Professional Documents
Culture Documents
Thesis On Road Nepal
Thesis On Road Nepal
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
PULCHOWK CAMPUS
Submitted By:
Suraj Bhandari (2070 MSCM 318)
A THESIS
SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING IN PARTIAL
FULFILLMENT OF THE REQUIREMENT FOR THE DEGREE OF MASTER OF
SCIENCE IN CONSTRUCTION MANAGEMENT
December 2017
ii
COPYRIGHT
The author has agreed that the library, Department of Civil Engineering, Pulchowk Campus,
Institute of Engineering may make this thesis freely available for inspection. Moreover, the
author has agreed that permission for extensive copying of this thesis for scholarly purpose
may be granted by the professor(s) who supervised the work recorded herein or, in their
absence, by the Head of the Department wherein the thesis was done. It is understood that the
recognition will be given to the author of this thesis and to the Department of Civil
Engineering, Pulchowk Campus, Institute of Engineering in any use of the material of this
thesis. Copying or publication or the other use of this thesis for financial gain without
approval of the Department of Civil Engineering, Pulchowk Campus, Institute of Engineering
and author’s written permission is prohibited. Request for permission to copy or to make any
other use of the material in this thesis in whole or in part should be addressed to:
Head
Department of Civil Engineering
Pulchowk Campus, Institute of Engineering
Lalitpur, Kathmandu
Nepal
iii
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
PULCHOWK CAMPUS
DEPARTMENT OF CIVIL ENGINEERING
The undersigned certify that they have read, and recommended to the Institute
of Engineering for acceptance, a thesis entitled “Factors Causing Delay in
SNRTP Eastern Cluster Road Upgrading Projects" submitted by Suraj
Bhandari in partial fulfillment of the requirements for the degree of Master in
Construction Management.
Supervisor,
Prof. Dr. Rabindra Nath Shrestha
Department of Civil Engineering
Pulchowk Campus
External Examiner,
Mr. Vishwa Nath Khanal
Program Coordinator,
Prof. Dr. Rabindra Nath Shrestha
iv
ACKNOWLEDGEMENT
v
ABSTRACT
Construction Delays are common Phenomenon in construction industry in Nepal including
SNRTP road upgrading projects which result in cost and time overrun of projects. Therefore,
this research was carried out to explore important factors contributing to delays in SNRTP
programme districts of eastern cluster road upgrading projects. Questionnaire surveys
together with desk study were carried out to collect data on time overrun. Out of 59 road
upgrading projects on programme districts, 7 projects were completed within estimated
completion time and 5 were completed with time overrun of ranges from 33.33% to 63.63%.
And on 47 ongoing projects, on 29 projects time elapsed ranges from 101.24% to 178.23%.
98 questionnaire were distributed to client, contractor and consultant involved in SNRTP
eastern cluster road upgrading projects and 37 questionnaire were received. Relative
Importance Index was calculated and according to analysis most contributing causes to time
overrun identified were poor site management, low bid, lack of proper division of
responsibility by contractors in Joint Venture, ineffective planning and scheduling of
projects, incompetence or inadequate number of technical staff, shortage of skilled labor,
inadequate modern equipment, incompetent design team, adhoc contract duration adopted
and insufficient data collection & survey before design. Spearman correlation coefficient test
were calculated for client & contractor, client & consultant and contractor & consultant. Test
result revealed good correlation among the attitudes of respondents in all three groups.
Some recommendations were proposed in order to control & minimize delays in SNRTP
programmed districts of eastern cluster road upgrading projects. These findings can be
helpful for project manager to mitigare road upgrading delays.
Key Words: Cost Overrun, Delay, Relative Importance Index, Time Overrun, SNRTP,
Spearman Correlation Coefficient, Upgrading roads
vi
Contents
COPYRIGHT........................................................................................................................................ii
ACKNOWLEDGEMENT....................................................................................................................iv
ABSTRACT..........................................................................................................................................v
LIST OF FIGURE...............................................................................................................................vii
LIST OF TABLES................................................................................................................................ix
LIST OF ANNEX..................................................................................................................................x
ABBREVIATIONS AND ACRONYMS..............................................................................................xi
CHAPTER 1: INTRODUCTION..........................................................................................................1
1.1 Background..................................................................................................................................1
1.2 Situation and Problems................................................................................................................1
1.3 Research Question.......................................................................................................................2
1.4 Research Objective......................................................................................................................2
1.5 Significance of study...................................................................................................................2
1.6 Scope and Limitation...................................................................................................................2
CHAPTER 2: LITERATURE REVIEW..............................................................................................3
2.1 Introduction to SNRTP................................................................................................................3
2.2 Institutional Arrangement of SNRTP...........................................................................................4
2.3 Delay...........................................................................................................................................5
2.4 Types of Delays...........................................................................................................................6
2.4.1Excusable or non-excusable delay.........................................................................................7
2.4.2 Concurrent or non-concurrent delays...................................................................................7
2.4.3 Compensable or non-compensable delays...........................................................................8
2.5 Causes of Delay...........................................................................................................................8
2.6 Effect of Delay...........................................................................................................................11
2.7 Measures to Control Delay........................................................................................................12
2.7.1 Project Time Management.................................................................................................12
2.7.2 Techniques used in managing project time........................................................................13
2.8 Time Overrun in Construction Project in Nepal.........................................................................13
2.9 Summary of Literature Review..................................................................................................14
CHAPTER 3: RESEARCH METHODOLOGY..................................................................................15
3.1 Introduction...............................................................................................................................15
3.2 Study Area.................................................................................................................................16
vii
3.3 Study Population & Sample size................................................................................................16
3.4 Sources of Data..........................................................................................................................16
3.4.1 Primary Data collection.......................................................................................................17
3.4.2 Secondary Data Collection..................................................................................................17
3.5 Data Collection Methods...........................................................................................................17
3.6 Respondent Information............................................................................................................17
3.7 Questionnaire Survey.................................................................................................................18
3.8 Questionnaire Design.................................................................................................................18
3.9 Method of Data Analysis...........................................................................................................18
3.9.1Relative Importance Index...................................................................................................18
3.9.2 Spearman Correlation Coefficient.......................................................................................19
CHAPTER 4: FINDINGS AND DISCUSSION..................................................................................20
4.1 Status of SNRTP Upgrading Roads.............................................................................................20
4.2 Output of questionnaire Survey.................................................................................................23
4.2.1. Top 10 causes of schedule overrun from point of view of employer.................................24
4.2.2 Top 10 causes of schedule overrun from point of view of Contractor................................26
4.2.3 Top 10 causes of schedule overrun from point of view of Consultant................................27
4.2.4 Top 10 causes of schedule overrun from point of average weighted view of Contractor,
Consultant and Employer............................................................................................................29
4.2.5Causes of delay categorized into different Group from point of average weighted view of
Contractor, Consultant and Employer.........................................................................................30
4.3 Test for agreements on causes of Time overrun among Client, Contractor and Consultant.......39
Chapter 5:- Conclusion and Recommendation.....................................................................................41
5.1. Conclusion................................................................................................................................41
5.2 Recommendation.......................................................................................................................42
5.3 Recommendations for Further Study.........................................................................................43
Bibliography........................................................................................................................................44
ANNEX...............................................................................................................................................46
viii
LIST OF FIGURE
Figure 2.1………… SNRTP Projects in Nepal
Figure 2.2………… Institutional framework of SNRTP
Figure 2.3………… Delay and Time overrun Difference
Figure 2.4………… Delay and Time overrun Difference
Figure 3.1………….Methodological Framework of Research
Figure3.2…………..Source of Data
Figure 3.3……….....Percentile of Questionnaire Respondent
Figure 4.0……….....Number of upgrading road projects in SNRTP Eastern Cluster Districts.
Figure 4.1………….Time period extended in upgrading road projects
Figure 4.2………….Total Project Scenario of SNRTP Eastern Cluster Upgrading Roads\
Figure 4.3…...……. Top 10 cause of schedule overrun from point view of employer
Figure 4.4………….Top 10 cause of schedule overrun from point view of Contractor.
Figure 4.5………… Top 10 cause of schedule overrun from point view of Consultant
Figure 4.6……….....Top 10 cause of schedule overrun from overall average weighted of
point view of employer, contractor and consultant.
Figure 4.7….……... Project & Contract related factors causing delay
Figure 4.8…… ……Client, Contractor & Consultant View on Low Bid (the most governing
factor on project & contract related factors.)
Figure 4.9………… Client related factors causing delay
Figure: 4.10………. Client, Contractor & Consultant View on Variation and additional works
(the most governing factor on Client related factors.)
Figure 4.11………...Contractor related factors causing delay
Figure 4.12……..… Client, Contractor & Consultant View on Poor site management (the
most governing factor on Contractor related factors.)
Figure 4.13…….…..Material related factors causing delay
Figure 4.14…….…. Client, Contractor & Consultant View on Absence of material stock at
site (the most governing factor on materials related factors.)
Figure 4.15……….. Equipment related factors causing delay
Figure: 4.16………..Client, Contractor & Consultant View on inadequate modern equipment
(the most governing factor on equipment related factors.)
Figure 4.17………... Labor related factors causing delay
Figure: 4.18……..….Client, Contractor & Consultant View on Shortage of skilled labor (the
most governing factor on equipment related factors.)
Figure 4.19…….….. Consultant and Designer related factors causing delay
Figure: 4.20………...Client, Contractor & Consultant View on Incompetent design team (the
most governing factor on equipment related factors.)
Figure 4.21………... Other Authority/Stakeholder related factors causing delay
Figure: 4.22….……..Client, Contractor & Consultant View on IEE/EIA approval (the most
governing factor on equipment related factors.)
Figure 4.23……...….External related factors causing delay
Figure: 4.24……...... Client, Contractor & Consultant View on Effect of social and cultural
factor (the most governing factor on equipment related factors.)
ix
LIST OF TABLES
Table 1....................SNRTP Funding Source, Amount and Percentage.
Table 2....................SNRTP Projects Running Districts
Table 3....................List of Important Delay Causes in Different Nation from Literature
Review.
Table 4....................Targeted Population and Sample in Study.
Table 5...................Questionnaire Distributed Vs Responded
Table 6...................Present Status of Upgrading Roads in SNRTP Eastern Cluster.
Table 7....................Factors influencing time overrun from point view of employer,
contractor, consultant and weighted average of them.
Table 8....................Top 10 cause of delay from point view of client categorized into different
group
Table 9....................Top 10 cause of delay from point view of contractor categorized into
different group
Table 10..................Top 10 cause of delay from point view of consultant categorized into
different group
Table 11..................Top 10 cause of delay from point view from overall average weighted of
point view of employer, contractor and consultant.
