I Pekerjaan Persiapan
Pekerjaan Bongkaran+Pembersihan Ls 1,00 3.000.000,00 3.000.000,00
Sub Total I 3.000.000,00
II Pekerjaan Baja
Rangka Dinding Facade, Hollow 30*30*1,6 m2 70,96 250.000,00 17.738.875,00
Rangka atap teras hollow 30*30*1,6 + Atap Galvalume 0,4 m2 26,68 300.000,00 8.004.000,00
Rangka Lisplang hollow 30*30*1,6 m' 14,74 250.000,00 3.686.000,00
Sub Total II 29.428.875,00
III Pekerjaan Penutup Dinding (GRC)
GRC facade bag. Belakang (included cat ex. Jotun Jotashield) m2 70,96 95.000,00 6.740.772,50
GRC facade bag. Depan (included cat ex. Jotun Jotashield) m2 51,69 95.000,00 4.910.550,00
GRC facade plint uk. 300*300 m' 32,63 66.500,00 2.169.895,00
GRC Lisplang flat m2 9,22 95.000,00 875.425,00
GRC plint lisplank m' 36,86 66.500,00 2.451.190,00
Sub Total III 17.147.832,50
IV Pekerjaan Banner/Papan Nama
Banner 1 uk. 255*581, included Rangka+list m2 14,82 400.000,00 5.926.200,00
Banner 2 uk. 255*468, included Rangka+list m2 11,93 400.000,00 4.773.600,00
Banner 3 uk. 255*614, included Rangka+list m2 15,66 400.000,00 6.262.800,00
Banner 4 uk. 80*500, included Rangka+list m2 4,00 400.000,00 1.600.000,00
Sub Total IV 18.562.600,00
V Pekerjaan Lain-lain
Pekerjaan Plafond Gypsum (Rangka+cat) m2 26,72 110.000,00 2.939.585,00
Pekerjaan List plafon gypsum m' 39,76 18.000,00 715.680,00
Pekerjaan Talang m2 18,43 50.000,00 921.500,00
Pekerjaan Pipa Buangan Air Hujan PVC 4" D m2 8,00 90.000,00 720.000,00
Pekerjaan Downlight+Lampu LED 12W untuk teras bh 6,00 165.000,00 990.000,00
Pekerjaan lampu sorot spot light bh 4,00 325.000,00 1.300.000,00
Sub Total V 7.586.765,00
TOTAL 75.726.072,50
PPN (10% 7.572.607,25
GRAND TOTAL 83.298.679,75
DIBULATKAN 83.000.000,00
Terbilang : Delapan Puluh Tiga Juta Rupiah