Professional Documents
Culture Documents
Jimma University Jimma Institute of Technology (Jit) University-Industry Linkage and Technology Transfer Office
Jimma University Jimma Institute of Technology (Jit) University-Industry Linkage and Technology Transfer Office
Jimma University Jimma Institute of Technology (Jit) University-Industry Linkage and Technology Transfer Office
JIMMA UNIVERSITY
Jimma Institute of Technology
(JiT)
University-Industry Linkage and
Technology Transfer Office
Weekday Activities
Monday -Most buildings are constructing the 7th floor beam. So I tried to see the obviously
activities.
Tuesday -I saw while they were casting B23 wing one seventh floor slab.
Friday I tried to see in detail about column casting and their types.
Summarization of week one of month four
In this week as I tried to dictate above most buildings are on the seventh floor.
Column :is as structural part of a building which is a vertical member that support vertical, horizontal and moments
coming from the beam ,slab, stair and other member of the structure and transfer it to the sub structure i.e.
foundation.
Foundations column: Acolumn that carries the load down to a foundation must have means to transfer the
Extensions column:When a column is too long to be built or transported in one piece, it has to be
extended or spliced at the construction site.
1|Page
Internship report
Weekday Activities
Monday -Most buildings are constructing the 7th floor beam. So I tried to see the obviously
activities.
Tuesday -I saw while they were casting B26 seventh floor slab.
Friday I tried to see in detail about column casting and their types.
Summarization of week two of month four
In addition to the obvious activities I tried to see in detail about vibration work.
Vibration: To compact concrete you apply energy to it so that the mix becomes more fluid. Air
trapped in it can then rise to the top and escape. As a result, the concrete becomes
consolidated, and you are left with a good dense material that will, after proper curing,
Vibration is the next and quickest method of supplying the energy. Manual techniques
such as rodding are only suitable for smaller projects. Various types of vibrator are available
1. The workability of the concrete: the less workable the mix, the longer it must be vibrated.
2. The energy put in by the vibrator: bigger vibrators do the job faster.
2|Page
Internship report
Weekday Activities
Monday -Most buildings are constructing the 8th floor. So I tried to see the obviously activities.
Tuesday -I saw while they were casting B26 seventh floor slab.
Classification of HCB
3|Page
Internship report
Weekday Activities
Monday -Most buildings are constructing the 8th floor. So I tried to see the obviously activities.
Tuesday -I saw while they were casting B24 seventh floor slab.
Here week again the construction is a wel progress. In addition to usual activities I tried to see about finishing
work.
Finishing Work
Plastering : Masonry walls and ceiling are provided with a thin mortar cover. This mortar cover ,called
plastering.
1. 1stcoat :-The 1st stage of plastering, is used to create a rough surface for the next coat to
adhere effectively. But for Beam, Column and slab before 1 st coat , it must be chiseled .the
main purpose of chiseling is providing good bond between mortar and wall.
Mortar mix design ratio:1 cement (50Kg) + 3 box sand (washed sand)
2. 2nd coat :-The 2ndstage of plastering and the major part of the plastering i.e the second
coat is plastered to make all the first coat aligned vertically and horizontally with required
4|Page
Internship report
thickness .For the aligning process ,we use nails and ropes in box axes i.e. well measured
and fixed from one end to another and bottom by using plumb-bob (ቱምቢ). And then
plastering with the desired thickness or locally “Fasha” is done along the horizontal top
and bottom edge, then we wait for a day for it to cure and the area in between is then
3. 3rd Coat :- This stage of coating is the last and outermost part. It should have smooth and
5|Page
Internship report
JIMMA UNIVERSITY
Jimma Institute of Technology
(JiT)
University-Industry Linkage and
Technology Transfer Office
Monthly Internship
Report : Month four
Name student: Abraham Dagne
Student ID No: 00580/05
Mentors Name: Galeta chala
Department: Civil engineering
To be filled by the department:__________________
Submission date:_______________
Accepted by:_______________________
(Date, full name and signature:_______________
Comments:
6|Page
Internship report
Column :is as structural part of a building which is a vertical member that support vertical, horizontal and
moments coming from the beam ,slab, stair and other member of the structure and transfer it to the sub structure
i.e. foundation.
Foundations column: Acolumn that carries the load down to a foundation must have means to transfer the
Extensions column:When a column is too long to be built or transported in one piece, it has to be
extended or spliced at the construction site.
Vibration:To compact concrete you apply energy to it so that the mix becomes more fluid. Air
trapped in it can then rise to the top and escape. As a result, the concrete becomes
consolidated, and you are left with a good dense material that will, after proper curing,
Vibration is the next and quickest method of supplying the energy. Manual techniques such as rodding are only
suitable for smaller projects. Various types of vibrator are available for use on site.
1. The workability of the concrete: the less workable the mix, the longer it must be vibrated.
2. The energy put in by the vibrator: bigger vibrators do the job faster.
7|Page
Internship report
Classification of HCB
Finishing Work
Plastering : Masonry walls and ceiling are provided with a thin mortar cover. This mortar cover ,called
plastering.
1. 1st coat :-The 1st stage of plastering, is used to create a rough surface for the next coat to
adhere effectively. But for Beam, Column and slab before 1 st coat , it must be chiseled .the
main purpose of chiseling is providing good bond between mortar and wall.
Mortar mix design ratio:1 cement (50Kg) + 3 box sand (washed sand)
2. 2nd coat :-The 2ndstage of plastering and the major part of the plastering i.e the second
coat is plastered to make all the first coat aligned vertically and horizontally with required
8|Page
Internship report
thickness .For the aligning process ,we use nails and ropes in box axes i.e. well measured
and fixed from one end to another and bottom by using plumb-bob (ቱምቢ). And then
plastering with the desired thickness or locally “Fasha” is done along the horizontal top
and bottom edge, then we wait for a day for it to cure and the area in between is then
3. 3rd Coat :- This stage of coating is the last and outermost part. It should have smooth and
9|Page
Internship report
10 | P a g e