Table12...................Spearman Correlation Coefficient among Client, Consultant and
Contractor.
x
LIST OF ANNEX
xi
ABBREVIATIONS AND ACRONYMS
ADB…………………Asian Development Bank
CPCU ……………… Centre Project Coordination Unit
DDC........................... District Development Committee
DOLIDAR…………. Department of Local Infrastructure Development and Agriculture Road
DoR………………….Department of Roads
DTMP………………. District Transport Master Plan
DTO………………….District Technical Office
FCAN……………….. Federation of Contractor Association Nepal
GDP………………… Gross Domestic Product
GoN…………………. Government of Nepal
IDA…………………. International Development Association
LRN…………………. Local Road Network
MOFALD…………… Ministry of Federal Affairs Local Development
MYRMP………….......Multi Year Routine Maintenance Plan
PAC……………..........Project Advisory Committee
PMBOK………………Project Management Body of Knowledge
PMU............................. Project Monitoring Unit
PPA……………...……Public Procurement Act
PPR……………..…….Public Procurement Regulation
RII………………...…. Relative Importance Index
SNRTP………………..Strengthening National Rural Transport Programme
SRN…………………..Strategic Road Network
UK……………………United Kingdom
USA…………………. United States of America
WB…………………... World Bank
xii
CHAPTER 1: INTRODUCTION
1.1 Background
Standard Industrial Classification, 2007 define construction industry as complete general
construction and allied construction activities for building and civil engineering works.
Construction industry is backbone of development so has great impacts in overall national
economy. According to FCAN, Nepalese construction industry contributes around 10 to 11%
of GDP and its uses around 35% of government budget and is providing employment
opportunities to about one million people which is large employment next to agriculture.
Road sector construction project involves large amount of capital so contributing to total
economy growth through job creation and in a ripple effect to other business activities.
(Mustefa, 2015). In Nepal, national road network comprises of national highway, feeder
road, urban road, district road and rural roads. National highway together with feeder roads
comprises the strategic road network which is the backbone of national road network.
District roads together with village roads comprise district road networks. Local road network
comprises of district roads, those urban roads not included in SRN, village roads, agricultural
roads, mule trials and tracks. There are two government agencies formed for road and bridge
construction in Nepal. SRN are undertaken by DOR and LRN are undertaken by DoLIDAR.
There are 15 national highway and 51 feeder road totaling 8000km in strategic road
networks. (Sitaula,2015).
Project for Strenghtening National Rural Transport Program Project operation manual, 2014
mentioned that Two-thirds of rural roads are earthen and so remain inaccessible during the
rainy season. Also Blacktopped and gravelled roads are poorly maintained and further
affecting access. So to enhance the rural connectivity for more than 14.6 million people in 36
districts of Nepal, the Strengthening the National Rural Transport Program (SNRTP)
Program is implemented. SNRTP program implementation period start from 23 December
2014 and end on 14 July 2019. There are two components under SNRTP. Component A and
Component B. Component A is being funding for institutional strengthening, beneficiary
monitoring of physical works support for updating District Transport Master Plans (DTMPs)
and Multi-Year Road Maintenance Plans (MYRMP). Component B is being supporting
districts to implement physical works needed for upgrading or rehabilitating rural transport
infrastructure; and maintaining rural transport infrastructure. With these support program is is
expecting to enhance the availability and reliability of transport connectivity for rural
communities in the programme districts.
1
Nepali Headlines Fuel shortage halts construction of mid hill puspha lal highway.
Republica, July 9 2017, No progress on road project financed by Indian soft loan.
Nepali Headlines, March 20 2015, Construction works on six lane highway in
Pokhara has commenced after delay of almost 15 yrs.
51 Annual Report of the Auditor General 2070 published that out of the 2937 contracts made,
56% contract were time extended, out of which time extensions up to 50% was made for 535
contracts, 51-100% time extension was given to 516 contracts, and time extension by more
than 100% was given to 581 contract cases was seen.
Delays adversely impact on project stakeholders including owners, design professionals,
construction professionals, purchaser and others. Many road constructions in Nepal seem to
be suffered by schedule overrun which cause cost overrun in project. Due to delay in road
construction people are travelling with discomfort and are vulnerable to traffic accident.
2
CHAPTER 2: LITERATURE REVIEW
This chapter was mainly focused on the review of theoretical concepts, review of related
studies. The related topics were on concepts of time overrun, their scenario in different
country in construction industry. Different books, journal, and research paper were collected
to develop understanding about an overview of time overrun. Internet researches were
conducted to get relevant information.
3
Udayapur Makwanpur Dang Palpa
Siraha Nuwakot Salyan Syangja
Dhanusha Rasuwa Pyuthan Kaski
Mahottari Dhading Arghakhanchi Bardiya
Sindhupalchowk Lamjung, Gulmi Gorkha
Source: - SNRTP POM (2016)
4
Figure 2.2: Institutional framework of SNRTP
Source: - SNRTP POM (2016)
2.3 Delay
The delay is the most common, costly, complex and risky problem encountered in
construction projects and there are different definitions of construction delays. (Aziz &,
Hakam, 2016). Assaf and Al-Hejji (2006) define delay is the time overrun either beyond
completion date specified in a contract,or beyond the date that the parties agreed upon for
delivery ofa project, Similary, Stumpf (2000) defined delay as an act or event that extends the
time required to perform the tasks under a contract which shows up as additional days of
work or as a delayed start of an activity. Stumpf stated in his article that construction delays
became an integral part of the project’s construction life and even with today’s advanced
technology, and management understanding of project management techniques, construction
projects continue to suffer delays and project completion dates still get pushed back.
Construction delays are considered as time lag in completion of activities from its specified
time as per contract or can be defined as late completion of activities to the baseline schedule.
As a result, there will be extensions of time required which will further result in fine,
increased cost due to inflation, termination of contract, court cases etc. or combinations of
above stated factors, resulting in delay damages. The social and economic costs of delay can
be amazingly high and to a certain extent cannot be absorbed by the industry. When a delay
can no longer be absorbed by the client, it will result in the project being abandoned. Thus, it
is important to predict and identify problems in the early stages of construction and diagnose
the main causes and implement the most appropriate and economical solutions to prevent
further negative impacts of delay.
5
Figure 2.3: Delay and Time overrun Difference
Source: (Hoseini 2014)
Type of Delay
7
A compensable delay is a delay where the contractor is entitled to a time extension and to
additional financial compensation. Relating to the excusable and non-excusable delays, only
excusable delays can be compensable. Non-compensable delays mean that although an
excusable delay may have occurred, the contractor is not entitled to any added compensation
resulting from the excusable delay. A non-excusable delay cause neither additional
compensation nor a time extension. Whether or not a delay is compensable depends primarily
on the terms of the contract. In most cases, a contract specifically notes the kinds of delays
that are non-compensable, for which the contractor does not receive any additional money but
may be allowed a time extension, (Mustafa A, 2015).
8
3) Owner’s responsibility
The factors that are related to owner's responsibility are;
Delay to furnish and deliver the site
Lack of working knowledge
Slowness in making decisions
Lack of coordination with contractors
Change orders by owner during construction
Financial problems
Slowness in decision making process
Poor communication and coordination.
4) External factors:
The factors that are related to external factors are;
Delay in obtaining permits from municipality
Lack of materials on the market
Lack of equipment and tools on the market
Poor weather conditions; poor site conditions (location, ground, etc.)
Poor economic conditions (currency, inflation rate, etc.)
Changes in laws and regulations; transportation delays
External work due to public agencies (utilities and public services); and
Delay in providing services from utilities (such as water, electricity)
Similarly, Alwi et al (2002) identified factors and categorized the factors in following three
categories as of owner, contractor and consultant.
Factors that influence time overruns category factors (Alwi et al, 2002)
1) Owner
Finance and payments of completed work.
Owner interference.
Slow decision-making by owners.
Change orders.
Unrealistic imposed contract duration.
2) Contractor
Subcontractors.
Site management.
Construction methods.
Improper planning.
Mistakes during construction.
Inadequate contractor experience.
Quality of material.
Shortage in material.
Labor supply.
Labor productivity.
Equipment availability and failure.
3) Consultant
Contract management.
Preparation and approval of drawings.
Quality assurance/control.
Mistakes and discrepancies in contract documents.
Waiting time for approval of tests and inspections.
9
Elawi G, Algahtany M & Kashiwagi D (2016) in their study of owner perspective on project
delay on road and bridge projects in Saudi Arabia identified the most severe cause of delay
was found to be the land acquisition factor which highlights the critical land ownership and
acquisition issues that are prevailing in the city. Additionally, other identified factors that
contribute to delay were contractors’ lack of expertise, re-designing, and haphazard
underground line services.
Odeh A M and Battaineh H T (2002) in their study identified 28 delays which affect
construction projects with traditional type of contracts in Jordan. Questionnaires were made
and were distributed to a random sample of contractors and consultants working on large
projects in Jordan. Then the Spearman’s rank correlation coefficient was then used to test
association between the contractors and consultants ranking. The study revealed that Owner
interference, inadequate contractor experience, financing and payments, labor productivity,
slow decision making, improper planning, and subcontractors are among the ten most
important factors, according to contractors and labor productivity was the most important
delay factor. Inadequate contractor experience was the most important delay factor to
consultants.
Soliman E M (2010) on his study on delay causes in Kuwait construction project identified
29 delays and categorized them into six groups then subjected to a questionnaire survey. Data
collected were analyzed by importance index and then the Spearman’s rank correlation
coefficient method was used to show the degree of agreement between the rankings of any
two parties. The study revealed that the financial and design related causes of delays are the
most important and frequent causes. The top five delay causes that were resulted from
contractors category were: delay of document submission from consultant, delaying of
payments from owner, conflict between contractor and consultant, in-appropriate owner
representative’s management style and owner financial problems, While the five top delay
causes from consultants category are: owner financial problems, contractor financial
problems, inefficient management capability of contractor staff, conflict between contractor
and consultant, and no planning before project start.
Comparative chart of research conducted for delay in different study region are listed as
below. The following table shows the five most important delay causes mentioned in
literature.
Table 3: List of Important Delay Causes in Different Nation from Literature Review.
Author Study
SN Main Delay Cause
/Year Region/Country
Change order Changed site
(Yang et
Delayed construction conditions
1 al., 2013) Taiwan
site handover Changed scope of the
Shortages of materials work
Financial difficulties Late supervision and
(Alaghbari and economic decision making
Malysia
2 et al., 2007) problems Construction mistakes
Lack of materials and defective work
Poor site management
3 (Abd El- Eygpt Financial difficulties Changes of design
Razek et al., of the contractor not application of
2008) Delay in progress construction/contractu
payments by al management
10
client method
Late delivery
Poor site management Poor planning and
(Pourrostam Delay in progress scheduling by
and Ismail, payments by client contractor
4 Iran Change orders by Financial difficulties
2011)
client of contractor
11
Cost overrun and time overrun effects are not only confined to construction industry but also
they are reflected in the overall economy of a country. They prevent the planned increase in
property and service production from taking place, and this phenomenon will affects in a
negative way of the rate of national growth.[Arditi,et al, 1985].
12
2.7.2 Techniques used in managing project time
Different techniques usually used in managing project time period are as follows.
