PROGRESS AS ON Date: 02/03/2020: PA-SSV (Doubling) SSV-ALN (Doubling)
PROGRESS AS ON Date: 02/03/2020: PA-SSV (Doubling) SSV-ALN (Doubling)
PROGRESS AS ON Date: 02/03/2020: PA-SSV (Doubling) SSV-ALN (Doubling)
CUM.SCOPE
Done Today
CUMULATIVE DONE
CUMULATIVE DONE
CUM.DONE
CUM.BAL
DONE TODAY
DONE TODAY
BALANCE
BALANCE
SCOPE
SCOPE
Foundation : 214 0 214 0 383 5 273 110 5 597 487 110
Mast Erection : 176 0 152 24 305 0 128 177 0 481 280 201
Grouting : 176 0 132 44 305 4 36 269 4 481 168 313
Boom : 4 0 4 0 8 0 0 8 0 12 4 8
Bracket Erection : 189 5 128 61 343 0 0 343 5 532 128 404
Bracket Adjustment : 189 24 55 134 343 0 0 343 24 532 55 477
Wiring Catenary (Shots) : 11 0 7 4 17 0 0 17 0 28 7 21
Wiring Contact (Shots) : 11 0 4 7 17 0 0 17 0 28 4 24
D&C (SPAN) : 189 0 60 129 343 0 0 343 0 532 60 472
Bond 176 0 134 42 305 0 0 305 0 481 134 347
DONE
Dismentling Work
Foundation
MAST 3
Dropper Arm 43
Bracket 5 50
Guy Rod 4
BWA
OHE Shifting 7
OHE Temparory Anchoring
PROGRESS AS ON Date: 02/03/2020
SHINDWANE-SATARA (Section-2 &3)
DESCRIPTION SHIV-JJR(SECTION-2) JJR-SLP(SECTION-3) SLP-AKI(SECTION-3A) AKI-STR(SECTION-4)
CUM.SCOPE
Done Today
CUM.DONE
DONE TODAY
DONE TODAY
DONE TODAY
DONE TODAY
CUMULATIVE
CUMULATIVE
CUMULATIVE
CUMULATIVE
CUM.BAL
BALANCE
BALANCE
BALANCE
BALANCE
SCOPE
SCOPE
SCOPE
SCOPE
DONE
DONE
DONE
DONE
Foundation : 689 2 678 11 1235 0 1178 57 281 1 185 96 1101 0 891 210 3 3306 2932 374
Mast Erection : 604 0 534 70 1031 0 932 99 255 0 129 126 906 0 113 793 0 2796 1708 1088
Grouting : 604 0 500 104 1031 0 914 117 255 0 108 147 906 0 111 795 0 2796 1633 1163
Bridge Mast : 16 0 0 16 4 0 0 4 0 0 0 0 1 0 0 1 0 21 0 21
Tunnel Core Cutting 198 0 176 198 0 0 0 0 216 0 0 216 108 0 0 108 0 522 176 522
Tunnel Ragbolt Grouting 198 0 143 198 0 0 0 0 216 0 0 216 108 0 0 108 0 522 143 522
Tunnel Bracket Fixing 11 0 0 11 0 0 0 0 12 0 0 12 6 0 0 6 0 29 0 29
Boom : 20 0 18 2 80 0 44 36 2 0 0 2 50 0 0 50 0 152 62 90
Bracket Erection : 677 0 486 191 1313 0 818 495 289 0 6 283 1039 0 0 1039 0 3318 1310 2008
Wiring Catenary (Shots) : 35 0 25 10 51 0 21 30 12 0 0 12 51 0 0 51 0 149 46 103
Wiring Contact (Shots) : 35 0 23 12 51 0 19 32 12 0 0 12 51 0 0 51 0 149 42 107
Dropping & Clipping 676 0 369 307 1309 0 349 960 289 0 0 289 1039 0 0 1039 0 3313 718 2595
ATD Erection : 64 0 9 55 103 0 10 93 26 0 0 26 91 0 0 91 0 284 19 265
Bracket Adjustment : 678 0 432 246 1309 6 297 1012 289 0 0 289 1039 0 0 1039 6 3315 729 2586
ATD Adjustment : 64 0 6 58 103 0 9 94 26 0 0 26 91 0 0 91 0 284 15 269
Guy Rod : 112 0 72 40 208 0 117 91 38 0 0 38 202 0 0 202 0 560 189 371
A/C Wire : 35 0 15 20 51 0 15 36 12 0 0 12 51 0 0 51 0 149 30 119
Bond : 714 0 345 369 1239 0 299 940 209 0 0 209 1192 0 0 1192 0 3354 644 2710
Man Power Details
Foundation Work 23 9 5 0 37
Grouting 0 0 0 0 0
OHE Activity 16 0 16
Other activity 29 25 82 136
Total Single Line 189
Other Progress Total Double Line 132
1. 6 nos of BKT adjustment with SED checking at 71 KM without TRD staff. KEC Staff Strength 74
2. 2 nos 9TON Insulator erevction erection at 58KM. Total 395
3. OHE load transferred to new structure GPR yard.
4. 5 nos of Bracket Dismentaling and re-erection at GPR yard.
5. 4 nos of guy rod erection at SSV yard.
6. 3 nos of Hole drilled at 53km bridge mast.
* Scope changed in FSG and ALN YARD after site survay for CRS.
* No traffic block for mast erection and wiring provided.
Notes:-
1. 17-18 KM ROW issue.
2. 133-134 KM ROW issue.
3. Yard modification hold at 146km.
4. Doubloing work ongoing at 112km, work hampered.
Help required:-
1. 6 hr wiring traffic block and 4 hr mast erection traffic block.
Drawing Pending:-
1. Nira Bridge mast drawing approval.
2. Underground cable route plan approvel for Lonand
3. SIP pending for all yard except Fursungi and Saswad yard.
4. ESP Balance for Salpha.