[1] In this project a detail reconnaisance and a tree count are not possible. Field manual
Bulldozer Thus quick method is used to estimate for the normal area clearing. (FM) No 5-434
15 June 2000
STEP 1
Determine the size of the area to clear (in acre).
Area to be cleard, A
= 1,100,000.33 m³
STEP 2
Determine the size and number of dozer available.
Assumed:
Bulldozer size = Heavy
Heavy Tractor has an operating weight of 108,390 kg
STEP 3
Determine the maximum size of the trees to clear. JKH 4A/1
Based on the site area is = 24 inches REFERENCE 2
= 60.96 cm
It is noted that the clearing rate is based on the average trees count
of 50 tree per arce.
Therefore it is assumed that:
Number of trees on site = 50 x 271.82 acre
= 13,590.79 trees
STEP 5
Operator require break and there are always secondary delay for minor Table 2.2
equipment repair. Therefore, actual production time per hour is REFERENCE 4
something less than 60 minutes. In the case of a well-managed job
expect 50 minutes of production time per hour.
1
Equipment/
Descriptions References
Labour
= 50 min/hr
60 min/hr
= 0.83
STEP 6
Determine the operator factor CIDB
Assume that the operator ability is average and the operation hour is during 2018 Machinery
daylight. Hire Rate and
Thus , the operator factor, O = 1.0 Equipment
Purchase Price
STEP 7 (LIST A)
Determine the total time (in hour) require to complete the mission. Pahang
REFERENCE 22
Total time (hours) = DxA
ExOxN
= 522 hr
= 65.2 day
KOMATSU
STEP 8
Determine the cost Catalog Crawler
The detail of medium bulldozer used are as below: Dozer
Brand : Komatsu
Model: SAA12V140E-3
Excluding cost of diesel / petrol used and transport cost from machinery
leasing company to construction site and back,
= 208.8 L /hr
= RM 3,640.60
Thus, it is assumed that the forest type of tahan rata us same in Caspian
forest as used our reference.
Including delay, total time needed to fell a tree per labour(output efficiency)
≈ 5 min.
Assume number of labour available = 8
Time needed to fell all the trees
= 13591 x 5 / 8
= 8494.242 min
≈ 142 hr ≈ 18 day
Also, tree in LMF on the large mountain may reach up to 1.8 - 10.0
which is averagely 5.9 m
However the length of the cargo of dump truck is 5.5m.
Thus, the tree should be cut smaller into averagely = 5.9 ≈ 1 sect.
5.0
= 6795.39 minutes
≈ 113 hr ≈ 14 days
Total day needed for tree feeling and cut the logs into smaller section,
= 142 + 113
= 255 hr
≈ 32 days
= 1.5 m³
= 0.83
Thus, Output efficiency for an excavator,
= initial time + delay time due to effciency factor
= 15 + 1 - 0.83 x 15
= 17.50
≈ 18 second/log
The dump truck needed to travel 35 trips to transport all the logs.Thus,
Total time needed to complete the task = 6 x 35
= 200 min
≈ 3.3 hr
≈ 0.4 day
A truck cycle time included the time a loaded truck takes to travel to the
dump site,unload,return to the loading unit and be reloaded.
Assume time required to unload = time required for loading = 3.5 min.
Trucuk recyle time = 0.32 + 0.32 + 23 + 23
= 47 min.