Length 76.

70
Width 4.50
thickness 0.15
Volume 51.77 cu.m

RMC 284,748.75
25,886.25

Formworks 26.00 pcs 14,300.00


rebar 14.00 pcs 4,900.00
G.I wire 1.00 spool 1,500.00
Basecourse 52.00 cu.m 44,200.00
Equipment Works 33,750.00
Roller 33,000.00

Labor Works 62,127.00

Mobilization/Demobilization 500.00 15,000.00

519,412.00
Qoutation For Roadworks
Attention to :
Mr. Jose kison

Location:
Brgy. San Jose Lipa City
Batangas

Scope of Works:
*Surplus Common Excavation
*Subgrade Preparation
*Aggregate Basecourse
*PCCP pouring

Bill of Quantities

* Formworks 26.00 pcs 14,300.00


* Rebar 16mm 14.00 pcs 4,900.00
* G.I wire 1.00 spool 1,500.00
* Basecourse 25.00 cu.m 21,250.00
* ReadyMixConcrete 52.00 cu.m 284,748.75

* Equipment Works
a. Excavator 33,750.00
b. Road Roller 33,000.00
c.Mobilization/Demobilization 20,000.00

* Labor Works
a. Preparation and Surplus Excavation 62,127.00
b. Concrete Pouring 25,886.25
501,462.00

OCM and Contractors profit(5%) 25,073.10


TOTAL 526,535.10