Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 22 (2004) 553–561
www.elsevier.com/locate/ijproman

Large construction projects in developing countries: a case


study from Vietnam
Nguyen Duy Long a, Stephen Ogunlana b,*
, Truong Quang c, Ka Chi Lam a

a
Department of Building and Construction, City University of Hong Kong, 83 Tat Chee Avenue, Kowloon, Hong Kong
b
School of Civil Engineering, Asian Institute of Technology, P.O. Box 4, Klong Luang, Pathumthani 12120, Thailand
c
School of Management, Asian Institute of Technology, P.O. Box 4, Klong Luang, Pathumthani 12120, Thailand
Received 29 April 2003; received in revised form 3 September 2003; accepted 12 March 2004

Abstract

Although various studies have been undertaken into the factors affecting delays, cost overruns, quality, safety, and productivity, etc.
and other problems in specific types of projects, these studies seldom discuss common and general problems of construction projects.
Thus, comprehensive studies on these problems are essential. Since the problems are rather contextual, the studies need to focus on a
specific geographical area, country or region. This paper presents problems of large construction projects in Vietnam. Data analysis
revealed that the problems could be grouped under five major factors: (1) incompetent designers/contractors, (2) poor estimation and
change management, (3) social and technological issues, (4) site related issues, and (5) improper techniques and tools.
Ó 2004 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Problems; Large construction projects; Construction management; Vietnam

1. Introduction and that there are intricate interrelations among these


indicators as well as the targets. Thus, practitioners must
It is widely accepted that a project is successful when develop the capacity to foresee potential problems likely
it is finished on time, within budget, in accordance with to confront their current and future projects. Identifica-
specifications and to stakeholders’ satisfaction. Unfor- tion of common problems experienced on past projects in
tunately, due to many reasons, high project performance their construction business environment is a good option.
and project success are not commonplace in the con- As the common Asian saying goes ‘‘a problem well de-
struction industry, especially in developing countries. fined is a problem half solved’’. Project parties must be
Therefore, professionals and scholars have been moti- proactive in managing their projects in which potential
vated to take extensive efforts to meet this challenge. As problems are fully anticipated.
a result, several studies have been undertaken on factors Vietnam is currently among countries with high gross
affecting delays [1–11], cost overruns [4,9], quality [12], domestic product (GDP) growth rates. For example,
safety [13–15], and productivity [14,16], etc. and prob- GDP growth hit 7% and recorded the fastest economic
lems in specific types of projects [17,18]. These studies growth in Southeast Asia in 2002 [19]. Construction
usually focus on one or some certain specific aspects of investment in Vietnam has been increasing to meet the
project performance. needs for the socioeconomic development. Management
Although the focuses are very often necessary, com- of construction projects in Vietnam, however, has faced
prehensive studies on common problems of construction various problems due to many causes, controllable and
projects seem much more urgent. The reason is that a otherwise. Gaining insight into the problems is neces-
project cannot be successful if all key project performance sary to help professionals to be active in dealing with the
indicators and project targets do not reach certain levels problems and their consequences.
The objective of this paper is to provide insight
*
Corresponding author. Tel.: +66-2-524-5534; fax: +66-2-524-6059. into problems experienced in large construction
E-mail address: ogunlana@ait.ac.th (S. Ogunlana). projects in Vietnam. The research defines a large

0263-7863/$30.00 Ó 2004 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2004.03.004
554 N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561

