23 Reserves On STG Briefing FINAL For NCS Approved Tagged
23 Reserves On STG Briefing FINAL For NCS Approved Tagged
Voleak Roeum
NASA Headquarters
• Introduction/Background
• Methodology
2
Introduction
• NASA Center guidance requires that a mission hold Funded Schedule
Reserve (FSR) corresponding to the remaining Schedule to Go (STG) at
an increasing rate over the development lifecycle
• The rates of required FSR may not be adequate given that many projects
have experienced significant schedule growth
• This study looks at the project-held FSR and actual schedule growth for a
variety of NASA missions at the Preliminary Design Review (PDR), Critical
Design Review (CDR), Systems Integration Review (SIR), and Pre-Ship
Review (PSR)
• The data can then be used as guidance for adjusting project FSR
requirements and for establishing additional reserves at the center or HQ
level for future missions
3
NASA Project Lifecycle
Phase D:
• Background
Phase A: Phase B:
Phase C: System
Project Final Design Assembly, Phase E:
Conceptual Preliminary
Phase & Integration & Operations
Design Design
Fabrication Test, Launch &
Checkout
Reviews
PDR CDR SIR PSR LRD
• Definitions:
– KDP = Key Decision Point = Transition from one Phase to the next
– PDR = Preliminary Design Review
– CDR = Critical Design Review
– SIR = Systems Integration Review
– PSR = Pre-Ship Review
– LRD = Launch Readiness Date
4
Reserve Tracking Assumptions
• JPL and GSFC Guidelines specify funded schedule reserves in months for
Phases C & D
5
Example Project Lifecycle
• Funded Schedule Reserve (FSR) = No planned activities, but funded schedule
• FSR Rate = FSR/(Planned Activity + FSR) = FSR / (P + FSR)
Total
Schedule
Funded
Planned Schedule
Activity Reserve
Launch
KDP-B KDP-C KDP-D Ship KDP-E
P FSR P FSR P FSR
Critical Path
PDR CDR SIR PSR LRD
Guideline FSR 0 8 8 3 19
(weeks)
6
Outline
• Introduction/Background
• Methodology
7
Large Diversity of Missions Included in Analysis
• Data collected from 37 science missions providing a representative mix
Launch Mission Launch Mission
Theme Lead Org. Theme Lead Org.
Mission Date Type Mission Date Type
AIM Apr-07 Helio CAT 3 Other RHESSI Feb-02 Helio CAT 3 Other
Cloudsat Apr-06 Earth CAT 2 JPL SDO Feb-10 Helio CAT 1 GSFC
DAWN ct Sep-07 Planetary CAT 2 JPL Spitzer Aug-03 Astro CAT 1 JPL
Deep Impa Jan-05 Planetary CAT 2 JPL Stardust Feb-99 Planetary CAT 2 JPL
EO-1 Nov-00 Earth CAT 2 GSFC STEREO Oct-06 Helio CAT 2 GSFC
GALEX Apr-03 Astro CAT 3 JPL Swift Apr-04 Astro CAT 2 GSFC
GENESIS Aug-01 Planetary CAT 2 JPL Terra Dec-99 Earth CAT 1 GSFC
GLAST Jun-08 Astro CAT 2 GSFC WISE Jun-09 Astro CAT 2 JPL
GRAIL Sep-11 Planetary CAT 2 JPL GLORY Mar-11 Earth CAT 2 GSFC
IBEX Oct-08 Helio CAT 3 Other GPM Feb-14 Earth CAT 2 GSFC
ICESAT Jan-03 Earth CAT 2 GSFC IRIS Jun-13 Helio CAT 3 LM
Kepler Mar-09 Astro CAT 2 JPL Juno Aug-11 Planetary CAT 1 JPL
LRO Jun-09 Planetary CAT 2 GSFC LADEE Sep-13 Planetary CAT 2 ARC
MER R Jul-03 Planetary CAT 1 JPL LDCM Feb-13 Earth CAT 2 GSFC
MESSENGE Aug-04 Planetary CAT 2 APL MAVEN Nov-13 Planetary CAT 3 GSFC
MRO Aug-05 Planetary CAT 1 JPL MSL Nov-11 Planetary CAT 1 JPL
New Horiz Jan-06 Planetary CAT 1 APL RBSP Aug-12 Helio CAT 2 APL
OCO Feb-09 Earth CAT 2 JPL NuSTAR Jun-12 Astro CAT 3 JPL
PHOENIX Aug-07 Planetary CAT 2 JPL
Actual Duration
– External Events: factors resulting increased schedule growth which were outside of the control of
NASA and/or the project and unreasonable to anticipate and plan for
• NASA External: Contractor closes and relocates facility; labor strike; Hurricane delays launch
• Project External (Including above): center/headquarters directed launch date move; funding cut;
stand down
9
Outline
• Introduction/Background
• Methodology
10
Results of Historical Mission Examination
FSR Rates - All Missions
50.0
Weeks per year calculations
-Numbers: average weeks per year used between
45.0 each milestone
Weeks per year between Milestone
42.7
-Orange line: unadjusted calculation from the raw
40.0 schedule data
20.0 20.5
19.2
14.9
15.0 14.7 13.0
13.5
10.6 12.0
10.0 10.5
8.0
5.0
4.0 4.0
0.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Schedule Phase
Average All Causes Average NASA External Removed
11
Average Project External Removed Current FSR Guidelines
Results of Historical Mission Examination
FSR Rates - All Missions
50.0
On Schedule Missions
45.0 -Green line: average of the 8 missions
Weeks per year between Milestone
30.0 28.4
25.0 24.3
20.0 20.5
19.2
14.9
15.0 14.7 13.0
13.5 12.5
10.6 12.7 12.0
10.0 10.5 8.8
7.1 8.0
5.0
4.0 4.0
0.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Schedule Phase
Average All Causes Average NASA External Removed Average Project External Removed
12
Current FSR Guidelines Avg. Launched On Schedule
Results of Historical Mission Examination
FSR Rates - All Missions
50.0
45.0
Weeks per year between Milestone
7.1 8.0
5.0
4.0 4.0
0.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Schedule Phase
Average All Causes Average NASA External Removed Average Project External Removed
Current FSR Guidelines Avg. Launched On Schedule
13
Results of Historical Mission Examination
FSR Rates - All Missions
50.0
SIR to PSR
-Even with external events removed the I&T
45.0 phase is the most prominent with largest
Weeks per year between Milestone
42.7
variance from guidelines
40.0
- Expected as the most intense development
35.0 effort takes place in this phase 33.9
7.1 8.0
5.0
4.0 4.0
0.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Schedule Phase
Average All Causes Average NASA External Removed Average Project External Removed
Current FSR Guidelines Avg. Launched On Schedule
14
Results of Historical Mission Examination
FSR Rates - All Missions
50.0
PSR to Launch
45.0 -External events such as launch vehicle
Weeks per year between Milestone
25.0 24.3
20.0 20.5
19.2
14.9
15.0 14.7 13.0
13.5 12.5
10.6 12.7 12.0
10.0 10.5 8.8
7.1 8.0
5.0
4.0 4.0
0.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Schedule Phase
Average All Causes Average NASA External Removed Average Project External Removed
Current FSR Guidelines Avg. Launched On Schedule
15
Further Analysis
• Examination of the average can be useful to asses overall trends
– However, there is much variation present in the schedule data
– Some missions were affected by “extraordinary” events which could not be planned for
– Data points to the far right can unfairly influence the average
• The following slides show the cumulative distributions at the guideline specified
milestones (PDR, SIR, PSR) with the 50% and 70% levels highlighted
16
Required Schedule Reserve at PDR
Guideline: 4 weeks/year
60% 13.5
7.2
50%
40%
Current FSR Guideline
4
0%
0 5 10 15 20 25 30 35 40 45 50
Weeks Per 17
Year
Required Schedule Reserve at SIR
Guideline: 8 weeks/year
60%
33.9
50%
40%
Current FSR Guideline
0% 8
0 5 10 15 20 25 30 35 40 45 50
Weeks Per 18
Year
Required Schedule Reserve at PSR
Guideline: 12 weeks/year
Required FSR @ PSR
100% 12
70% w/o
90%
NASA
80%
External
42.7
19.2
50% w/o
70%
Project
External 11.8
Cumulative Probability
60%
13.4
50%
40%
Current FSR Guideline
10%
12 17 Launched On Schedule
0% 12
0 5 10 15 20 25 30 35 40 45 50
19
Weeks Per Year
Outline
• Introduction/Background
• Methodology
20
Recommendations
• Examination of the cumulative distributions of historical data yielded the following
recommended values of FSR given the example project schedule
Phase ATP to PDR PDR to SIR SIR to PSR PSR to Total Total
Launch (Years) (months)
Example Duration (years) 0.75 2.0 1.0 0.25 4.0 48
Current Guidelines
FSR Rate (wks/year) 0 4 8 12 Total Total
(Weeks) (months)
Total FSR (weeks) 0 8 8 3 19 4
21
Summary
• This study aimed to assess if the adequacy of the current guidelines for
carrying funded schedule reserve based on schedule-to-go
Current Guidelines 4 8 12
22