phase will extend from the completion of the detailed
planning until the completion of the Project. The objective of this phase will be to monitor, track and
control the progress of the Project using a variety of schedule and progress related documents that will
identify adverse trends or schedule exceptions.

To obtain current project status of construction, project review meetings will be conducted along with
Plant Managers so that problems can be identified and resolved as early as possible. If the problem
cannot be resolved at Project level, it will be brought to the attention of COO -Operations.

d) Progress Measurement and Control

In order to evaluate current project status and forecast future trends, the progress of each phase of the
Project will be measured and reviewed by making a comparison between actual progress and planned
progress.

6.0 CONTROL OF PROJECT QUALITY PLAN


The Project Manager or QA/QC Engineer develops project quality plan. Project Manager reviews the
project quality plan (PQP) and submits to client for approval. QA/QC Engineer in conjunction with
Project Manager shall identify and distribute to concerned operational personnel required to receive the
PQP as per section. 11 of this document.

Master lists will be updated by QA/QC Engineer giving Date, Revision, Title, Recipient Name, and Date
Approved as shown in section 7.4 of this PQP.
It is the responsibility of all department heads to ensure:

A.That each Project Quality Plan retained in their department is immediately updated with the
latest Revision.

A.That the QA/QC Department is notified of any recommendations to modifications of


controlled plans.

c. To recommend any changes that will improve quality efficiency control within their
Department.

The Project Manager or Engineer shall be responsible for the control, revision and distribution of
PQP.

Documents relevant to control of Project Quality Plan as per ref. Of QMS document #
MNT/QSM/01 -------Control of Document

7.0 GENERAL

7.1 OBJECTIVES STATEMENT


7.1.1 General Statement on Quality Objectives.

The assurance of Quality is fundamental to all work undertaken by the (MNT) and is practiced by
all personnel in their daily activities.

Quality is enhanced by working in a systematic method to formalized procedures designed to


eliminate the occurrence of deficiencies.

It is the responsibility of the Management to ensure that these procedures shall be compiled by
persons with adequate qualifications, and integrated into the requirements of the regular working
methods, which shall be clearly defined and documented.

MNT Operating Quality System Procedures shall be used as guidelines in the control of project
specific areas such as procurement, Nonconformance’s, Training, Document Control, Inspection,
Quality Records, etc.

The Management of the MNT LLC shall review, at a minimum interval of twelve months, the
quality management system to ensure its continuing suitability and effectiveness.

It shall be the responsibility of the QA/QC Engineer to monitor through audit the quality
management system in order to verify the ongoing application of the necessary systems and
procedures.

7.1.2 Overall Statement on Quality Objectives

Management of the MNT LLC establishes the Quality Objectives in support of the Quality Policy.
These objectives are reviewed during the annual Management Review committee meetings and
ratified or modified to answer the requirements of the Company as well as of the Customer .
The Quality Policy of the AL MAWAKAB NATIONAL TRADING AND CONSTRUCTIONN COMPANY
LLC is supported by the following quality objectives:

a) To ensure Customer satisfaction through quality of its products and services

b) To develop people through training and modern technologies

In order to familiarize all MNT employees in accordance with the system. The
MNT quality Policy is prominently displayed at all locations where activities are
ongoing.

All MNT employees are expected to perform in accordance with this system and
are encouraged to identify and suggest ways to improve this system.

7.2 SCOPE OF WORK

Scope of work is “EPC WORKS OF LIGHT GAUGE STRUCTURE” at site for a RAS MARKAZ CRYDE
OIL PARK PROJECT (PHASE 1), RAS MARKAZ, DUQM.

7.3 QUALITY SYSTEM MANUAL & OPERATING QUALITY PROCEDURE REFERENCE

The following documents have been used in formulating this Project Quality Plan as mentioned
in section 7.1.1 of this project quality plan.

A) MNT Operating Quality Procedure Document # MNT-QC-PR-01

7.4 DOCUMENT CONTROL, RECEIPT AND ISSUING PROCEDURE

All Quality documents (PQP, QCP (ITP) & Quality Procedures) relating to this contract will be
retained in the custody of the QA/QC Engineer.

A distribution matrix for project all specific quality documents will be maintained by QA/QC
Engineer.

8.0 ORGANIZATION
The project will be carried out by MNT. Whereas MNT will have onsite allocation of staff and
management for the Project, MNT will have own staff, labor and adequate management allocated
and distributed to the Project for their respective works organized in hierarchical order. Allocation
and organization of personnel may be subject to changes to Suit project requirements

8.1 ORGANIZATION CHART

Organization Chart for Project.


Project Manager

Project Engineer Project Coordinator

QA QC Engineer Site Engineer HSE Officer

MEP Engineer Surveyor Store Keeper

8.2 REPORTING RESPONSIBILITIES

8.2.1 COO-Operations

He shall be the authorized representative of the Contractor. They shall have overall responsibility for all
aspects of the work from start to finish, including construction, safety, quality and planning. The COO-
Operations shall report directly to the General Manager.

8.2.2 Project Manager

Project Manager shall be directly responsible to the COO-Operations for all aspects of Planning,
Procurement & Construction Coordination. He is the focal point for field liaison with the project
Representatives.

8.2.3 Project Engineer

The Project Engineer is directly responsible to the Construction for overall project through his Managers&
Supervisors. He has direct control of all site personnel, equipment and material movements. He shall
coordinate with QA/QC Engineer to implement the quality requirements of the project. The Project
Engineer shall directly report to Project Manager -Operations.

8.2.4 MEP Engineer

Responsible for planning and design in the area of Mechanical, Electrical and Plumping system including
developing policies standard, Method Procedure and evaluation tools for MEP matters along with
prepare, review drawing, specification and cost estimates for the MEP.
8.2.4 QA/QC Engineer

Responsible for compilation and maintenance of QCP's as well as revision and distribution of the project
quality plan. Additional responsibilities include the calibration control of equipment/instruments, NCR's,
verification and availability of procedures, ITP, etc. He shall supervise the QC’s and ensure that the work is
carried out in accordance with Project requirements or relevant international standard as applicable.

8.2.5 HSE Officer

Responsible for maintaining the overall safety and health requirements established by the concern, Safety
standards at their particular work locations he is in charge of. Organize/conduct HSE training, facilitate
implementation of HSE requirements and monitor the activity regularly.

8.2.6 Store Keeper

Material Controller shall be responsible for receipt and issue of materials and goods ensuring that correct
identification, registration, storage and preservation takes place. He shall be responsible for all material
files and records.

9.0 RECORDS / FORMS


9.1 Each format shall have a unique document number .All Report Formats will be attached along
with relevant Operating Quality Procedures.

9.2 Whenever a new format is required, the QA/QC Engineer will develop the format in
consultation with the concerned personnel and subsequently submitted to the Project Manager
for review and approval.

10.0 PROJECT SPECIFIC QUALITY CONTROL PLAN


10.1 Quality Control Plans

QA/QC Engineer/Supervisor shall monitor the performance of all tests undertaken to establish
conformance with Quality Control Plan requirements, duly assisted by Engineer(s) responsible for relative
activities.

11.0 CONSTRUCTION METHOD STATEMENT /PROCEDURE


(Ref. Procedure Document # MNT-QC-PR-01)

The method statement/procedure gives a brief description of the steps taken prior to and during the
Construction phase of the project. The operating Quality procedures and quality control plans
incorporated in the project quality plan gives detailed description of the methods used to achieve
compliance to the Project specifications and relevant international standard requirements.

You might also like