2.7.2.1 Critical Path Methods (CPM)
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for
scheduling a set of project activities. In this method, critical activities of a program or a
project are identified which have a direct impact on the completion date of the project. It
offers a visual representation of the project activities and presents the time to complete the
tasks and overall project and help to track of critical activities. The focus of CPM is on
calculating float in order to determine which activities have the least scheduling flexibility.
13
2.9 Summary of Literature Review
The literature review was done through book studies, internet, engineering journals. By
referring to the previous literature, the information about time delay, its type’s causes,
effects and rectification method were observed which would be used to develop the
questionnaire survey in order to collect data from the targeted respondent.
There is a wide range of views for the causes of time delays for engineering and construction
projects. It can therefore be concluded that the most important factors vary from one region to
another. There are many factors that contribute to causes of delays in construction projects.
They can range from factors inherent in the management, to those resulting from the physical,
social, and financial environment. It is essential to define the actual causes of delay in order
to minimize and avoid the delays in any construction project.
14
CHAPTER 3: RESEARCH METHODOLOGY
3.1 Introduction
Research methodology is a way to systematically solve the research problem. It is a science
of studying how research is done scientifically. In it, we study the various steps that are
generally adopted by a researcher in studying his research problem along with the logic
behind them.
This research has begun with the literature review of published and unpublished materials
like books, reports, management journals, electronic journals, published papers and articles.
The research has been further carried out by collecting primary and secondary data which
were analyzed and interpreted, thereafter conclusions and recommendations were drawn from
it.
Literature Review
Research Design
Data Collection
Data Compilation
15
3.2 Study Area
Study area is generally the geographical area for which data is analyzed. For this thesis, study
area was Programmed district of SNRTP Eastern Cluster. They are Rasuwa, Dhading ,
Nuwakot, Sindhupalchowk, Makwanpur, Rahutahat, Saralahi, Mohatari, Dhanusa, Siraha,
Udaypur, Parsa, Saptari, Bara, Terathum, Sankhuwasaba & Bhojpur districts.
Total Respondents %
35%
43%
Client
Contractor
Consultant
22%
17
3.7 Questionnaire Survey
Existing literatures of causes of delay on onstruction projects in different countries were
reviewed and draft Questionnaires was prepared. With the support of the Supervisor thirty
eight causes of delay were identify and categorized on six major groups.
A questionnaire was organized in the form of an importance scale. Respondents were asked
to indicate by ticking a column the relative importance of each of the causes of construction
delay.
18
Spearman correlation coefficient was used to investigate whether there was agreement or not
on the response of employer, contractor and consultant respondent towards the causes of time
overrun on roads upgrading projects in SNRTP Eastern Cluster. Respondents’ response was
tested for correlation using Spearman rank correlation coefficients, to see if there was
difference in ranking between two groups of respondents; these were Clients versus
Contractors; Contractors versus Consultants; and Clients versus Consultants.
The Spearman (rho) rank correlation coefficient is used for measuring the differences in
ranking between two groups of respondents scoring for various factors. The Spearman (rho)
rank correlation coefficient for any two groups of ranking is given by the following formula.
Rho (ρcal) = 1 –6 x (Σdi) ^2
N x (N2– 1)
Where:
Rho (ρcal) – Spearman rank correlation coefficient
di– The difference in ranking between each pair of factors
N– Number of factors (variables)
19
CHAPTER 4: FINDINGS AND DISCUSSION
This chapter describes the findings and discussion of results of desk study and of
questionnaire survey. Questionnaire survey was done to find major factors causing delay in
upgrading road projects of SNRTP Eastern Cluster from contractors, consultant and
employers viewpoints. To meet the research objectives, the necessary data were collected
from desk study and from questionnaire survey. Questionnaires were distributed to the
employers, contractors, consultants who are directly/indirectly involved in SNRTP upgrading
roads. The tables used for analysis are attached to the appendix. The data were analyzed and
results are obtained as below which has been presented in figure, chart with explanation.
20
Table 6:- Present Status of Upgrading Roads in SNRTP Eastern Cluster.
Contract Original Final
Name of Total Estimated Extended Physical % Time
SN Districts
Name of Contracts
Length
Name of Contractors Signing Completion
Time Time
Completion
Progress Ellapsed
Date Date Date
Bhimdunga-Lamidanda
M/S Aashish-Suryachandra JV,
Road
12.58 21-Jan-16 20-May-17 16 months 4 months 21-Sep-17 40.00 110.51
(Jeevanpur-Kewalpur-
1 Dhading Dhapasi, Kathmandu, Nepal
Goganpani Section)
Dhadingbesi-Sangkosh- M/S Lama/Mahalaxmi JV,
25.03 8-Sep-16 18-Dec-17 16 months 18-Dec-17 25.00 94.85
Tipling Road Balaju, Kathmandu
Mahendradhunga-
M/S Tamang Construction 18months
Khadgabhanjyang- 10.88 30-May-14 2-Dec-15 18 months 12-Jun-17 93.00 114.88
Pvt.Ltd. Sitapaila, Kathmandu (4 times)
Grosyang-Dhasing Road
Mahendradhunga-
M/S Nagarjun Construction
Khadgabhanjyang-
12.60 Company Pvt.Ltd., 27-Oct-16 24-Jan-18 15 months 24-Jan-18 20.00 86.56
Grosyang-Dangsing-
Kamalpokhari, Kathmandu
Kaphalpani Road
Trisuli-Deurali-Meghang-
2 Nuwakot M/S Trishuli/BM JV Biddur,
Kimtang-Thambu Khola 13.00 10-Nov-15 8-May-16 6 months 8 months 1-Jan-17 50.00 178.23
Nuwakot Nepal
Road
Trisuli-Deurali-Meghang- M/S Shrinkhala Nirman Sewa
Kimtang-Thambu Khola 9.00 Pvt.Ltd, 26-Oct-16 26-Oct-17 12 months 26-Oct-17 65.00 107.95
Road Bidur-4, Batar, Nuwakot
M/S Srinkhala Nirman Sewa
Bageshwari-Urleni Road 10.00 Pvt.Ltd, Bidur-4, Batar, 26-Oct-16 26-Oct-17 12 months 26-Oct-17 67.00 107.95
Nuwakot
M/S Koshi and Newoane
Bogatitar_Simle_Bhorle_Pa Nirman Sewa Pvt. Ltd.,
3 Rasuwa 6.25 19-Nov-15 12-Feb-17 15 months 5 months 6-Jul-17 52.00 123.70
rchayang Baneshwar-10, Kathmandu,
Nepal
M/S Kumar and Amar
Kulekhani-Phakel- 6 months
15.40 Construction JV , Kalimati, 18-Nov-15 18-Feb-17 15 months 14-Aug-17 82.00 116.06
Humanebhnjyang (2 times)
Kathmandu Nepal
4 Makwanpur
M/S. Mahalaxmi-Sigha &
Daman-Dandabas Rd: 11.34 Brothers JV , Kathmandu-14, 2-Mar-16 2-Jun-17 15 months 2-Jun-17 50.00 138.29
Kalanki, Nepal
1
M/S. United Builders and
Aurahaiya-Laxminiya-
Engineers Pvt.Ltd. ,Marpha
Rampurkhap-Bankul- 30.02 12-May-16 12-May-18 24 months 12-May-18 40.00 76.85
House, Anamnagar,
Himalibas
Kathmandu,Nepal
5 Rautahat Gaur-Banjarha-Auriya-
M/S Rasuwa- Ashraya-Shah
Dumariya-Bishanpatti- 25.62 17-May-16 17-May-18 24 months 17-May-18 40 76.16
JV, Basundhara-03, Kathmandu
Inerwari
Sauratha-Badaharwa- MS Pappu- Shivshankar jv,
17.51 11-Jan-17 11-Jan-18 12 months 11-Jan-18 3.00 86.85
Bankul-Aruwa Khola Road Garuda, Rauthat.
2
Devpura-Ghodghas- M/S. Raman/Kamal JV 12 months
13.70 18-Jun-15 17-Sep-16 15 months 24-Sep-17 72.35 107.36
Fulgama-Tulsiyahi Road Janakpur-09, Dhanusha (2 times)
Mahuwa-Dhaubauli- M/S. Lohani & Brothers and
12 months
Yadukhowa-Balabakhar 16.50 Shiva Shankar JV, Gauruda, 17-Jun-15 16-Sep-16 15 months 23-Sep-17 89.34 107.48
(2 times)
Road Rauthat
M/S. Lohani & Brothers and
Janakpur-Manharpur- 12 months
16.20 Shiva Shankar JV, Gauruda, 17-Jun-15 16-Sep-16 15 months 23-Sep-17 68.71 107.48
Khariyani Road (2 times)
Rauthat
Mahuwa-Dhaubauli-
M/S Raman-Kamal J.V
Yadukhowa-Balabakhar 12.85 11-Dec-16 24-Dec-17 12 months 24-Dec-17 23.69 92.06
Janakpur-9,Dhanusha
Road
Janakpur-Manharpur- M/S Raman-Kamal J.V
11.65 16-Sep-16 29-Dec-17 15 months 29-Dec-17 23.76 92.54
Khariyani Road Janakpur-9,Dhanusha
Dhanushadham- M/S. Shivshanakr 7.5
Under
8 Dhanusha Raghunathpur-Kiratpur 9.00 Construction-Pipariya, Dostiya- 15-Jul-15 15-Jun-16 11 months months 31-Dec-16 100.00
DLP
Road 9, Rauthat , Nepal (2times)
Janaki Medical Colege- 7.5
M/S. Kamal/Sagun JV, Under
Ramdaiya-Sabaila- 12.20 15-Jul-15 15-Jun-16 11 months months 31-Dec-16 100.00
Janakpur-9, Nepal DLP
Patewrwa Road (2times)
7.5
Kurtha-Shantipur- M/S. Kamal Nirman Sewa Under
10.00 15-Jul-15 15-Jun-16 11 months months 31-Dec-16 100.00
Jamunibas Pvt.Ltd., Janakpur-9,Nepal DLP
(2times)
Janaki Medical-Sabela-
M/S Y.P. Construction Pvt.