construction project as a project with a total budget Owner-related problems are the problems for which
more than $1 million. It is intended that findings of clients or employers are responsible. Finance and pay-
the paper are useful not only for Vietnamese con- ments for completed work [1,2,4,5,11], excessive change
struction participants but also for those in other de- orders [1,5,8], slow owner’s decision-making process
veloping countries. [2,5,6,11,18], owner interference [11], and ill-defined
duties and responsibilities [2] are adverse factors fre-
quently cited in previous studies.
2. Previous research Contractor-related problems concern problems or
adverse factors caused by contractors. They include in-
The major problems faced by contractors in devel- adequate experience [11,24], construction errors [1,4,11],
oping countries have been classified as: (1) problems poor site management and supervision [1,6,8,11],
imposed by the industry’s infrastructure, (2) problems of equipment failures or allocation problems [1,6,11], in-
inaccurate information and frequent changes in in- adequate labor skills [1,5], site manager lacking au-
structions and failure to meet obligations on the part of thority [2], improper planning and scheduling
clients and consultants, and (3) problems imposed by [1,2,6,11,24], inaccurate estimation [4,5], and poor con-
their own shortcomings [20]. Research into the delays tract management [1,4,11].
experienced in high-rise building construction projects in Consultant-related problems are problems or adverse
Thailand supports this classification. Specifically, factors attributable to designers/consultants. Prepara-
Ogunlana et al. [6] confirmed that construction industry tion and approval of drawings [11,12], design errors,
problems in developing economies can be nested in three delays in work approval [4,6,11], uncompromising atti-
layers: problems of shortages or inadequacies in indus- tude [6] are common problems for which consultants are
try infrastructure, problems caused by clients and con- held responsible in literature.
sultants, and problems caused by contractor’s Project attributes-related problems are problems or
incompetence/inadequacies. A recent study on East Asia adverse factors that derive from the characteristics of
cross-border construction [21], identified five groupings the project and/or are difficult to classify into other
of obstacles as business environment risk, regulatory problem categories when the project delivery system and
restrictions, contractual arrangement, and differences in other project information are not taken into account.
standards and culture. If the problems and/or obstacles For example, in some research [11], an adverse factor,
are not solved swiftly, they can cause delays and cost namely improper quality assurance/control was consid-
overruns in projects, harm cooperative relationships, ered to be within the purview of consultants. Except for
reduce efficiency, lead to claims and disputes, and traditional procurement, this classification may be in-
probably invoke litigation proceedings [22]. appropriate in other project delivery systems. In the
Other studies relating to industry problems concern other project delivery systems such as design and build,
causes of time delays and/or cost overruns. Such studies contractors have to establish systematic quality assur-
have been conducted worldwide from developed coun- ance/control or face the consequences of low quality
tries such USA [1] and UK [3] to developing countries otherwise. This research therefore considers improper
such as Turkey [2], Nigeria [4], Saudi Arabia [5], Thai- quality assurance/control as a project attributes-related
land [6], Hong Kong [7–9,23], Malaysia [24] and Jordan problem. Unforeseen site conditions [1,4,8,11,24], con-
[10,11]. Causes and factors pertinent to time and cost fined site [6], problems with neighbors such as pollution
overruns and other project performance indicators in [6,11,25], unrealistic imposed contract duration [4,11],
these studies are generally termed ‘‘adverse factors’’ in inaccuracy of project information [18] are other adverse
this paper. A set of the adverse factors is a compre- factors in this category.
hensive foundation for identifying common problems of Coordination-related problems are problems or ad-
large construction projects in this research. By probing verse factors such as poor communication [1,3,11,18],
the underlying relationships, the adverse factors can be excessive use of subcontractors and nominated sup-
classified into groups of problems within the purview of pliers [1,4,11], excessive bureaucracy [2,5,25], fraudu-
financiers, owners, contractors, consultants (including lent practices and kickbacks [4,25], misalignment of
designers), project attributes, coordination and envi- client’s expectations [18], and jurisdictional disputes
ronment. The problems or adverse factors are listed in [1,22].
the respective groups as follows: Environmental problems are external problems or
Financier-related problems are problems in the fi- adverse factors. They may be caused by natural condi-
nancing domain. High cost of financing [1] and difficulty tions, for example inclement weather [1,3,4,11] or so-
in getting loans [2] are adverse factors identified in cioeconomic conditions such as material shortage or late
previous work. Furthermore, interference in owner’s delivery [1,3,4,6,11,24], labor shortage [1,2,5,11], price
decisions and funding shortages are other common fluctuations [4,11]. In addition, problems or adverse
problems attributed to financiers. factors perceived to be responsible by external project
N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561 555

stakeholders are also grouped into this category. Ex- Table 1


amples are inconsistent policies [11,25] and slow gov- Questionnaire return rate
ernment permits [6,11]. Party Questionnaires Responses Response Propor-
A major observation is that most of the problems are distributed received rate (%) tion (%)
human and management related problems [4,24]. These Owners 82 36 43.9 33.0
problems or adverse factors are included in a list of Designers/ 85 27 31.8 24.8
problems that were investigated to ascertain the extent consultants
Contractors/ 120 46 38.3 42.2
of their occurrence in, and influence on, large con- subcontractors
struction projects in Vietnam.
Total 287 109 38.0 100.0

