Commercial Management of

Construction Assignment
Assignment 1.

Reference CPWD –Plinth Area Rate (PAR). Derive the estimated cost of construction of the
following works as on April 2017, you may assume any missing data but write down
assumptions.

1. Construction of a 10 storey residential building in a one acre plot with a built up area of
10,000 M2 and specification as per Annexure-V in Delhi

Group-1= Construction of a 10 storey residential building in a one acre plot with a built up area of 10,000 M2 and specification as per Annexure-V in Delhi.

Plot Area 1 Acre = 4046.86 SQM


No of Flats
Constuction Area in SQM 10,000 Per Floor Per Flat Total
per floor
Constuction Area in SFT 107600 10760 1076 10 100
Floor To Floor Height 2.9m
Plinth Area 1219
Per Floor 1000Sqm

Estimated Cost/Sqm
AMOUNT
Sr. No. Description of Work UNIT Area in Sqm % on BUA as per PAR ASSUMPTIONS
(Rs/Sqm)
Total for Site Enabling works…(A)
A SITE LEVELLING Sqm 4,047 95 384,452 PAR Annex I
B RCC WORKS as per PAR Annex V Sqm 10,000 16,820 168,200,000 PAR Annex V 1,563.20
TOTAL for Civil + Enabling works ...(A+B) 16,915 168,584,452 1,572
C FINISHING WORKS
1 PLUMBING & SANITARY Sqm 10,000 12.25% 2,060 20,604,500 % of RCC cost
2 EXTERNAL SERVICES CONNECTION Sqm 10,000 5.25% 883 8,830,500 % of RCC cost
3 INTERNAL ELECTRICAL INSTALLATIONS Sqm 10,000 12.75% 2,145 21,445,500 % of RCC cost
4 PASSANGER / STRECHER LIFT Sqm 10,000 - 370 3,700,000 PAR
5 FIRE FIGHTING with Sprinkler System Sqm 10,000 - 750 7,500,000 PAR
6 OTHER FINISHES Sqm 10,000 - 550 5,500,000 Assumed

TOTAL FOR FINISHING….(B) 6,758 67,580,500


Project Total….(A+B)…. COST/ SQM 23,673 236,730,500
Project Total….(A+B)…. COST/SFT 2,200

Page 1 of 6
Akshata S Parvatikar
Commercial Management of
Construction Assignment

Page 2 of 6
Akshata S Parvatikar
Commercial Management of
Construction Assignment
`

Page 3 of 6
Akshata S Parvatikar
Commercial Management of
Construction Assignment

Page 4 of 6
Akshata S Parvatikar
Commercial Management of
Construction Assignment

Assignment 2

Reference CPWD Analysis of Rates; find out the rate analysis of following for Delhi. Assume any
missing information:

Group-1= Cost of M50 RCC (1:0.6:1.2)


Volume Of Cement = 1 X 1.54 0.55 cum 0.55

1+0.6+1.2
Volume of 1 cement Bag = 0.0347cum 0.0347

No. Of Bags = 0.55/0.0347 15.85014409 16 Bags 0.8 Tonne

Volume of Sand = 0.6x1.54 0.924 0.33 Cum

1+0.6+1.2 2.8

Volume of Aggregates = 1.2X1.54 1.848 0.66 Cum


1+0.6+1.2 2.8

Steel Estimation = 2.5 X 7850 196.25 Kg 0.19625


Assume 2.5% for Column 100 x 1 196.25

Labours
Mason 0.37 days

Labour 5.55 days


Barbender 100kg/day
Coolie 1.88 days

Page 5 of 6
Akshata S Parvatikar
Commercial Management of
Construction Assignment
Code Description Unit Quantity Rate Rs Amount Rs
Details of Cost of 1 cum Material
MATERIALS
Stone Aggregate (Single size) :
0 295 Cum 0.396 1350 534.60
20 mm nominal size
Stone Aggregate (Single size) :
0 297 Cum 0.264 1350 356.40
10 mm nominal size
Carriage of Stone aggregate below
2202 Cum 0.66 103.77 68.49
40 mm nominal size
0 982 Coarse sand (zone III) Cum 0.33 1350 445.50
2203 Carriage of Coarse sand Cum 0.33 103.77 34.24
1004 Average rate of Mild steel round bars for reinforcement Kg 196.25 45 8,831.25
0 367 Portland Cement (0.2833 cum) Tonne 0.8 4940 3,952.00
2209 Carriage of Cement Tonne 0.8 92.24 73.79
LABOUR -
0 155 MASON Days 0.37 709 262.33
0 114 BELDAR Days 5.55 558 3,096.90
0 116 FITTER Days 1.9625 738 1,448.33
0 101 BHISTI Days 0.9 617 555.30
Hire charges of Concrete Mixer
000 2 Days 0.07 800 56.00
0.25 to 0.40 cum with hooper
00 12 Vibrator(Needle type 40mm) Days 0.07 370 25.90
9999 Sundries LS 14.3 2 28.60
0 115 Coolie Days 1.88 558 1,049.04
TOTAL A 20,818.67
Add 1 % Water Charges ( A) 208.19
Total B 21,026.86
Add GST ( Multiply by 0.1405) 2,954.27
TOTAL C 23,981.13
15% on COHP (C) 3,597.17
TOTAL ( D) 27,578.30
1 % Edu Cess on D 275.78
TOTAL ( Cost of per 1 cum RCC) 27,854.08

Page 6 of 6
Akshata S Parvatikar