Paterwa Sadak (From 11.60 20-Sep-16 19-Sep-17 12 months 19-Sep-17 25 118.13
Ltd. Tansen, Palpa
Inarwa to Kamala)
Pushpalpur-Ichhapur- M/S Roshan –Laxman Rekha
16.14 19-Apr-17 19-Apr-18 12 months 19-Apr-18 35 60
Tarapatti Road J.V., Janakpur-4, Dhanusha
M/S. Dhukuchhu Construction
Balhagoth-Saghara-Lakkad
11.51 Company Pvt.Ltd.Budhanagar- 15-Jan-17 16-Jan-18 12 months 16-Jan-18 20 85.52
Road
10 Kathmandu
M/S AMR-Pappu construction
Siraha-Sukhipur Road 18.96 Jv Pvt. Ltd., Tinkune, 19-Oct-15 19-Jan-17 15 months 4 months 28-Apr-17 14.00 137.70
Kathmandu Nepal
9 Siraha
Jamdaha-Lagadi-Gadiyani M/S Yakthunhang & BP JV,
17.00 13-Apr-17 13-Apr-18 12 months 13-Apr-18 0.00 61.64
Road Lahan-7
3
Under
Kataniya Bridge 0.03 SAI Builders 9-Jun-15 9-Oct-15 4 months 9-Oct-15 100.00
DLP
7.5
M/S Rautaha Construction
Gaighat-Phattepur Road 9.83 14-Jul-15 13-Sep-16 14 months months (2 29-Mar-17 95.00 138.46
Pvt.Ltd.Triyuga-2 Udayapur
times)
Tapeshwori- Bhagalpur-
Rampur Road ( Ch 00+ 000 Under
22.00 M/S Gaura -Pabitra JV. 30-Aug-16 30-Aug-17 12 months 30-Aug-17 100.00
Km to 22+ 000 Km) with DLP
PM of crossing structures
M/S. Pappu Construction ,
Janta Sadak 17.50 Pokhariya VDC-7, Parsa , 2-Mar-16 1-May-17 14 months 7 months 1-Dec-17 54.00 149.70
Nepal
M/S. Gauri Parbati Nirman
Aatmaram Path 13.01 Sewa Pvt.Ltd,Kalanki-14, 6-Apr-16 6-Jul-17 15 months 6-Jul-17 33 130.92
Kathmandu , Nepal
11 Parsa
Dhore-Pakaha-Bankatawa- M/S. Roshan/Rajan Jv, Under
28.50 11-Feb-16 11-Nov-17 21 months 7 months 11-Feb-18 100.00
Sonbarsa Road Janakpur, Dhanusha ,Nepal DLP
Sonbarsa-Gadi-Sakhuwa-
Prasauni-Mahuwan M/S. Roshan/Rajan Jv, Under
14.25 11-Feb-16 11-Nov-17 21 months 11-Nov-17 100
Ramnagari Padam Road Janakpur, Dhanusha ,Nepal DLP
Road
M/S. Ank-Lumbini JV,
Jandaul-Kusha Belhi 24.55 26-Apr-16 25-Jul-17 15 months 25-Jul-17 60 126.81
Kathmandu,Nepal
M/S. Pappu -Mrit Sanjivini JV
12 Saptari Kushaha-Belhi 16.23 26-Apr-16 25-Jul-17 15 months 25-Jul-17 65 126.81
Kalanki , Kathmandu, Nepal
Mahuli-Lohajara-
9.28 M/S Apex Uday J/V. 1-Mar-17 1-Mar-18 12 months 1-Mar-18 16.05 73.42
Hanumannagar Road
M/S. Sapna-Shivshakti-Merina
Kabigoth-Bariyarpur 7.94 5-May-16 29-Jul-17 15 months 5 months 24-Dec-17 70.00 128.65
Jv, Hetauda, Makwanpur
13 Bara
Kalaiya -Gunjbhawanipur- M/S Sapana-Shivashakti,
16.08 5-Feb-17 30-Apr-18 15 months 30-Apr-18 5 65.03
Malahi Road Hetauda, Makawanpur
4
M/S Dev & Sayar/Binod Sah
Kalaiya -Jaitapur Road 10.50 18-Sep-16 18-Sep-17 12 months 18-Sep-17 75 118.36
JV, Kathmandu.
Piparpati- Bairiya-Kotbali M/S. Sapna-Shivshakti-Merina Under
8.55 5-May-16 5-May-17 12 months 5-May-17 100.00
Road Jv, Hetauda, Makwanpur DLP
Sukrabare-Fakchamara- M/S Jagriti Nirwan Sewa , New
14 Terathum 17.11 31-Jan-16 30-Jan-17 12 months 30-Jan-17 45 181.64
Hakparaghat Road: Baneshwar, Kathmandu ,Nepal
M/S Oasis-Shree Jayanti JV,
Chainpur-Barhabise Road 16.00 8-May-16 7-Oct-17 17 months 7-Oct-17 5 109.28
Sankhuwasa Lazimpat
15 bha RamMandir – Okharbote – M/S Apex-Joshi JV, 2.5
18.55 5-Aug-16 5-Aug-17 12 months 24-Oct-17 35.00 106.97
Mawadin – Nundhaki Road Bijulibazar, Kathmandu, Nepal months
M/S PS/ Kirateshwar-Om
Bhojpur Mane Bhanjyang
12.50 Jamviyoung JV , Dillibazar, 1-Jan-16 30-Jun-17 18 months 5 months 28-Nov-17 31.00 127.78
-Rani bas- Ghodetar
Kathmandu ,Nepal
Upgrading works along with SBA-Marseli JV,Kapan- Under
8 25-Mar-16 14-Jun-16 3 months 14-Jun-16 100.00
8 RCC causeway in 4 Roads 1,Kathmandu DLP
Taksar-Gumba-Dalgaun- M/S SBA-Marseli J.V Kapan-1, Under
16 Bhojpur 15.00 14-Jul-15 18-Oct-16 15 months 7 months 14-May-17 70.00
Bhulke-Dhodhlekhani Road Kathmandu DLP
Tiwaribhanjyang-Chyangre-
M/S SBA-Marseli J.V Kapan-1,
Bastim-Thulodumma- 15.10 14-Jul-16 29-Apr-17 9.5 months 8 months 25-Dec-17 79.00 173.68
Kathmandu
Sanodumma Road
8.5
Bhojpur -Dingla - Mulpani - M/S Thodung-Waiba & Lama 15.5
13.36 1-Jan-16 15-Apr-17 months 6-Jan-18 30.00 148.38
Keureni pani Rd: JV , Kathmandu Nepal months
(2times)
Source:- SNRTP Progress Report, June 2017
5
From the above table we can see that 59 roads had been identified for upgrading road
projects. Among them 12 projects have been completed out of which 7 were completed
within estimated completion time and 5 were completed with range of time overrun of
33.33% to 63.63%. Further, Out of remaining 47 ongoing projects 29 have already incurred
time overrun and 18 projects are likely to be delayed. On 29 ongoing projects percentage of
time elapsed ranges from 101.24% to 178.23%. Though there may be various reasons for
such divergence, nonconformity to plans is observed from the above table no.6.
Figure: - 4.0 Number of upgrading road projects in SNRTP Eastern Cluster Districts.
Figure no 4 reflects the total number of road projects in each programmed district of SNRTP
Eastern Cluster. There are 17 districts in SNRTP Eastern Cluster among which only in 16
district upgrading road projects are running. Dhanusha has maximum 11 numbers of road
projects and Sindhupalchowk has no road project.
21
Time Period Extended
14
12
10
8
6
4
2 No. of projects
0
The above figure no. 4.1 shows the time period extended compare with number of upgrading
road projects. 8 project’s completion time period has been extended up to 6 months, 13
project’s completions time period has been extended within 6 month to 1 year and 1 project
completion time period has been extended within 1 year to 2 years.
Likely to be delayed
31%
Delayed
49%
Completed
20%
Figure 4.2. Total Project Scenario of SNRTP Eastern Cluster Upgrading Roads
Figure 4.2 illustrates that 20% i.e. 12 project out of 59 projects have been completed.
Similarly, 49% i.e. 29 projects are delayed from estimated completion date and 31% i.e. 18
projects are likely to be delayed from estimated completion time.
22
4.2 Output of questionnaire Survey
Questionnaires were collected from concerned engineers of employers, consultants and
contractors. Collected questionnaire were analyzed and then ranked using relative importance
index. Views of employer, consultants and contractors were calculated and ranked using
relative importance index. And also overall ranking was calculated based on relative
importance index.
Table:-7 Factors influencing time overrun from point view of employer, contractor,
consultant and average weighted of them.
Weighted
Factors Causing Time Employer Contractor Consultant
Average
Overrun
RII Rank RII Rank RII Rank RII Rank
Low Bid 0.825 3 0.675 4 0.754 3 0.768 2
legal dispute between various
0.45 27 0.375 28 0.446 28 0.432 28
parties
Problem in land acquisition,
0.525 16 0.5 14 0.631 7 0.557 14
utility relocation
Adhoc Contract Duration
0.6375 9 0.6 6 0.585 9 0.611 9
adopted.
Minimum/Ineffective delay
0.525 16 0.4 27 0.569 12 0.514 16
penalties
Incomplete design and drawing 0.475 25 0.45 22 0.462 25 0.465 23
Delay in delivery the site 0.4875 23 0.45 22 0.415 30 0.454 24
Poor communication and
0.4125 33 0.425 24 0.508 20 0.449 26
coordination
Late in revising and approving
0.4875 23 0.55 10 0.462 25 0.492 19
design & documents
Variations and additional works 0.6 13 0.6 6 0.508 20 0.568 12
Delay in payment of completed
0.4125 33 0.475 17 0.492 22 0.454 24
works.
Poor site management 0.8875 1 0.525 11 0.846 1 0.795 1
Inadequate capability 0.6125 10 0.5 14 0.569 12 0.573 11
Incompetence or inadequate
0.85 2 0.575 8 0.708 5 0.741 5
number of technical staff
Absence of lead contractor in
0.6125 10 0.375 28 0.538 15 0.535 15
case of JV
Lack of proper division of
responsibility by contractors in 0.775 5 0.725 2 0.754 3 0.757 3
JV
Ineffective planning and
0.8 4 0.575 8 0.785 2 0.746 4
scheduling of project
Rework due to errors during
0.5 21 0.475 17 0.538 15 0.508 17
construction
Cash flow problem 0.5875 15 0.475 17 0.585 9 0.562 13
Claims 0.375 35 0.35 32 0.523 18 0.422 32
Shortage of materials 0.35 37 0.525 11 0.462 25 0.427 31
Absence of material stock at
0.525 16 0.375 28 0.523 18 0.492 19
site
Shortage of spare part 0.375 35 0.35 32 0.369 33 0.373 36
Frequent breakdown 0.425 32 0.3 37 0.338 36 0.368 38
Inadequate modern equipment 0.6125 10 0.7 3 0.615 8 0.632 7
Shortage of skilled labor 0.7375 6 0.8 1 0.662 6 0.724 6
Poor workmanship 0.6 13 0.525 11 0.385 32 0.508 17
23
Strike 0.525 16 0.425 24 0.323 37 0.432 28
Complexity of project design 0.3375 38 0.325 34 0.446 28 0.373 36
Insufficient data collection and
0.6625 8 0.425 24 0.585 9 0.584 10
survey before design
Incompetent design team 0.675 7 0.625 5 0.569 12 0.627 8
Delay in producing, finalizing
0.4375 29 0.3 37 0.369 33 0.384 35
or updating design documents
Delay in performing inspection
0.4375 29 0.325 34 0.4 31 0.4 33
and testing
Local objection and
0.45 27 0.325 34 0.477 24 0.432 28
interventions
IEE and EIA approvals 0.5125 20 0.375 28 0.538 15 0.492 19
Natural Disasters (Flood,
0.5 21 0.475 17 0.354 35 0.443 27
landslide, earthquakes.)