3. Research methodology
impractical to separate construction managers from
A questionnaire (in Vietnamese) was designed based designers/consultants in Vietnam since there are no
upon literature and current construction practice in specialized construction management firms. The re-
Vietnam to obtain information on the problems known sponse rates from the different groups are 33% from
to participants in large projects. Although the ques- owners, 24.8% from consultants and 42% from con-
tionnaire survey investigated several issues relating to tractors (Table 1).
large construction projects, this paper focuses only on More than half (57%) of the respondents were line
problems experienced. To fit into the Vietnam con- managers and engineers, followed by functional/project
struction conditions, the preliminary questionnaire was managers (28%) and top management (15%). It would
pilot tested. Six experienced professionals in the Viet- have been better if the proportion of the respondents
nam construction industry were involved in the pilot who were top management and functional/project
test. Test participants included a city government officer managers could be increased. Due to several reasons,
in the Department of Construction, a public owner, a however, the data collection faced difficulties in involv-
designer, a contractor, and two university senior lec- ing more respondents from these categories. Research in
turers actively involved in industry practice. Their Indonesia [26] suggests that very senior managers may
comments were used to revise the research question- have different focus from line executives. The propor-
naire. The final questionnaire was distributed to pro- tions of the respondents in terms of number of years
fessionals involved in large projects in Hochiminh City, involved in construction were: less than or equal to 5
the biggest city in Vietnam, and its surroundings at the years (39%), between 5 and 10 years (42%), and 10 years
end of the year 2002. Since the professionals may be or more (19%).
experienced in many large projects with different degrees Among the respondents, two-thirds were mostly ex-
of success or failure, this research does not attempt to perienced in public projects while one-third were expe-
differentiate between successful and problematic or rienced in private projects. The respondents were
failed projects. Several means were employed to deliver involved in building projects (44%), industrial con-
the questionnaires to potential respondents. However, struction projects (40%), road projects (11%), bridge
direct (face-to-face) delivery was preferred to motivate projects (2%) and others (3%). This implies that the re-
respondents and to ensure the accuracy of answers and search is scoped in building, industrial and road con-
improve response rate. struction sectors.
Responses to the questionnaire were then collected
and analyzed. The analysis included ranking the prob-
lems in terms of degree of occurrence and level of in- 5. Findings and analysis
fluence. The analysis also examined whether or not
perceptions of different respondent groups affect the 5.1. Achievements of project objectives
rankings. The Spearman’s rank correlation coefficient
was used to test the strength of associations between the To elicit the extent of the occurrence of unexpected
rankings of the respondent groups. Finally, factor status on project objectives, the survey respondents were
analysis was employed to derive interrelationships asked to rate against the five-point scale, from ‘‘not
among the problems. significant’’ (1) to ‘‘extremely significant’’ (5). This nu-
merical equivalence scale was also applied for questions
regarding degrees of occurrence and influence of prob-
4. Respondent’s characteristics lems. Project delays and cost overruns were rated as
having very high occurrence. The considerable occur-
The respondents were grouped into owners, design- rence of labor accidents, low quality and disputes were
ers/consultants and contractors/subcontractors. It is also perceived (Table 2). It can be explained that large
556 N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561

Table 2 Table 3
Failure to meet project objectives Problems and problem categories
Rank Project performance Mean SD (CV)a Categories Problems
1 Project delays 3.73 1.11 (29.76) Financier Unreasonable constraints to owner
2 Cost overruns 2.98 1.17 (39.26) High interest rate
3 Labor accidents 2.46 1.36 (55.28) Interference in owner’s decisions
4 Low quality 2.34 1.17 (50.00) Funding shortage
5 Disputes between parties 2.21 1.17 (52.94)
a
Owner Lack of strategic management
SD – standard deviation; CV – coefficient of variance. Confusing requirements
Improper project feasibility study
Lack of clear bidding process
projects are being poorly managed in Vietnam. Effective Excessive change orders
construction management at corporate, process, project, Unclear responsibility
and activity levels. . . should be introduced to profes- Lack of capable representatives
sionals to enhance construction industry performance in Owner’s financial difficulties
Owner’s poor contract management
Vietnam.
Slow decision making

