Professional Documents
Culture Documents
T02 08 Pejovic - Tesovic - Bulatovic - Lukovic - Dvornik - Kovacevic - GNP2020
T02 08 Pejovic - Tesovic - Bulatovic - Lukovic - Dvornik - Kovacevic - GNP2020
T02 08 Pejovic - Tesovic - Bulatovic - Lukovic - Dvornik - Kovacevic - GNP2020
Abstract
The topic of this paper is the main structural design of Ro-Ro (roll on - roll of) ramp, within the
rehabilitation of the jetty No. 1 on the north shore at Port of Bar – Montenegrin main seaport.
Designed Ro-Ro ramp is located in the Port of Bar, in the jetty No. 1 root, with the main
purpose for loading and unloading of cargo and goods. Port of Adria JSC Bar engaged Institut
za građevinarstvo ltd from Podgorica to develop a detailed structural design.
The existing structure of the jetty No. 1, next to whom is located Ro-Ro ramp, is RC structure
founded on RC piles, whose top edge is at the level +3.00 m. The outer shore of jetty No. 1 and
No.2 is constructed by a stone embankment and still is not finished. Seafloor at jetty No. 1
north shore has a depth of maximum 11.00 m. Ro-Ro ramp is positioned in a way that minimum
draught of a boat of 7.50 m is provided.
The basis of the Ro-Ro ramp structure is rectangular, with dimensions 21.00x31.00 m. In order
to achieve completeness of the structure, beside the ramp was predicted execution of reinforced
concrete transition slab (d= 20 cm), with a slope of 6° (10.51%). Between the ramp and
transition slab is designed reinforced concrete L shaped wall, 2.90 and 4.50 m high. Along this
wall are designed wing walls. Toward to existing asphalt is designed new asphalt surfacing
(31.00x5.50 m), which consists of two layers of BNS 22 (d= 6 cm).
During designing, engineering challenge was to meet the requirements for valid Standards and
Rulebooks for designing of this type of structures, with an additional requirement for structure's
durability in a very aggressive environment. Supervisor during the execution of works was
Institut za građevinarstvo ltd Podgorica and Contractor was Aquamont Service ltd Herceg
Novi. Total price for construction of the designed structure was 680 339.40 €.
Key words
Reconstruction, jetty, port of Bar, Ro-Ro ramp
1 Prof. PhD, Faculty of Civil Engineering, University of Montenegro, Podgorica, Montenegro, radenko@ucg.ac.me
2 Civil Engineer, Institut za građevinarstvo ltd Podgorica, Montenegro, ivanatesovic90@gmail.com
3 Civil Engineer, Institut za građevinarstvo ltd Podgorica, Montenegro, bulatovicteodora95@gmail.com
4 Civil Engineer, Port od Adria AD Bar, Montenegro, olga.lukovic@portofadria.me
5 Civil Engineer, Aquamont ltd, Herceg Novi, Montenegro, zdenko.dvornik@aquamontservice.me
6 Civil Engineer, Pizzarotti Montenegro ltd Herceg Novi, Montenegro, danilce1@gmail.com
337
Civil En g in eerin g – S cien ce a n d Pra ctice
1. INTRODUCTION
At the Port of Bar, in the root of the jetty No. 1 north shore, is designed Ro-Ro ramp for
loading and unloading of cargo and goods. Existing structure of jetty No. 1, next to whom is
located Ro-Ro ramp, is RC structure foundated on piles, whose top edge is at the level +3.00 m.
The outer shore of jetty No. 1 and No. 2 is constructed by a stone embankment and still is not
finished. Perpendicular to the direction of jetty No. 1 north shore, waterside wall of new Ro-Ro
ramp is located. Seafloor at jetty No. 1 north shore has a depth of maximum 11.00 m. Ro-Ro ramp
is positioned in a way that minimum draught of a boat of 7.50 m is provided. On Figures 1 and 2 is
shown the location and layout plan of Ro-Ro ramp.