Political factors like strikes,
0.4375 29 0.475 17 0.308 38 0.4 33
hindrances
Effect of social and cultural
0.4625 26 0.5 14 0.492 22 0.481 22
factors
Table no. 7 depicts the relative importance index and respective ranking from view point of
contractor, consultant and client individually and also their weighted average on factors
relating to cause time overrun. Annex B, C, D &E Shows the relative importance indices and
the relative ranking by contractor, consultant and client individually and on weighted average
of the 38 lists of factors that are considered to be cause of delay in SNRTP Eastern Cluster
Upgrading Roads.
Figure 4.3. Top 10 cause of schedule overrun from point view of employer
Above figure shows the client representative respondent's view on causes of delay in
upgrading road projects of SNRTP Eastern Cluster. According to employer responses, Poor
Site Management (RII =0.8875) of contractor related factor is being ranked first causes of
delay, incompetent or inadequate number of technical staff of contractor (RII=0.85) of
contractor related factor is ranked second, low bid of contract(RII=0.825) of contract/project
24
related factor is ranked third, ineffective planning & scheduling project(RII=0.8) of
contractor related factor is ranked fourth, lack of proper division of responsibility by
contractor in JV(RII=0.775) of contractor related factor is ranked fifth, shortage of skilled
labor(RII=0.7375) of labor related factor is ranked sixth, incompetent design team
(RII=0.675) of consultant/designer related factor is ranked seventh. Similarly, absence of lead
contractor in case of JV of contractor related factor, inadequate capability of contractor
related factor and inadequate modern equipment of equipment related factor(RII=0.6125) are
equally ranked to eight.
The percentile frequencies of the Client/Employer respondents response on top ten cause of
schedule overrun is shown in table below.
Table 8:- Top 10 cause of delay from point view of client categorized into different group
Extreme Moderate
Cause of Delay Very Slightly Not
S Ran ly ly
categorized under Significa Significa Signific
N k Significa Significan RII
different groups nt nt ant
nt t
1 1 Poor site management 50% 43.75% 6.25% 0 0 0.8875
Incompetence or
2 2 inadequate number of 25% 75% 0 0 0 0.85
technical staff
3 3 Low Bid 43.75% 25% 31.25% 0 0 0.825
Ineffective planning and
4 4 18.75% 68.75% 6.25% 6.25% 0 0.8
scheduling of project
Lack of proper division of
5 5 responsibility by 25% 37.5% 37.5% 0 0 0.775
contractors in JV
6 6 Shortage of skilled labor 18.75% 31.25% 50% 0 0 0.7375
7 7 Incompetent design team 18.75% 18.75% 43.75% 18.75% 0 0.675
Absence of lead contractor
8 8 18.75% 25% 12.5% 31.25% 0 0.6125
in case of JV
9 9 Inadequate capability 6.25% 31.25% 37.5% 12.5% 0 0.6125
Inadequate modern
10 10 6.25% 31.25% 31.25% 25% 0 0.6125
equipment
25
0.55
0.58
0.58
0.6
0.6
0.63
0.68
0.7
0.73
0.8
Figure 4.4 Top 10 cause of schedule overrun from point view of Contractor.
The figure 4.4 shows the contractor representative respondent's view on causes of delay in
upgrading road projects of SNRTP Eastern Cluster. According to contractor representative
responses, shortage of skilled labor (RII =0.80) of labor related factor is being ranked the
first causes of delay, lack of proper division of responsibility by contractors in JV
(RII=0.725) of contractor related factor is ranked second, inadequate modern equipment
(RII=0.675) of equipment related factor is ranked third, low bidding of contract(RII=0.675)
of contract/project related factor is ranked fourth, incompetent design team (RII=0.625) of
consultant/designer related factor is ranked fifth, adhoc contract duration &variations and
additional works adopted of client related factors (RII=0.6) are ranked sixth, incompetence or
inadequate number of technical staffs and ineffective planning and scheduling of project
(RII=0.575) of contractor related factors are equally rated and ranked eight. Similarly, late in
revising and approving design & documents (RII=0.55) of client related factor is ranked as
tenth.
The percentile frequencies of the Contractor respondents response on top ten cause of
schedule overrun is shown in table below
Table 9:- Top 10 cause of delay from point view of contractor categorized into different
group
26
Duration adopted.
Variations and
7 7 0 25% 50% 25% 0 0.6
additional works
Incompetence or
8 8 inadequate number of 0 25% 37.5% 37.5% 0 0.575
technical staff
Ineffective planning and
9 9 0 25% 37.5% 37.5% 0 0.575
scheduling of project
Late in revising and
10 10 approving design & 0 37.5% 25% 12.5% 0 0.55
documents
0.59
0.59
0.57
0.63
0.66
0.71
0.75
0.75
0.79
0.85
Figure 4.5 Top 10 cause of schedule overrun from point view of Consultant
The figure 4.5 shows the consultant representative respondent's view on causes of delay in
upgrading road projects of SNRTP Eastern Cluster. According to consultant representative
responses, poor site management (RII =0.846) of contractor related factor is being ranked
the first causes of delay, ineffective planning and scheduling of project (RII=0.785) of
contractor related factor is ranked second, low biding of contract of project/contract related
factor & lack of proper division of responsibility by contractors in JV of contractor related
factor (RII=0.754) are equally ranked as third, incompetence or inadequate number of
technical staff(RII=0.708) of contractor related factor is ranked fifth, shortage of skilled labor
(RII=0.631) of labor related factor is ranked sixth, problem in land acquisition, utility
relocation (RII=0.631) of client related factor is ranked seventh, inadequate modern
equipment (RII=0.569) of equipment related factor is ranked eight , similarly, insufficient
data collection and survey before design of consultant/designer related factor and cash flow
problem of contractor related factor (RII=0.585) are equally ranked as ninth.
The percentile frequencies of the Consultant respondents response on top ten cause of
schedule overrun is shown in table below
27
Table 10:- Top 10 cause of delay from point view of consultant categorized into different
group
Extremel Moderate
Cause of Delay Very Slightly Not
Ran y ly RII
Sn categorized under Significa Significa Significa
k Significan Significan
different groups nt nt nt
t t
28
4.2.4 Top 10 causes of schedule overrun from point of average weighted
view of Contractor, Consultant and Employer
0.58
0.61
0.63
0.63
0.72
0.74
0.75
0.76
0.77
0.8
Figure 4.6. Top 10 cause of schedule overrun from overall average weighted of point view of
employer, contractor and consultant.
The figure 4.6 shows the overall average weighted of point of views of client, contractor and
consultant representatives respondent's view on causes of delay in upgrading road projects of
SNRTP Eastern Cluster. According to their responses, poor site management (RII =0.795)
of contractor related factor is being ranked the first causes of delay, low bid of contract
(RII=0.768) of project/contract related factor is ranked second, lack of proper division of
responsibility by contractors in JV (RII=0.757) of contractor related factors is ranked as third,
ineffective planning and scheduling of project(RII=0.746) of contractor related factors is
ranked fourth, incompetence or inadequate number of technical staff (RII=0.741)of contractor
related factor is ranked fifth, shortage of skilled labor (RII=0.724) of labor related factor is
ranked sixth, inadequate modern equipment (RII=0.632) of equipment related factors is
ranked seventh , incompetent design team (RII=0.627) of consultant/designer related factors
is ranked eight, adhoc contract duration adopted(RII=0.611) of project/contract related factor
is ranked ninth. Similarly, insufficient data collection and survey before design (RII=0.584)
of consultant/designer related factor is ranked tenth.
The percentile frequencies of the average weighted of Client, Contractor and Consultant
respondents response on top ten cause of schedule overrun is shown in table below:
29
Table 11:- Top 10 cause of delay from point view from overall average weighted of point
view of employer, contractor and consultant.
Extremel
Cause of Delay Very Moderatel Slightly Not
Ran y RII
Sn categorized under Significa y Signific Significa
k Significan
different groups nt Significant ant nt
t
0.43
0.47
0.51
0.56
0.61
0.77
In this category, from overall average weighted of contractor, consultant and client
respondents point view, low bidding of contract (traditional selection procedure) is the most
30
governing factor with relative importance index of 0.768 and legal dispute between various
parties with relative importance index 0.432 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents’ response on
most governing factor of contract related factor ie low bidding of contract is shown in bar
diagram as below.
0
100% 12.5
90% 31.25 15.39
0
80%
70% 50
25 Not Significant
60% 46.15 Slightly Significant
50% Moderately Significant
Very Significant
40% Extremely Significant
30% 25
43.75
20% 30.77
10% 12.5
0%
Client Contractor Consultant
Figure 4.8: Client, Contractor & Consultant’s View on Low Bid (the most governing factor
on project & contract related factors.)
0.45
0.45
0.45
0.49
0.57
On client related causes of delay, from overall average weighted of contractor, consultant and
client respondents point of view, variation and additional works is the most governing factor
with relative importance index of 0.568 and poor communication and coordination among
various parties with relative importance index 0.449 is the least governing factor causing
delay.
The percentile frequencies of the Client, Contractor and Consultant respondents response on
most governing factor of client related factor i.e. Variation and additional works is shown in
bar diagram below:
31
100
25
90
25
80 23.08
70
Not Significant
60 31.25 Slightly Significant
50
50 Moderately Significant
Very Significant
40 53.85 Extremely Significant
30
37.5
20 25
10 7.69
0
Client Contractor Consultant
Figure 4.10:. Client, Contractor & Consultant’s view on variation and additional works (the
most governing factor on Client related factors.)
0.42
0.51
0.54
0.56
0.57
0.74
0.75
0.76
0.8
On contractor related causes of delay, from overall average weighted of contractor, consultant
and client respondents point of view, Poor site management by contractor is the most
governing factor with relative importance index of 0.795 and claim by contractor with
relative importance index 0.422 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents response on
most governing factor of Contractor related factor i.e. Poor site management is shown in bar
diagram below.
32
0 0
6.25
100%
25 23.08
90%
80% 43.75
12.5
70%
30.77
Not Significant
60% Slightly Significant
50% 37.5 Moderately Significant
Very Significant
40% Extremely Significant
30% 50 46.15
20% 25
10% 0
0%
Client Contractor Consultant
Fig: 4.12 Client, Contractor & Consultant’s View on Poor site management (the most
governing factor on Contractor related factors.)
0.43
0.49
On material related causes of delay, from overall average weighted of contractor, consultant
and client respondents point of view, absence of material stock at site is the most governing
factor with relative importance index of 0.492 and shortage of material with relative
importance index 0.427 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents’ response on
most governing factor of material related factor ie Absence of material stock at site is shown
in bar diagram below.
33
6.25 7.69
100%
90%
80% 37.5
62.5 46.15
70%
Not Significant
60% Slightly Significant
50% Moderately Significant
0 Very Significant
40% 43.75 23.08 Extremely Significant
30% 25
20%
23.08
10% 12.5 12.5
0%
Client Contractor Consultant
Figure:4.14. Client, Contractor & Consultant’s view on absence of material stock at site (the
most governing factor on materials related factors.).