5.2. Rankings of problems’ occurrence and influence Contractor Improper planning and scheduling
Inadequate experience (c)
From literature and interviews with professionals in Inadequate modern equipment
Inaccurate time estimating
the Vietnam construction industry, 62 problems were Inaccurate cost estimating
identified (Table 3). They were subjectively divided into Poor site management
organizational, project attributes-related, coordination- Improper monitoring and control
related and environmental problems. Organizational Poor labor and management relations
problems were also subdivided into problems that are Inappropriate construction methods
Contractor’s financial difficulties
under the purview of financiers, owners, designers/con- Incompetent project team
sultants and contractors. The following are discussions Poor contract management
about degrees of occurrence and influence of the prob- Severe overtime
lems in large construction projects in Vietnam. Material waste
The full rankings of the degree of occurrence and Lack of necessary skills
Inadequacy of site inspection
degree of influence of the 62 problems rated by the dif- Lack of competent subcontractors/suppliers
ferent respondent groups are available from the authors
on request. Table 4 shows the top 20 problems perceived Consultant Inadequate experience (d)
as having high degrees of occurrence and influence. Lack of standardization in design
Lack of responsibility
From these rankings, many problems had high ranks for
Impractical design
both their degrees of occurrence and influence. Examples Inadequate project management assistance
are inaccurate time estimating, slow site clearance, slow Slow response
government permits, lack of capable owner’s represen- Lack of involvement through project life
tatives, obsolete technology and unsatisfactory site Project attributes Ambiguous project scope
compensation. It can be said that these problems oc- Lack of constructability
curred under a wide range of causes: owners, designers, Inaccurate site investigation
contractors, project attributes and environment. How- Pollution during construction
Non-value-added works
ever, several problems had high occurrence but low in-
Improper quality assurance/control
fluence and vice versa. Although severe overtime and Unrealistic imposed contract duration
inadequate modern equipment were identified as having Obsolete technology
high occurrence, their influences were low. Severe over-
Coordination Excessive contractors/subcontractors
time is a common management policy to accelerate Lack of communication among parties
project progress. Some unintended side effects of severe Lack of comprehensive dispute resolution
overtime have been widely recognized in the industry, yet Inappropriate type of contracts used
it does not usually have strong impact on project per- Fraudulent practices and kickbacks
Unreasonable risk allocation
formance. In Vietnam, since construction is still labor-
Bureaucracy
intensive work, it is logical that inadequate modern
equipment was not rated as very high impact. Improper Environment Unforeseen ground conditions
Inclement weather
planning and scheduling and contractor’s financial dif-
Unsatisfactory site compensation
ficulties were given high ratings in degree of influence. Slow site clearance
These accords with previous studies [2,6,11] conducted in Price fluctuations
developing countries. Material shortage
N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561 557

Table 3 (continued) esis testing at the 1% significance level. The Spearman’s


Categories Problems correlation coefficients for ranking of the occurrence of
Unreasonable regulatory framework
problems between owners and consultants, owners and
Unstable regulatory framework contractors and consultants and contractors are 0.681,
Slow government permits 0.810, and 0.796, respectively. Similarly, the Spearman’s
correlation coefficients for ranking of the influence of
problems between owners and consultants, owners and
To deeply investigate which parties and groups were contractors and consultants and contractors are some-
responsible for these problems, problem categories were what high values: 0.700, 0.769, and 0.733, respectively. It
ranked in terms of their degree of occurrence and degree implies a high degree of agreement between the three
of influence as shown in Tables 5 and 6, respectively. groups on the level of occurrence and degree of influence
Consultants, contractors, and coordination were iden- of the problems. Therefore, further attempt to analyze
tified as the progenitors of problems. Regarding the the problems faced by the different groups of respon-
degree of influence, problems associated with the con- dents is not necessary.
sultants, owners and environment highly impacted
projects. Owners and consultants obviously have high 5.3. Factor analysis of problems’ occurrence
influences on whether or not projects are successful since
they are involved in the early stages of project life. In- To capture any multivariate interrelationships exist-
terestingly, external problems were also ranked highly. ing among the problems in terms of degree of occur-
This differs from previous research elsewhere (Jordan rence, factor analysis was applied. Factor analysis
[11] for example). A possible explanation is that though addresses the problem of analyzing the structure of the
price fluctuations, unforeseen ground conditions were correlations among a large number of variables by de-
not serious, yet slow government permits, unstable fining a set of common underlying dimensions, known
regulatory framework, slow site clearance and unsatis- as factors or components [27]. Several tests are required
factory site compensation were strongly influential to determine the appropriateness of factor analysis for
problems. These imply that the legal and institutional factor extraction. They include anti-image correlation –
framework for the construction industry is problematic indicating the negative value of the partial correlation,
in Vietnam. the Bartlett test of sphericity – a statistical test for the
Concerning the attitudes of different parties towards presence of correlations among the variables, the
these problems, there were strong agreements on the Kaiser–Meyer–Olkin (KMO) – the measure of sampling
ranking based on degree of occurrence. These associa- adequacy (MSA). Details of the factor analysis process
tions among ranking of parties are verified by hypoth- and these tests can be found in Hair et al. [27].

