Monera Monthly Report
Monera Monthly Report
ACKNOWLEDGMENT
I would like to thank GOD for his merciful and endless guidance through my life
and for giving me a supportive and loving family and friends that are always there
through all my success and failure, supporting, and lifting me up morally and
financially.
I would like to thank Ambo university institute of technology and the UIL
(University Industry Linkage) office for preparing this internship program and
MONERA ENGINEERING for accepting my request to share his experience, enlighten
me the practical knowledge. Not forgetting the staff members of the Project for their
help and cooperation they have given me.
I would like to thank also the
Site engineer, Engineer Kibrom
Project Forman:-Ato Addis
Carpenter:-Ato Solomon & Ato Ali
Bar man:-Ato Kassahun
Office engineer and supervisor on monera engineering:-Engineer Genet
Gange chief :-Ato Dereje
Project supervisor from consultant office:-Ato Agazi
1
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
EXECUTIVE SUMMARY
In my internship program at MONERA ENGINEERING for four months I was
able to participate on Building construction. I was working in both office and site
engineering department in order to improve both my practical and theoretical knowledge
and skills.
Initially I joined office engineering department for 1 month partially. During this
period of time I obtained a great deal of knowledge regarding what is done in the office.
For example I was able to learn about contract document, payment for contractor, unit
cost break down, take off preparation for different item of works, scheduling, evaluation
etc….which will be dealt briefly in the report. And also I was able to create a smooth
relation with the engineers and other employees in the office.
After I finished my stay at the office I joined the site for the rest of the internship
period. Here I tried to grasp knowledge regarding each and every step followed in the
process of changing the plans on to the ground. For example construction of columns
beams, installation of electrical and sanitary conduits, construction of solid slab,
formwork materials, formwork construction, formwork management and engineer labor
relation etc. And also I was able to learn the local languages that are widely used by the
employs so that I can communicate with them by the use of these terms.
The internship program has helped me to improve my theoretical knowledge
regarding the construction of buildings by exposing me to the real and practical world.
And also through this time I have developed my communication skills. But in my
internship period I saw highlight and made me familiar with the real task that I am going
to be performing after I graduate from the university.
In general, this internship experience thought me a valuable lesson regarding what
is happening in the practical world.
2
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
3
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
Next to the human factor, the most important element for any construction
firm is the availability of construction machineries, equipment and vehicles compatible to
the magnitude of projects at hand. The availability of this element is very essential for the
efficiency of work.
In this regards, MONERA ENGINEERING Plc, has given due attention to the
subject and acquired sufficient number of equipments and vehicles to be readily deployed
to its construction and real estate projects. The Company currently owns the following
construction plants, compounds, and construction machineries, big & small vehicles. Like
Mixers, Trucks, excavators.
About my Internship
4
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
1st Month
It is such a good opportunity to join a company where I could get loads of chances
to learn further that could help me develop my knowledge to the next level.
MONERA ENGINEERING PLC is one of the leading companies in construction
industry. As the UIL officers inform me to search for internship hosting company, it was
such a pleasure for most of me to have my internship in this company.
The site I have been working in is around 22 which Is located in front of Addis
Hiwot hospital. The project will be used for hotel purpose when it is complete.
Site description
5
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
Week 1
In the first week of my internship I was mainly reading the structural and the
architectural plan of the site other than visiting of the site. This helps to me easily
understood and be familiar to the site in which I can easily identified the types of the
building. And also in this week the other task was to practicing the working environment
which includes introduction to the worker of that site includes the office and the site we
spend a lot of time in this week by visiting the site.
Weeks Activities
One *I went to head office
*I went to construction site and I introduce myself with the employers and
visit the site.
*2ND floor slab form work is done
*Beam form work and rebar of beam
During my first week I have learned how to check bars on beam.
Week 2
6
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
On the second week the site engineer gives me an assignment on types of concrete
mix ratios. And I prepared types of concrte mix ratios from construction material slide. In
this week also i visit the site frequently.
Two Activities
*form work for shear wall
*2nd floor beam and slab form work
*casting of column
*about contract document and specification
*schedule
*payment for contractor
*in office work I saw preparing of BOQ,TAKE OFF /PAYEMENT,
REINFORECEMENT(BAR SCHEDULE)
Also on this week form work for slab, beam & shear wall and casting of column
is done in site works. Otherwise in addition to site work for office work I was doing
preparation of take off and payment I know about contract document and specification.
