Subgrade

S.No Chainage Side Length Width Depth Qty.(Cum) Trips


1 91480 91540 RHS 60 7.5 0.45 202.5
2 91520 91600 LHS 80 7.1 0.13 73.84
3 94770 94850 LHS 80 7.1 0.13 73.84
4 91420 91480 LHS 60 7.1 0.45 191.7
5 91660 91700 LHS 40 7.1 0.25 71
6 92800 92850 LHS 50 7.1 0.45 159.75
7 88530 88650 LHS 120 7.1 0.45 383.4
8 94200 94450 LHS 250 7.1 0.25 443.75 27
9 134580 135270 LHS 690 1 0.4 276
10 102500 102820 RHS 320 7.5 0.45 1080 Excavation upto sg top
11 103300 103650 RHS 350 7.5 0.45 1181.25 Excavation upto sg top
12
Total: Exc. 960 3198.60
Total: Subgrade 450 662.43
Total: Drain 690 276.00
GSB
S.No Chainage Side Length Width Depth Qty.(Cum) Trips
1 89520 89690 RHS 170 6.9 0.2 234.6 19
2 103770 104140 RHS 370 6.9 0.2 510.6
3 104850 105050 LHS 200 6.9 0.2 276
4
5 Total: 740 1021.20
WMM
S.No Chainage Side Length Width Depth Qty.(Cum) Trips
1 131900 132750 RHS 850 5.15 0.13 569.075
2 135000 135350 RHS 350 5.15 0.13 234.325
3 131560 131900 RHS 340 5.15 0.13 227.63
4 104850 105000 RHS 150 5.15 0.13 100.425
5 131170 131350 RHS 180 5.15 0.13 120.51
6 89030 89440 LHS 410 3.65 0.07 104.755 4
7 89740 90190 LHS 450 3.65 0.13 213.525 9
8 90190 90720 LHS 530 3.65 0.25 525 21
9 90700 91080 LHS 380 3.65 0.15 208.05 18
10 89740 90430 LHS 690 3.65 0.25 629.625 31
11 89030 89650 LHS 620 3.65 0.25 565.75 34
12 89650 89750 RHS 100 3.65 0.15 54.75
13 90400 90550 RHS 150 3.65 0.15 82.125 19
14 92200 92800 RHS 600 WMM TOP Rectification
15 92900 93800 RHS 900 WMM TOP Rectification
16 89440 89700 RHS 260 3.65 0.15 142.35 22

Total: 6960 3777.90


DBM
S.No Chainage Side Length Width Depth Qty.(Ton)
1 89030 89740 LHS 710 3.5 0.06
519.63
2 89740 90450 LHS 710 3.5 0.06
3 90450 91060 LHS 610 3.5 0.06
502
4 90060 90400 LHS 340 3.5 0.06
5 89750 90060 RHS 310 3.5 0.06
503
6 89040 89600 RHS 560 3.5 0.06
7 132375 132700 RHS 325 5 0.06 255.51

Total: 3565 1780.14


Remarks
Excavation
Filling
Filling
Excavation
SG 1ST FILLING
Excavation After Covid -19
Excavation S.No Item Length Qty. Remarks
SG 1ST FILLING 1 Excavation 960 3198.60 Cum
drain excavation 2 Subgrade 450 662.43 Cum
Excavation upto sg top 3 Drain 690 276.00 Cum
Excavation upto sg top 4 GSB 740 1021.20 Cum
5 WMM 6960 3777.90 Cum
6 DBM 3565 1780.14 Ton
7 M-15 14 Cum
8 M-20 51.49 Cum
9 M-30 17.5 Cum
Remarks
GSB TOP
GSB TOP After Covid -19
GSB TOP Material Received(FROM PN-44)
S.No Item Trips Qty. Remarks
1 40mm 25 625.00 Cum
2 20mm 21 525.00 Cum
Remarks 3 10mm 20 500.00 Cum
WMM TOP 4 dust 31 775.00 Cum
WMM 1ST 5 DBM 0 1780.14 Ton
WMM TOP
WMM TOP
WMM TOP
WMM TOP Rectification
WMM TOP
WMM TOP
WMM TOP
WMM 1ST AND TOP
WMM 1ST AND TOP
WMM TOP
WMM TOP
WMM TOP Rectification
WMM TOP Rectification
WMM 1ST AND TOP
Remarks
S.No Chainage Side Item M15(Cum)M20(Cum)M30(Cum)
1 93833 RHS H/W 2nd Lift 14
2 93150 RHS H/W 3rd lift 6
3 93150 RHS Enc.2nd lift 4
4 91150 LHS H/W 2nd Lift 8
5 91150 LHS Enc.1st lift 4
6 91150 RHS parapet wall 1.98
7 66732 A1 Abutment wall 2nd lift 17.5
8 95171 RHS H/W 1st Lift 9
9 95171 RHS pipe bed PCC 2
10 91150 LHS H/W 3rd lift
11 91150 LHS Enc.2nd lift 4 6
12 91150 LHS H/W 4TH lift 2.01
13 93150 LHS parapet wall 2.2
14 93833 RHS parapet wall 2.3

Total: 14 51.49 17.50