Progress Rev

Name Of Project:PN-41(B)

Total Work Achieved In


Sr. No Activity Unit Planned For 4th
4th Week(BHS)
Week(BHS)

1 Earth work Kms 1.22 0.25


2 GSB Kms 2.63 0.62
3 WMM Kms 0.36 0.35
4 DBM Kms 2.90 1.565
5 BC Kms 0.00 0
6 DBM Kms 0.00 0
5 SHOULDER Kms 2.94 0.79
Progress Review Meeting Date:28.05

Balance for 5th Hurdles /Constrains Target For Requirements To Achieve The
Week(BHS)(from 5th
During Last Week Targets
past 4 weeks) Week(BHS)

0.970 1.09
2.015 1.32 Continous Material from crusher
0.005 1.16 Continous Material from crusher
1.330 Bitumen Problem 1.16 bitumen,
0.000 0.00
0.000 0.00
2.155 1.50
Date:28.05.2020

Balance to be
Total Achieved Till Done in 5th
Remark
Qty(BHS) Date(BHS) Week
Qty(BHS)

2.31 0.250 2.06


3.95 0.615 3.34
1.52 0.350 1.17
4.06 1.565 2.49
0.00 0.000 0.00
0.00 0.000 0.00
4.44 0.785 3.66