Condition of contract
General conditions of contract
Special conditions of contract
Concrete forms
Contract forms
Agreement
Contract security
Performance bond
Advance payment security
Testing of construction materials
Week 3
Weeks Activities
8
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
In this week’ I was saw how slab is reinforced and how shear walls are casted.in
addition to how shear walls are casted I know about why shear walls are provided for a
building and minimum number of shear walls on one building.
Shear wall and lift shafts are a vertical structure and have the same work
procedure and the same structural design. In my site there are 4 shear walls and 3 lift
shafts goes up to top.
Why shear walls are provided??
One of the major reasons is for laterally support loads. to prevent the building
from earth quake and wind loads.
But in our country shear walls are provided for earth quake loads but not for wind
load.
Week four
Four *form work for stair case
*slab reinforcement and form work
9
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
Conclusion
Every Building construction consists of two basic components; sub-structure and
super-structure part. Unfortunately for this month I haven’t got the opportunity to
observe the sub-structure work (especially foundation part) of the building. I saw only
the super structure part about slab beam and column works. but in office I saw different
things like:-
2nd Month
10
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
In this second month I am doing the same things lastly I was doing like
formworks, rebar, casting, preparation of take off...
11
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
Note that the casting of the staircase is done in accordance with the landing
beams monolithically.
12
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
While I was on the site I was able to observe and learn the construction of
solid slabs. Unfortunately solid slab is the only type of slab being constructed on the site.
The procedures to follow in order to construct the slab are discussed as follows;
Form work preparation will begin by the construction of supports (Ponte) that will
support the slab. This is done by constructing the Ponte with 50c.m spacing in both
directions. After the completion of this, panels are laid on top of the supports.
The panel is covered with a lubricant that will help to protect the form work against
damage. Since mold oil is expensive, a mixture of kerosene and burned oil is used.
Reinforcement or rebar is prepared according to the structural detail drawing. That is
rebar is prepared according to the length specified. And the reinforcement bars are
laid longitudinally and transversely both on top and bottom. Note that the
reinforcement for slab is connected to the suspended slab in every direction.
The depth of slab is maintained by using a member known as bar chair or locally
known as “kebeleto”. This helps to keep the effective depth of the slab constant.
During the week ends the activities continue and concrete work for slab
were performed. I will discuss about the work steps for casting of concrete
for beam and slabs.
13
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
In the case of concrete work in the site done for slab is C-30 grade of
cement.
For the second floor slab needs around 1000 m3 cement of concrete.
Concrete we can cast monolithically by using of ready mix it is a
better than other types of concrete casting method like by using of
mixer on the site .
Casting on the site or mixing on the site take a long period of time b/c
of labor cost, availability of material, like cement,sand,aggeregate .
In the case of casting we cast only 1/3 of the bar that means up to
negative bars ends (joint casting method).and we must stop on the 1/3
vertically. To prevent the concrete from diagonal shear. Diagonal
shear mainly found on the joint because of that we must cast our
concrete specially slab by using of joint method.
Before casting of slab electrical and sanitary installation works are
done..
During the week ends the activities continue and beam reinforcing and
form work for slab were performed.
14
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
I will discuss about the work steps for arrangement for beams bars discussed
below..
First step is cutting of bars according to the structural design.
Placing of the main bars 1ST on the top and then place the stirrups
according to the design in the specified space.
Finally place the main bottom bars and the negative bars.
3rd Month
Week Activity
15
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
My activity during this month’s is mainly just like last month (2nd month).because of
its length of the project all things are done slowly. The building in this month still in
second floor column erection. Otherwise other than column works lift shafts and shear
walls are also casted and rebar.
16
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
Casting of the column is done by using a ladder like structure locally known as
“estanga” whose main purpose is to support and hold the formwork vertical after
it is checked by the plumb bob.
Next moving the formwork by using the estanga until the plumb bob shows
squadra will follow. When the tumbi shows squadra, the Estanga will be fixed
upon a large horizontal member known as “gindila”.
4th month
17
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
In this month only on the site we are doing form work for 3rd floor
slab for one month. Because of the disagreement between the contractor
consultant and the owners.
The cause of the conflict between those bodies is the contractor only has 1
month to finish his contract but he is now on 3rd floor slab but the building is
around 8 storys.
18
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
19
AMBO UNIVERSITY INSTITUTE OF TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING
20