PN-41 (A) Progress Review Meeting 28.05.2020

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

Progress

Name Of Project:PN-41(A)

Total Work Achieved In 4th


Sr. No Activity Unit Planned For 4th
Week(BHS)
Week(BHS)

1 Earth work Kms -1.2 0.040


2 GSB Kms -0.46 0.190
3 WMM Kms -1.21 1.145

4 DBM Kms 1.96 1.220

5 BC Kms 0 0.000

6 DBM Kms 0 0.000

7 SHOULDER Kms 1.12 1.400


Progress Review Meeting Date:2

Balance for 5th Hurdles /Constrains During Last Target For


Week(BHS)(from past 4 5th
Week
weeks) Week(BHS)

-1.240 0.89
-0.650 0.94
-2.355 0.68

0.740 0.71

0.000 2.42

0.000 0.08

-0.280 Route problem due to COVID-19 2.42


Date:28.05.2020

Balance to be
Requirements To Achieve The Total Achieved Till Done in 5th
Targets Qty(BHS) Date(BHS) Week
Qty(BHS)

-0.31 0.040 -0.35


0.48 0.190 0.29
Continous Material from crusher -0.53 1.145 -1.68

Bitumen,Another set of DBM 2.67 1.220 1.45


Labour

2.42 0.000 2.42

0.08 0.000 0.08

3.54 1.400 2.14


Remark