0.37
0.37
0.63
On equipment related factors causing delay, from overall average weighted of contractor,
consultant and client respondents point of view, Inadequate modern equipment is the most
governing factor with relative importance index of 0.632 and frequent breakdown of
equipment with relative importance index 0.368 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents’ response on
most governing factor of Equipment related factor ie inadequate modern equipment is
shown in bar diagram below.
34
100% 12.5
90% 15.39
25
80%
37.5
70%
38.46 Not Significant
60% 31.25 Slightly Significant
50% Moderately Significant
Very Significant
40% Extremely Significant
37.5
30% 31.25
38.46
20%
10% 12.5 0
6.25
0%
Client Contractor Consultant
Figure: 4.16.Client, Contractor & Consultant’s View on inadequate modern equipment (the
most governing factor on equipment related factors.)
0.43
0.51
0.72
On labor related factors causing delay, from overall average weighted of contractor,
consultant and client respondents point of view, shortage of skilled labor is the most
governing factor with relative importance index of 0.724 and strike by labor with relative
importance index 0.432 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents’ response on
most governing factor of Labor related factor ie Shortage of skilled labor is shown in bar
diagram below
35
100%
25
90%
80% 50
70% 53.85
Not Significant
60% Slightly Significant
50
50% Moderately Significant
Very Significant
40% 31.25 Extremely Significant
30% 30.77
20% 25
18.75
10% 7.69
0%
Client Contractor Consultant
Figure: 4.18.Client, Contractor & Consultant’s View on Shortage of skilled labor (the most
governing factor on equipment related factors.)
0.37
0.38
0.4
0.58
0.63
On consultant and designer related factors causing delay, from overall average weighted of
contractor, consultant and client respondents point of view, incompetent design team is the
most governing factor with relative importance index of 0.627 and complexity of project
design with relative importance index 0.373 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents response on
most governing factor of Consultant & Designer related factor i.e. Incompetent design team
is shown in bar diagram below.
36
100%
18.75
90%
38.46
80% 0
70% 25
43.75 Not Significant
60% Slightly Significant
50% Moderately Significant
38.46
Very Significant
40% Extremely Significant
37.5
18.75
30%
20%
18.75 23.08
10% 12.5 0
0%
Client Contractor Consultant
Figure: 4.20.Client, Contractor & Consultant’s View on Incompetent design team (the most
governing factor on equipment related factors.)
0.43
0.49
0.4 0.41 0.42 0.43 0.44 0.45 0.46 0.47 0.48 0.49 0.5
On other authority/stakeholder related factors causing delay, from overall average weighted
of contractor, consultant and client respondents point of view, IEE/EIA approval is the most
governing factor with relative importance index of 0.492 and local objection and intervention
with relative importance index 0.432 is the least governing factor causing delay.
The percentile frequencies of the Client, Contractor and Consultant respondents response on
most governing factor of Other Authority/Stakeholder related factor i.e. IEE/EIA approval
is shown in bar diagram below.
37
100%
90% 30.77
37.5
43.75
80%
70%
23.08 Not Significant
60% 6.25 Slightly Significant
50% Moderately Significant
50 Very Significant
40% Extremely Significant
37.5 23.08
30%
20%
10% 12.5
0%
Client Contractor Consultant
Figure: 4.22.Client, Contractor & Consultant’s View on IEE/EIA approval (the most
governing factor on equipment related factors.)
0.4
0.44
0.48
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5
On external related factors causing delay, from overall average weighted of contractor,
consultant and client respondents point of view, effect of social and cultural factors is the
most governing factor with relative importance index of 0.481 and Political factors like
strike, hindrances with relative importance index 0.4 is the least governing factor causing
delay.
The percentile frequencies of the Client, Contractor and Consultant respondents’ response on
most governing factor of Consultant & Designer related factor ie Effect of social and cultural
factors is shown in bar diagram below.
38
100% 12.5 12.5 15.39
90%
80%
70% 38.46
50
62.5 Not Significant
60% Slightly Significant
50% Moderately Significant
Very Significant
40% Extremely Significant
12.5 30.77
30%
12.5
20%
10%
0%
Client Contractor Consultant
Fig: 4.24.Client, Contractor & Consultant’s View on Effect of social and cultural factors (the
most governing factor on equipment related factors.)
The Null Hypothesis (HO) is: -There is no agreement in the ranking of causes of time
overrun between two groups of respondents
The Alternative Hypothesis (HA) is: -There is agreement in the ranking of causes of time
overrun between two groups of respondents
The spearman correlation coefficient (ρ) was calculated and tabulated as shown below in
Table In order to decide whether to accept or reject the null hypothesis, the level of
significance 95% (P = 0.05) was used. This allows to state whether or not there was
"agreement" between respondents response.
If the calculated value of ρ is greater than the critical value, H0 is rejected, i.e. there is
evidence of a statistically significant agreement between the groups. If the calculated value of
ρ is less than the critical value, H0 is accepted, i.e. there is no evidence of a statistically
significant agreement between the two groups
39
0.670752 Significant Ho
Client Vs Contractor 0.330
rejected
Contractor Vs 0.581026 Significant Ho
0.330
Consultant rejected
0.736952 Significant Ho
Client Vs Consultant 0.330
rejected
In this case, with a significance level of 95% (P = 0.05), the calculated value of ρ for all the
three group cases are greater than the critical values of ρ, so the hypothesis that there is no
significant agreement between the respondents is rejected i.e. the null hypothesis is rejected
and alternative hypothesis I.e. there is agreement in the ranking of causes of time overrun
between two groups of respondents is accepted. There is correlation between the attitudes of
the respondents in all the three groups. In nutshell, most of respondent have similar
perception about the factors causing time overrun.
40
Chapter 5: Conclusion and Recommendation
This chapter includes the conclusions and recommendations that would help in solving the
problem of delay at construction in SNRTP Eastern Cluster Roads Upgrading Project. For
this research desk study was used to identify the existence and extent of time overrun of road
upgrading projects in SNRTP Eastern Cluster. Questionnaire survey was done with client,
contractors and consultant representative to identify the causes of delay affecting time
overrun in the SNRTP Eastern Cluster road upgrading project. The data gathered from the
survey were analyzed using the relative importance index and spearman rank correlation
coefficient method was used to test the agreements on causes of Time overrun among Client,
Contractor and Consultant.
5.1. Conclusion
Based on the results of the analysis of desk study and respondents’ responses the following
conclusions are drawn:
1. The first specific objective was to identify whether time overrun exist or not and evaluate
the extent of time of upgrading road construction. Out of 59 road projects investigated in
the research, 12 projects were completed out of which 7 were completed within estimated
completion time and 5 were completed with range of time overrun of 33.33% to 63.63%.
Further, Out of remaining 47 ongoing projects 29 have already incurred time overrun and
18 projects are likely to be delayed. On 29 ongoing projects percentage of time elapsed
ranges from 101.24% to 178.23%.
2. The second specific objective was to identify and rank factors influencing time overruns
in road upgrading project in SNRTP Eastern Cluster. The total of 38 factor were
identified in this thesis and top 10 causes of delay identified from overall average
weighted of point of views of client, contractor and consultant representatives
respondent's view were poor site management (RII =0.795), low bid of contract
(RII=0.768), lack of proper division of responsibility by contractors in JV (RII=0.757),
ineffective planning and scheduling of project(RII=0.746), incompetence or inadequate
number of technical staff (RII=0.741), shortage of skilled labor (RII=0.724), inadequate
modern equipment (RII=0.632),incompetent design team (RII=0.627), adhoc contract
duration adopted(RII=0.611), insufficient data collection and survey before
design(RII=0.584) .
3. According to employer representative response top ten causes identified were poor site
management(RII=0.8875), incompetent or inadequate number of technical staff of
contractor (RII=0.85), low bid (RII=0.825), ineffective planning & scheduling
project(RII=0.8), lack of proper division of responsibility by contractor in JV(RII=0.775),
shortage of skilled labor(RII=0.7375), incompetent design team (RII=0.675), absence of
lead contractor in case of JV(RII=0.6125), inadequate capability(RII=0.6125) and
inadequate modern equipment (RII=0.6125).
4. According to contractor representative responses, top ten causes identified were shortage
of skilled labor (RII =0.80), lack of proper division of responsibility by contractors in JV
(RII=0.725), inadequate modern equipment (RII=0.675), low bidding of
contract(RII=0.675), incompetent design team (RII=0.625), adhoc contract duration
adopted(RII=0.6),variations and additional works (RII=0.6), incompetence or inadequate
number of technical staffs (RII=0.575), ineffective planning and scheduling of project
(RII=0.575) ,late in revising and approving design & documents (RII=0.55..
5. According to consultant representative responses, top ten causes poor site management
(RII =0.846), ineffective planning and scheduling of project (RII=0.785), low biding of
41
contract (RII=0.754),lack of proper division of responsibility by contractors in JV
(RII=0.754), incompetence or inadequate number of technical staff(RII=0.708), shortage
of skilled labor (RII=0.631), problem in land acquisition, utility relocation (RII=0.631),
inadequate modern equipment (RII=0.569),insufficient data collection and survey before
design (RII=0.585) and cash flow problem (RII=0.585) were identified.
6. The spearman correlation coefficient of client and contractor calculated was 0.67,client
and consultant was 0.736 and of contractor and consultant was0.581 which were greater
than critical values at significance level of 5% so concluded that there was correlation
between the attitudes of the respondents in all the three groups.
5.2 Recommendation
The following points are recommended to all parties in order to minimize and control time
overrun in SNRTP upgrading road projects.
.
1. It is recommended to have good site management system in the project by proper
planning and management of resources (material, manpower, equipment, capital),
proper scheduling of work, safety and risk management.
3. It is recommended to ask clarification of rate analysis of unnatural low bidding (as per
PPR2064, Rule 65(2)) and asking for additional performance security (as per PPR
2064, Rule 65(3)) to control unusual low bid.
42
Bibliography
1. Alaghbari M.W, Razali A, Azizah S and Ernawati P (2007). The significant
factors causing delay of building construction projects in Malaysia. Journal of
Engineering, Construction and Architectural Management, Vol.14, No.2, No. 8, PP.
192-206.
2. Ahikari R P (2014) Lecture notes, Advance Construction Management. Pulchowk
Campus
3. Arditi D., and F. Yasamis (1997), Reasons for delays in public projects in Turkey.
Journal of Construction Management and Economics, Vol. 3, No.12, pp. 171-181.
4. Assaf S. and Hejji S (2006), Causes of delay in large construction projects.
International Journal of Project Management, Vol. 24, No. 4, pp. 349-357
5. Aziz R, Asmaa A and Hakam A (2014), Exploring delay causes of road
construction projects in Egypt. Alexandria Engineering Journal Volume 55, Issue
2, June 2016, Pages 1515-1539
6. Asnaashari E, Knight A, Hurst A, and Farahani S.S (2011) Causes of
Construction Delays In Iran. Project Management, Logistics, Technology and
Environment https://www.researchgate.net/publication/267723885
7. Dallakoti K (2014) Lecture Notes, Procument Management. Pulchowk Campus.
8. Faridi, A. and Sayegh, S. (2006) ‘Significant factors causing delay in the UAE
construction industry. Construction Management and Economics, 24, 1167–1176.
