Klamath Marsh Mapping Project - FWS - DRAFT Work Estimate Estimated Hours Staff Hourly Rate Budgeted Cost 1. Field Work Recon Field Visit (One Week)
Klamath Marsh Mapping Project - FWS - DRAFT Work Estimate Estimated Hours Staff Hourly Rate Budgeted Cost 1. Field Work Recon Field Visit (One Week)
1. Field Work
Image prep for polygon processing (tile imagery, texture from pan?) 8 JM $100.00 $800.00
Polygon selection for field sampling and accuracy assessment (for FWS) 8 DW $100.00 $800.00
Plots for field sampling and accuracy assessment (for FWS) 8 DW $100.00 $800.00
Classification and evaluation 80 JM $100.00 $8,000.00
40 DW $100.00 $4,000.00