338
GNP 2 0 2 0
339
Civil En g in eerin g – S cien ce a n d Pra ctice
Structure of Ro-Ro ramp is reinforced concrete structure, with precast beams and „Omnia“
slab, and cast-in-place pile foundations with 60 cm diameter and 30 m length, at mutual space of
7.50 m in a longitudinal, and 5.00 m in transverse direction. Formwork for piles is steel tube Ø600,
with 8 mm wall thickness and reinforced concrete filling.
Loadbearing structure is a system of reinforced concrete slabs and beams in two orthogonal
directions. Main beams (50x70x690 cm) are positioned at axis B, C, D and E, in line with piles.
Main beams are at mutual spacing of 5.00 m. Edge beam at axis A is different from other main
beams (75x70x690 cm), with overhang at bottom side (25x40 cm), because of structural reasons.
In vertical direction, at axis 1,2,3,4 and 5, in line with piles, are positioned secondary beams
(30x40x440 cm). Secondary beams are at mutual spacing of 7.50 m. A part of construction
between axis C and E has a slope of 6° (10.51%) and 1% between axis A and C.
For reliance of main and secondary prefabricated beams during the assembly phase, special
square pile's caps (100x100x110 cm) were designed (Figure 5). These pile's caps are made from
steel plates, with reinforced concrete filling. Their connection with top edge of pile's tubes is
designed as welded connection. At the same time, plates have a role of formwork for capitel's
concrete.
340
GNP 2 0 2 0
Before the monolitization, on the existing concrete surface needs to be aplicated coat for
bonding of old and new concrete slab. During hte design, was paid attention to leave a rein-
forcement for monolitization of joints and continualization of „Omnia“ slabs. In final, monoliti-
zation slab above precast beams is executed, with additional reinforcement at the upper zone, so
there are formed continuous multispan beams in two orthogonal directions and slab with 30 cm
thickness.
At the contact between ground and ramp is designed cascade L shaped wall, 2.90 and
4.50 m high. Along these walls are predicted wing walls. There is point of support for transition
slab (20x450x3100 cm). At this point is formed expansion joint between structure of ramp and
transition slab. Expansion joint has a width of 2 cm, which needed to be filled with bitumen.
Toward to existing asphalt is designed new asphalt surfacing in width of 31.00 m and length
5.50 m, which is formed from two layers of BNS 22, 6 cm thickness.
In order to protect the seafloor in zone of boat's landing, there is prevised throwing of large
stone ruffle (0.1-0.2 m3), in layers of 1.00-1.20 m.
On figures 3 and 4 are presented a base view and characteristic longitudinal section of the
structure.
341
Civil En g in eerin g – S cien ce a n d Pra ctice
pile's caps. Surface preparation and method of coating application is executed according to the
manufacturer's recommendation. For reinforcement of slabs and beams was predicted protection by
galvanizing.
3. CONSTRUCTION WORKS
342
GNP 2 0 2 0
mounting of precast elements (main beams, secondary beams and „Omnia“ slabs). Mounting of
prefabricated elements was done after the achievement of 70% of the designed concrete grade,
but not earlier than 14 days;
after the mounting was finished, there was necessary to finish works on placing of
reinforcement for slab's upper zone and concreting of layer for monolitization;
concreting of transition slab and execution of asphalt surface;
during the building construction was performed adequate preparation for cathode protection
and after finishing of all works, final positions of cathode protection are executed;
cleaning and landscaping of the site.
Figure 8 – Installation of the pile’s formwork Figure 9 – Placing of the pile’s reinforcement
343
Civil En g in eerin g – S cien ce a n d Pra ctice
Figure 16 – Reinforcement of the upper zone Figure 17 – Ramp and transition slab
4. CONCLUSION
This design represents one successful structural solution, wherein is successfully applied
precast building system. During designing and execution of works, main task was to meet
rerquirements from valid Standards and Rulebooks for designing of maritime structures, and to
carry out requirements for structure's durability in a very aggressive environment. The main design
was developed in two months and the structure is executed and put into operation in four months.
LITERATURE
[1] Institut za građevinarstvo ltd (2018). Glavni projekat rekonstrukcije gata 1 – Sjeverna obala,
izgradnja Ro-Ro rampe u luci Bar.
[2] BS 6349-1:1998; BS 6349-2:1998; BS 6349-3:1998 and BS 6349-4:1998 (Maritime structures).
344