9. Głuszak & A. Lesniak (2015) Construction delays in clients opinion – multivariate
statistical analysis. Creative Construction Conference 2015 (CCC2015)
10. http://www.fcan.org.np
11. Kaliba C, Muya M &Mumba, K.(2009). Cost Escalation and Schedule Delay in
Road Construction Projects in Zambia. International Journal of Project
Management,Vol27, Issue 5, pp 522-531
12. Manavazhia MR, Adhikarib DK. (2002) Material and Equipment Procurement
Delays in Highway Projects in Nepal. International Journal Project Management; 20:
27-32
13. Mezher, T.C. and Tawil, W 1998, Causes of delay in the construction industry in
Lebanon.Engineering Construction and Architectural Management, Vol. 5, No.3, pp.
252-260.
14. Mustefa A.J (2015) Factors affecting time and cost overrun in road construction
projects in Addis ababa. Msc thesis Addis ababa
15. Project for Strenghtening the National Ruaral Transport Program(2016) Project
Operation manual version -2
16. Office Of Auditor General (2070) 51st Annual Report of Auditor General
17. Projects Progress Report and completion reports from CPCU lalitpur
18. Public Procurement Act 2007 and Public Procurement Rules 2008 ,Kathmandu: Nepal
Law Commission
19. Remon F.R, F.Aziz, Asmaa A & Hakam A (2016) Exploring delay causes of road
construction projects in Egypt. Alexandria Engineering Journal (2016) 55, 1515–1539
20. Shah M K, Shahi P B, Pandit, R & Pandey A (2016) Causes and Effect of Delay in
Construction Projects. IOSR Journal of Mechanical and Civil Engineering (IOSR-
JMCE) Volume 14, Issue 2 Ver. VI , PP 52-58
43
21. Sigdel P (2017) Factors Causing Delay of Bridge Projects Carried Out by Bridge
Project Mid Regional Sector-02,Department of Roads. MSC thesis, Pulchowk campus
22. Sitaula T (2015) Infrastructure Development in Nepal: Opportunities and Challenges
for Engineers.
23. Stumpf, G. (2000). Schedule delay analysis.Construction Engineering Journal.
42(7):32–43
24. Suwal A & S.K Shrestha.(2016) Causes of Delays of motorable bridge construction
under postal highway projects, Department of Roads. Journal of advanced college of
engineering and management, vol. 2, 2016.
25. Theodore J and Trauner Jr. (2009). Types of Construction Delays. Construction
Delays (SecondEdition), 2009, Pages 25-36
26. UK Standard IndustrialClassification of EconomicActivities( 2007)
27. Williams T (2003) Assessing extension of time delays on major projects.
International J Journal of ProjectManager;21:19–26
44
ANNEX
45
ANNEX 1
Questionnaire Survey Form
Institute of Engineering
Pulchowk Campus
M.Sc. in Construction Management
Introduction
This questionnaire is prepared to obtain information from key informants with semi- structured
questions. The information is required for the academic research entitled “Factors causing delay in
Upgrading Road Projects of SNRTP Eastern Cluster” which is being conducted as partial
fulfillment of requirement on M.Sc. in construction management. The main objective of this research
is to find main factors causing delay in SNRTP eastern sector road upgrading and to make
recommendations based on the findings.
You are humbly requested to answer following questionnaires. Your response is highly valuable and
contributory to the outcome of the research. The information obtained from this questionnaire will be
solely used for the research purpose and all information is kept strictly confidential.
Thank you.
Suraj Bhandari
2070/MSCM/318
Pulchowk Campus.
a
vi Lack of good governance
3 Contractor Related
i Poor site management
ii Inadequate capability
Incompetence or inadequate number of technical
iii
staff
iv Absence of lead contractor in case of JV
Lack of proper division of responsibility by
v
contractors in JV
vi Ineffective planning and scheduling of project
vii Rework due to errors during construction
viii Cash flow problem
ix Claims
Material related problems
x a) Shortage
b) Absence of material stock at site
Equipment related problems
a) Shortage of spare part
xi
b) Frequent breakdown
c) Inadequate modern equipment
Labor related Problems
a) Shortage of skilled labor
xii
b) Poor workmanship
c) Strike
4 Consultant & Designer Related
i Complexity of project design
Insufficient data collection and survey before
ii
design
iii Incompetent design team
Delay in producing, finalizing or updating design
iv
documents
v Delay in performing inspection and testing
5 Other Authorities/Stakeholders Related
i Local objection and interventions
ii IEE and EIA approvals
6 External Related
i Natural Disasters (Flood, landslide, earthquakes.)
ii Political factors like strikes, hindrances
iii Effect of social and cultural factors
Respondent views and comments If you have comments on time overrun kindly request to write
here:…………………………………………………………………………………………………
b
ANNEX 2
RII Calculation Sheet of Consultant Point of View.
ES VS MS SS NS RII
SN Causes of Delay Rank Remarks
5 4 3 2 1
Project & Contract Related
1 Low Bid 4 6 0 2 1 0.754 3
2 legal dispute between various parties 1 1 4 1 6 0.446 28
3 Problem in land acquisition, utility relocation 3 3 3 1 3 0.631 7
4 Adhoc Contract Duration adopted. 1 2 5 5 0 0.585 9
5 Minimum/Ineffective delay penalties 2 2 3 4 2 0.569 12
6 Incomplete design and drawing 2 0 2 5 4 0.462 25
Client Related
1 Delay in delivery the site 1 1 1 5 5 0.415 30
2 Poor communication and coordination 1 2 3 4 3 0.508 20
Late in revising and approving design &
3 0 2 4 3 4 0.462 25
documents
4 Variations and additional works 0 1 7 3 2 0.508 20
5 Delay in payment of completed works. 2 2 1 3 5 0.492 22
Contractor Related
1 Poor site management 6 4 3 0 0 0.846 1
2 Inadequate capability 2 2 4 2 3 0.569 12
Incompetence or inadequate number of
3 3 3 5 2 0 0.708 5
technical staff
4 Absence of lead contractor in case of JV 0 3 5 3 2 0.538 15
Lack of proper division of responsibility by
5 4 3 5 1 0 0.754 3
contractors in JV
Ineffective planning and scheduling of
6 3 6 4 0 0 0.785 2
project
7 Rework due to errors during construction 1 2 5 2 3 0.538 15
8 Cash flow problem 2 2 4 3 2 0.585 9
9 Claims 1 3 2 4 3 0.523 18
Material Related Factors
10 Shortage 1 0 4 5 3 0.462 25
11 Absence of material stock at site 0 3 3 6 1 0.523 18
Equipment Related Factors
12 Shortage of spare part 0 1 2 5 4 0.369 33
13 Frequent breakdown 0 1 1 4 7 0.338 36
c
14 Inadequate modern equipment 0 5 5 2 1 0.615 8
Labor Related Factors
15 Shortage of skilled labor 1 4 7 0 1 0.662 6
16 Poor workmanship 0 0 3 6 4 0.385 32
17 Strike 0 0 2 4 7 0.323 37
Consultant & Designer Related
1 Complexity of project design 0 2 3 4 4 0.446 28
Insufficient data collection and survey before
2 1 3 4 4 1 0.585 9
design
3 Incompetent design team 0 3 5 5 0 0.569 12
Delay in producing, finalizing or updating
4 0 0 2 7 4 0.369 33
design documents
5 Delay in performing inspection and testing 0 1 1 8 3 0.4 31
Other Authority/Stakeholder Related
1 Local objection and interventions 0 3 2 5 3 0.477 24
2 IEE and EIA approvals 2 3 1 3 4 0.538 15
External Factors Related
Natural Disasters (Flood, landslide,
1 0 0 3 4 6 0.354 35
earthquakes.)
2 Political factors like strikes, hindrances 0 0 1 5 7 0.308 38
3 Effect of social and cultural factors 0 2 4 5 2 0.492 22
ANNEX 3
RII Calculation Sheet of Contractor Point of View
ES VS MS SS NS
SN Causes of Delay RII Rank Remarks
5 4 3 2 1
Project & Contract Related
1 Low Bid 1 2 4 1 0 0.675 4
2 legal dispute between various parties 0 1 1 2 4 0.375 28
3 Problem in land acquisition, utility relocation 2 0 0 4 2 0.5 14
4 Adhoc Contract Duration adopted. 0 4 1 2 1 0.6 6
5 Minimum/Ineffective delay penalties 0 0 2 4 2 0.4 27
6 Incomplete design and drawing 1 1 0 3 3 0.45 22
Client Related
1 Delay in delivery the site 0 1 2 3 2 0.45 22
2 Poor communication and coordination 0 2 0 3 3 0.425 24
3 Late in revising and approving design & 0 3 2 1 2 0.55 10
d
documents
4 Variations and additional works 0 2 4 2 0 0.6 6
5 Delay in payment of completed works. 1 1 0 4 2 0.475 17
Contractor Related
1 Poor site management 0 2 3 1 2 0.525 11
2 Inadequate capability 0 0 5 2 1 0.5 14
Incompetence or inadequate number of
3 0 2 3 3 0 0.575 8
technical staff
4 Absence of lead contractor in case of JV 0 0 2 3 3 0.375 28
Lack of proper division of responsibility by
5 1 4 2 1 0 0.725 2
contractors in JV
6 Ineffective planning and scheduling of project 0 2 3 3 0 0.575 8
7 Rework due to errors during construction 2 1 0 0 5 0.475 17
8 Cash flow problem 2 0 0 3 3 0.475 17
9 Claims 0 0 2 2 4 0.35 32
Material Related Factors
10 Shortage 1 0 2 5 0 0.525 11
11 Absence of material stock at site 0 1 2 0 5 0.375 28
Equipment Related Factors
12 Shortage of spare part 1 0 0 2 5 0.35 32
13 Frequent breakdown 0 1 0 1 6 0.3 37
14 Inadequate modern equipment 1 3 3 1 0 0.7 3
Labor Related Factors
15 Shortage of skilled labor 2 4 2 0 0 0.8 1
16 Poor workmanship 0 2 2 3 1 0.525 11
17 Strike 1 1 1 0 5 0.425 24
Consultant & Designer Related
1 Complexity of project design 1 0 0 1 6 0.325 34
Insufficient data collection and survey before
2 0 1 2 2 3 0.425 24
design
3 Incompetent design team 1 3 2 0 2 0.625 5
Delay in producing, finalizing or updating
4 0 1 0 1 6 0.3 37
design documents
5 Delay in performing inspection and testing 0 0 1 3 4 0.325 34
Other Authority/Stakeholder Related
1 Local objection and interventions 0 0 1 3 4 0.325 34
2 IEE and EIA approvals 0 1 0 4 3 0.375 28
External Factors Related
Natural Disasters (Flood, landslide,
1 1 1 0 4 2 0.475 17
earthquakes.)