Table 4
Problems having high occurrence and high influence
Rank Problems as high occurrence Mean SD Rank Problems as high influence Mean SD
1 Inaccurate time estimating 3.64 1.04 1 Slow site clearance 3.77 1.40
2 Slow site clearance 3.47 1.43 2 Slow government permits 3.63 1.21
3 Excessive change orders 3.42 1.15 3 Inaccurate time estimating 3.56 1.07
4 Slow government permits 3.38 1.17 4 Lack of capable representatives 3.54 1.28
5 Severe overtime 3.33 1.41 5 Contractor’s financial difficulties 3.49 1.16
6 Inadequate modern equipment 3.29 1.12 6 Improper planning and scheduling 3.45 1.16
7 Lack of capable representatives 3.28 1.18 7 Unsatisfactory site compensation 3.43 1.33
8 Bureaucracy 3.26 1.43 8 Inadequate experience (d) 3.40 1.22
9 Obsolete technology 3.26 1.23 9 Obsolete technology 3.40 1.22
10 Unsatisfactory site compensation 3.22 1.31 10 Lack of responsibility 3.40 1.30
11 Fraudulent practices and kickbacks 3.18 1.26 11 Impractical design 3.38 1.21
12 Inaccurate cost estimating 3.17 1.13 12 Incompetence project team 3.32 1.25
13 Improper planning and scheduling 3.16 1.17 13 Excessive change orders 3.32 1.15
14 Contractor’s financial difficulties 3.14 1.10 14 Bureaucracy 3.29 1.27
15 Inadequate project management assistance 3.11 1.08 15 Inaccurate cost estimating 3.29 1.16
16 Lack of involvement through project life 3.05 1.32 16 Inaccurate site investigation 3.28 1.29
17 Poor site management 3.02 1.13 17 Inadequate modern equipment 3.21 1.14
18 Excessive contractors and/or subcontractors 2.99 1.31 18 Unrealistic imposed contract duration 3.20 1.27
19 Impractical design 2.97 1.12 19 Lack of involvement through project 3.15 1.31
life
20 Incompetence project team 2.94 1.16 20 Inadequate project management 3.14 1.18
assistance
558 N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561

Table 5
Ranking of degree of occurrence of problem categories
Problem category Overall Owners Consultants Contractors
Mean Rank Mean Rank Mean Rank Mean Rank
Financier 2.24 7 2.41 7 2.14 7 2.15 7
Owner 2.75 5 2.88 4 2.71 4 2.68 5
Contractor 2.88 2 3.08 1 2.75 2 2.80 2
Consultant 2.96 1 3.05 2 2.74 3 3.02 1
Project attributes 2.60 6 2.60 6 2.56 6 2.61 6
Coordination 2.79 3 2.82 5 2.86 1 2.72 3
Environment 2.78 4 2.96 3 2.69 5 2.70 4

Table 6
Ranking of degree of influence of problem categories
Problem category Overall Owners Consultants Contractors
Mean Rank Mean Rank Mean Rank Mean Rank
Financier 2.67 7 2.81 7 2.68 7 2.57 7
Owner 3.00 3 3.29 3 3.04 5 2.77 6
Contractor 2.98 4 3.11 4 3.10 2 2.82 5
Consultant 3.22 1 3.42 1 3.07 3 3.15 1
Project attributes 2.96 5 3.03 5 3.05 4 2.85 3
Coordination 2.92 6 2.97 6 2.96 6 2.85 4
Environment 3.13 2 3.34 2 3.12 1 3.00 2

The top-twenty highly-ranked problems regarding equal or greater than 0.5 and 0.525, respectively. Each
their degrees of occurrence were selected for factor variable’s communality, representing the amount of
analysis since their occurrences were perceived from variance accounted for the factor solution for the vari-
‘moderate’ to ‘extremely’ significant. That is, their able, should be equal to, or greater than, 0.5 to have
means approximate to or are more than 3 on a scale of sufficient explanation [27]. As recommended in Hair
1–5. However, three of the problems – severe overtime, et al. [27], with sample size around 110 – this research
obsolete technology and lack of capable owner’s repre- had 109 – factor loading for each factor should exceed
sentatives – were ignored since they did not pass the tests 0.525.
mentioned above. In this case, either the communalities The remaining 17 problems were appropriate for
or their factor loadings of all components were not factor analysis. The value of Bartlett test of sphericity is

