Professional Documents
Culture Documents
Sagar Technical Seminar
Sagar Technical Seminar
By:
1. HISTORY
2. INTRODUCTION
5. LITERATURE SURVEY
6. CASE STUDIES
7. REFERANCES
1. HISTORY OF OFFSHORE STRUCTURES
INTRODUCTION
1. Fixed Platforms
• Steel template Structures
• Concrete Gravity Structures
2. Compliant tower
• Compliant Tower
• Guyed Tower
• Articulated Tower
• Tension Leg Platform
3. Floating Structures
• Floating Production System
• Floating Production, Storage and Offloading System
Fixed Platforms
The fixed type of platform shall exhibit a low natural period and deflection again
environmental loads.
• Compliant Tower
• Guyed Tower
Ø consists of a narrow, flexible tower and a piled
Ø extension of complaint tower with guy wires
foundation that can support a conventional
tied to the seabed by means of anchors or piles
deck for drilling and production operations
Ø minimises the lateral displacement of the
Ø usually used in water depths between 300m
platform topsides
and 600m.
Sergio Sánchez et Foundations in Journal of marine Monopiles are the most used
al Offshore Wind Farm science and foundations in shallow (0–15 m) and
(2019) engineering intermediate depths (15–30 m).
Jacket and tripod structures remain
as strong competitors to monopiles
when the seabed depth is higher than
30 m.
Torgeir Moan et al Offshore Structure ASCE fatigue analysis,static and dynamic
(2016) analysis is carried out in design of
foundatio Long-term wave climate is
the starting point fatigue analysisyn
and sea loads and load effects are
incresed by considering several
factors in ssuming required factor of
CASE STUDIES :
1.Case Study of Offshore Pile System Failure in Hurricane Ike
• Platform EC368A is a 3-leg, steel jacket platform located in approximately 110m of water offshore
the coast of Louisiana. It was installed in 2003 and loaded by Hurricane Ike in 2008(after 5 years of
construction).
• platform was constructed by placing the jacket on the seafloor, driving the steel pipe piles through
the jacket legs into the soils, connecting the piles to the jacket legs with shims at the top of the legs,
and then welding the platform deck to the pile heads above the jacket legs.
• the design axial load was 11,900 kN in tension, the required axial capacity was 1.5 times the design
load or 17,800 kN in tension, and the selected pile length was 67.1 m.
• eye of Hurricane Ike passed within 64 km to the southwest of Platform EC368A on September 12,
2008.
• Based on the hurricane hindcast (Oceanweather 2008), the maximum wave height was 22 m and the
maximum wind speed was 114 km/h at Platform EC368A. For reference, the maximum wave height
was 15 to 20 percent higher than the design wave height associated with the 100-year metocean
conditions.
• the base shear in Hurricane Ike was approximately 30 to 40 percent higher than the design base shear.
• Hurricane resulted in pile tilted about 4 degress,pile are pulled out upto 1m from sea bed hence axial
pull-out failure of Pile C, was identified as the cause of failure for Platform .
2.Failure Case Study of Offshore Battered Drilled Shafts Due to Seabed Rock Scouring
• Construction of 3,440m long grand bridge crossing from A Island to B Island started in 2008 .
• the foundation of bridge constructed is of group pile system.
• The bridge consists of a total of 38 piers with 31 of them founded on battered piles.
• soil is made of a layer of sedimentary sand, weathered rock over granite and schist bedrock.
• The average water depth in the region of the main bridge span is 20~23 m.
• The piers in the shallow depth region consist of four drilled shafts with a diameter equal to 1.8 m.
Piers in the deep regions consist of four drilled shafts with a diameter equal to 1.8 m battered to
enhance the lateral resistance.
• the piers supporting the main bridge span, six 2.5 m diameter battered drilled shafts are used for high
lateral resistance.
• In August 2011 during construction, pier No. 21 of the 34 piers bridge, collapsed overnight. A month
later, pier No. 18 also collapsed.
• The pile foundation of the collapsed piers was investigated, and it was found that the piles showed
tensile failure in the bearing layer of weathered rocks.
• High tidal velocities and waves also cause scour around the piles which is a potential safety hazard
• Due to the high flow velocities at the construction site, seabed scour was assumed to be the main
cause of pile failure ,particularly large amount of seabed scour was observed at the location of pier
P17 through P19
Referances: