Professional Documents
Culture Documents
Capital Budget 1
Capital Budget 1
❖Growth
❖Risk
❖Funding
❖Irreversibility
❖Complexity
Capital budgeting process
❑ The major process in capital budgeting process includes
d. Implementation
Annual
Machine Revenue Operating cost EBDT Depreciation
Old $150,000 $70,000 $80,000 30,000
New 180,000 60,000 120,000 50,000
1. independent projects
3. contingent projects.
1. Independent projects
➢ are projects whose cash flows are unrelated or independent
of the other.
0 1 2 3 4 5
1. It is simple to calculate.
✓ You may reject projects that have large cash flows in the
outlying years that make it very profitable.
NPV=118.7829-100=18.78287
Con’t…
Example 2: Given the following cash flow, and investors
required rate of return (K) is 10%
Investment initial cost CF1 CF2 CF3
A Br 100 10 60 80
B Br 100 70 50 30
Compute the NPV if,
(a) Project A and B are independent projects.
(b) Project A and B are mutually exclusive.
(C) Comment on the Decision rule.
Sol: A=NPR 18.78(see slide 35)
B) 70/1.1+50/1.21+30/1.331=127.49
=127.49-100=27.49
C) If independent both, because NPV> 0
If mutually exclusive, Project “B”, because highest NPV
Evaluation of the NPV Method
• NPV is most acceptable investment rule
for the following reasons:
❖Time value
❖Measure of true profitability
❖Value-additivity
❖Shareholder value
• Limitations:
– Involved cash flow estimation
– Discount rate difficult to determine
– The NPV is expressed in absolute terms rather than relative
terms and hence does not factor is the scale of investment.
– The NPV does not consider the life of the project correctly .
3. Internal rate of return
➢ Internal rate of return : is the discount rate at which the
NPV value equals zero.
➢ This rate shows that the PV cash flows for the project
would be equal to the PV of its cash out flows.
39
Calculation of IRR
1 N P V P r o file
D is c o u n t
2 C a s h F lo w r a te NPV
3 -2 0 0 0 0 0% 1 2 ,5 8 0
IR
4 5430 5% 7 ,5 6 1
R
5 5430 10% 3 ,6 4 9
7 5430 16% 0
8 5430 20% ( 1 ,9 4 2 )
9 5430 25% ( 3 ,9 7 4 )
F i g u r e 8 .1 N P V P r o f i l e
NPV Versus IRR
Which Method is better: the NPV or the IRR?
The NPV is superior to the IRR method for at least
two reasons.
1. Reinvestment of Cash flows: The NPV method
assumes that the projects cash in flows are
reinvested to earn the hurdle rate; the IRR
assumes that the cash inflows are reinvested to
earn the IRR of the two. NPV’s assumption is
more realistic in most situations since the IRR
can be very high on some projects.
2. Multiple Solutions for the IRR: It is possible
for the IRR to have more than one solution. If
the cash flow experience a sign change, the IRR
method will have more than one solution.
4. Profitability index(PI)
✓ PI is the ratio of the present value of cash flows
(PVCF) to the initial investment of the project.
✓ Some times they are called benefit cost ratio
✓ It compares the present value of future cash inflows
with the initial investment on a relative basis.
✓ It is used as a means of ranking profits in
descending order of attractiveness.
PVCF
PI =
Initial investement
Con’t….