2 Political factors like strikes, hindrances 0 2 1 3 2 0.475 17
e
3 Effect of social and cultural factors 0 2 1 4 1 0.5 14
ANNEX 4
RII Calculation Sheet of Client Point of View
N
ES VS MS SS Ran
SN Causes of Delay S RII Remarks
k
5 4 3 2 1
Project & Contract Related
1 Low Bid 7 4 5 0 0 0.825 3
2 legal dispute between various parties 0 2 4 6 4 0.45 27
3 Problem in land acquisition 0 4 6 2 4 0.525 16
4 Adhoc Contract Duration adopted. 0 7 6 2 1 0.6375 9
5 Minimum/Ineffective delay penalties 1 2 5 6 2 0.525 16
6 Incomplete design and drawing 1 3 2 5 5 0.475 25
Client Related
1 Delay in delivery the site 1 2 4 5 4 0.4875 23
Late in revising and approving design &
2 4 0 3 7 0.4875 23
2 documents
3 Variations and additional works 0 6 5 4 1 0.6 13
4 Delay in payment of completed works. 0 0 4 9 3 0.4125 33
Contractor Related
f
1 Poor site management 8 7 1 0 0 0.8875 1
2 Inadequate capability 1 5 6 2 2 0.6125 10
Incompetence or inadequate number of
4 12 0 0 0 0.85 2
3 technical staff
4 Absence of lead contractor in case of JV 3 4 2 5 2 0.6125 10
Lack of proper division of responsibility by
4 6 6 0 0 0.775 5
5 contractors in JV
6 Ineffective planning and scheduling of project 3 11 1 1 0 0.8 4
7 Rework due to errors during construction 1 2 5 4 4 0.5 21
8 Cash flow problem 2 4 4 3 3 0.5875 15
9 Claims 1 1 2 3 9 0.375 34
Material Related Factors
10 Shortage 0 1 3 3 9 0.35 36
11 Absence
of material stock at site 0 2 7 6 1 0.525 16
Equipment Related Factors
12 Shortage of spare part 1 2 1 2 10 0.375 34
13 Frequent breakdown 0 2 5 2 7 0.425 32
14 Inadequate modern equipment 1 5 5 4 1 0.6125 10
Labor Related Factors
15 Shortage of skilled labor 3 5 8 0 0 0.7375 6
16 Poor workmanship 2 5 2 5 2 0.6 13
17 Strike 4 1 2 3 6 0.525 16
Consultant & Designer Related
1 Complexity of project design 0 1 3 2 10 0.3375 37
Insufficient data collection and survey before
3 2 8 3 0 0.6625 8
2 design
3 Incompetent design team 3 3 7 3 0 0.675 7
Delay in producing, finalizing or updating
0 3 2 6 5 0.4375 29
4 design documents
5 Delay in performing inspection and testing 0 1 3 10 2 0.4375 29
Other Authority/Stakeholder Related
1 Local objection and interventions 2 2 2 2 8 0.45 27
2 IEE and EIA approvals 1 6 1 1 7 0.5125 20
External Factors Related
1 Natural Disasters (Flood, landslide, earthquakes.) 2 2 3 4 5 0.5 21
2 Political factors like strikes, hindrances 1 3 2 2 8 0.4375 29
3 Effect of social and cultural factors 1 1 2 10 2 0.4625 26
g
h
ANNEX 5
RII Calculation Sheet of Overall Average Weighted Point of View of Contractor,
Consultant & Client
V M S N
S ES
Causes of Delay S S S S MSI Rank
N
5 4 3 2 1
Project & Contract Related
1 Low Bid 12 12 9 3 1 0.768 2
2 legal dispute between various parties 1 4 9 9 14 0.432 28
3 Problem in land acquisition 5 7 9 7 9 0.557 14
4 Adhoc Contract Duration adopted. 1 13 12 9 2 0.611 9
5 Minimum/Ineffective delay penalties 3 4 10 14 6 0.514 16
6 Incomplete design and drawing 4 4 4 13 12 0.465 23
Client Related Factors
1 Delay in delivery the site 2 4 7 13 11 0.454 24
2 Poor communication and coordination 2 5 7 9 14 0.449 26
3 Late in revising and approving design & documents 2 9 6 7 13 0.492 19
4 Variations and additional works 0 9 16 9 3 0.568 12
5 Delay in payment of completed works. 3 3 5 16 10 0.454 24
Contractor Related Factors
1 Poor site management 14 13 7 1 2 0.795 1
2 Inadequate capability 3 7 15 6 6 0.573 11
Incompetence or inadequate number of technical
3 staff 7 17 8 5 0 0.741 5
4 Absence of lead contractor in case of JV 3 7 9 11 7 0.535 15
Lack of proper division of responsibility by
5 contractors in JV 9 13 13 2 0 0.757 3
6 Ineffective planning and scheduling of project 6 19 8 4 0 0.746 4
7 Rework due to errors during construction 4 5 10 6 12 0.508 17
8 Cash flow problem 6 6 8 9 8 0.562 13
9 Claims 2 4 6 9 16 0.422 32
Material Related Factors
11 Shortage 2 1 9 13 12 0.427 31
12 Absence of material stock at site 0 6 12 12 7 0.492 19
Equipment Related Factors
13 Shortage of spare part 2 3 3 9 20 0.373 36
14 Frequent breakdown 0 4 6 7 20 0.368 38
15 Inadequate modern equipment 2 13 13 7 2 0.632 7
Labor Related Factors
16 Shortage of skilled labor 6 13 17 0 1 0.724 6
i
17 Poor workmanship 2 7 7 14 7 0.508 17
18 Strike 5 2 5 7 18 0.432 28
Consultant/Designer Related Factors
1 Complexity of project design 1 3 6 7 20 0.373 36
2 Insufficient data collection and survey before design 4 6 14 9 4 0.584 10
3 Incompetent design team 4 9 14 8 2 0.627 8
Delay in producing, finalizing or updating design
4 documents 0 4 4 14 15 0.384 35
5 Delay in performing inspection and testing 0 2 5 21 9 0.4 33
Other Authority/Stakeholder Related Factor
1 Local objection and interventions 2 5 5 10 15 0.432 28
2 IEE and EIA approvals 3 10 2 8 14 0.492 19
External Related Factors
1 Natural Disasters (Flood, landslide, earthquakes.) 3 3 6 12 13 0.443 27
2 Political factors like strikes, hindrances 1 5 4 10 17 0.4 33
3 Effect of social and cultural factors 1 5 7 19 5 0.481 22
j
ANNEX 6
Spearman Correlation Coefficient of Client and Contractor
k
2
7 Poor workmanship 13 11 2 4
2
8 Strike 16 24 -8 64
2
9 Complexity of project design 38 34 4 16
3 Insufficient data collection and survey
0 before design 8 24 -16 256
3
1 Incompetent design team 7 5 2 4
3 Delay in producing, finalizing or updating
2 design documents 29 37 -8 64
3
3 Delay in performing inspection and testing 29 34 -5 25
3
4 Local objection and interventions 27 34 -7 49
3
5 IEE and EIA approvals 20 28 -8 64
3 Natural Disasters (Flood, landslide,
6 earthquakes.) 21 17 4 16
3
7 Political factors like strikes, hindrances 29 17 12 144
3
8 Effect of social and cultural factors 26 14 12 144
Total 3009
6 x (Σdi)^2 18054
l
ANNEX 7
1 Low Bid 3 3 0 0
2 legal dispute between various parties 27 28 -1 1
3 Problem in land acquisition 16 7 9 81
4 Adhoc Contract Duration adopted. 9 9 0 0
5 Minimum/Ineffective delay penalties 16 12 4 16
6 Incomplete design and drawing 25 25 0 0
7 Delay in delivery the site 23 30 -7 49
8 Poor communication and coordination 33 20 13 169
Late in revising and approving design & 23 25 -2 4
9 documents
1
13 20 -7 49
0 Variations and additional works
1
33 22 11 121
1 Delay in payment of completed works.
1
1 1 0 0
2 Poor site management
1
10 12 -2 4
3 Inadequate capability
1 Incompetence or inadequate number of 2 5 -3 9
4 technical staff
1
10 15 -5 25
5 Absence of lead contractor in case of JV
1 Lack of proper division of responsibility by 5 3 2 4
6 contractors in JV
1 Ineffective planning and scheduling of 4 2 2 4
7 project
1
21 15 6 36
8 Rework due to errors during construction
1
15 9 6 36
9 Cash flow problem
2
35 18 17 289
0 Claims
2
37 25 12 144
1 Shortage
2
16 18 -2 4
2 Absence of material stock at site
2
35 31 4 16
3 Shortage of spare part
2
32 36 -4 16
4 Frequent breakdown
2
10 8 2 4
5 Inadequate modern equipment
2 Shortage of skilled labor 6 6 0 0
m
6
2
13 33 -20 400
7 Poor workmanship
2
16 37 -21 441
8 Strike
2
38 28 10 100
9 Complexity of project design
3 Insufficient data collection and survey 8 9 -1 1
0 before design
3
7 12 -5 25
1 Incompetent design team
3 Delay in producing, finalizing or updating 29 34 -5 25
2 design documents
3
29 31 -2 4
3 Delay in performing inspection and testing
3
27 24 3 9
4 Local objection and interventions
3
20 15 5 25
5 IEE and EIA approvals
3 Natural Disasters (Flood, landslide, 21 35 -14 196
6 earthquakes.)
3
29 38 -9 81
7 Political factors like strikes, hindrances
3
26 22 4 16
8 Effect of social and cultural factors
Total 2404
6 x (Σdi)^2 14424
n
ANNEX 8
Spearman Correlation Coefficient of Contractor and Consultant
o
2
7 Poor workmanship 11 33 -22 484
2
8 Strike 24 37 -13 169
2
9 Complexity of project design 34 28 6 36
3 Insufficient data collection and survey
0 before design 24 9 15 225
3
1 Incompetent design team 5 12 -7 49
3 Delay in producing, finalizing or updating
2 design documents 37 34 3 9
3 Delay in performing inspection and
3 testing 34 31 3 9
3
4 Local objection and interventions 34 24 10 100
3
5 IEE and EIA approvals 28 15 13 169
3 Natural Disasters (Flood, landslide,
6 earthquakes.) 17 35 -18 324
3
7 Political factors like strikes, hindrances 17 38 -21 441
3
8 Effect of social and cultural factors 14 22 -8 64
Total 3829
2297
6 x (Σdi)^2 4
p
ANNEX 9
q
28 Akilash Kumar Mishra Roshan Construction Pvt.Ltd
29 Shrinkhala Nirwan Sewa Pvt. Ltd
30 Deepak Bhatt Dolidar
31 Chandra Kumar Negi Dolidar
32 Kalpana Subedi GON
33 Baburam Bhandari Contractor
34 Shivaram Pandey Contractor
35 Sumit Khadka Papu Construction
Purna Chandra Shakya Consolidated Engineer & Architect
36 service
37 Dipendra Poudel Robust Consultancy