Table 7
Results of the factor analysis using varimax orthogonal rotation
Factors Factor labels Eigenvalue Percentage Problems Factor loading
of variance
1 Incompetent designer/contractor 6.395 37.620 Inadequate project management assistance 0.851
Impractical design 0.842
Lack of involvement through project life 0.700
Contractor’s financial difficulties 0.597
Incompetent project team 0.578
Poor site management 0.527
2 Poor estimation and change 2.086 12.271 Excessive contractors and/or 0.796
management subcontractors
Inaccurate time estimating 0.634
Inaccurate cost estimating 0.628
Excessive change orders 0.563
3 Social and technological issues 1.758 10.339 Obsolete technology 0.887
Bureaucracy 0.824
Fraudulent practices and kickbacks 0.758
4 Site related issues 1.196 7.036 Slow site clearance 0.880
Unsatisfactory site compensation 0.860
5 Improper techniques/tools 1.048 6.162 Inadequate modern equipment 0.715
Improper planning and scheduling 0.636
N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561 559

878.186 and associated significance level is small 6.2. Poor estimation and change management
(p ¼ 0:000). These suggest that the population correla-
tion matrix is not an identity matrix [27]. The correla- The factor grouping is made up of excessive number
tion matrix shows that all variables have significant of contractors and/or subcontractors, inaccurate time
correlation at the 5% level. It implies that the deletion of estimating, inaccurate cost estimating, and excessive
any other problems is unnecessary. The value of the change orders. Most of the parties involved are re-
KMO MSA is 0.794, which is satisfactory for factor sponsible for these problems. Inadequate and ineffective
analysis [27]. coordination among parties is a major cause of the
Principle component analysis carried out produced a problems. In recent times, the amount of subcontracting
five-factor solution with eigenvalues greater than one in construction procurement has increased through the
(Table 7). The varimax orthogonal rotation of principle use of specialist works and offsite production [29]. As
component analysis was used to interpret these factors. more contractors, subcontractors and, especially nomi-
The factor grouping based on varimax is displayed in nated subcontractors/suppliers, are involved in a pro-
Table 7. The factors and associated variables are readily ject, relationships and information flows among the
interpretable as: factor 1 concerns incompetent design/ project parties become more complicated. Such intricate
contractor, factor 2 concerns poor estimation and relationships often cause conflict between them as well
change management, factor 3 is social and technological as causing other coordination problems [28]. Accurate
issues, factor 4 concerns site related issues and factor 5 is estimations need accurate project information in terms
improper techniques and tools. The factors are elabo- of the quality of information and information flow,
rated further in the following section. availability and supply of resources, and the expertise of
the consultants involved [29]. Time and cost estimates
involve and/or are prepared by many parties. Although
contractors were perceived to cause these inaccurate
6. Discussion of factor analysis results estimates in this research since they are the ultimate
party who produce estimates, owners and consultants
6.1. Incompetent designers/contractors were also responsible. For example, designs are often
not clear or detailed enough to ensure accurate estima-
This factor consists of inadequate project manage- tion by contractors. Besides, excessive change orders are
ment assistance, impractical design, lack of involvement issued for many reasons such as unclear project objec-
through project life, contractor’s financial difficulties, tives and scope from the owners, problems of con-
incompetent project team, and poor site management. structability of designs, use changes, etc. Excessive
These problems were clearly caused by designers and change orders can cause significant disruption to con-
contractors. Designers are responsible for inadequate struction projects and, consequently, cause changes in
project management assistance, impractical design and the planned schedules, increase costs through rework
lack of involvement through project life while contrac- and decrease labor efficiency [30,31]. Unclear project
tors are responsible for their financial difficulties, in- objectives and scope from the owners cause unexpected
competent project team and poor site management. Two design changes while issues of constructability of designs
root causes are the fact that procurement and project lead to many changes during the construction stage.
delivery system have not been applied properly and that Broadly speaking, poor estimation and change man-
lack or inadequacy of capable consultants and con- agement reflect lack of efficient and effective project
tractors for handling large projects are common phe- management procedures resulting in project parties not
nomena in Vietnam. Bidding processes, for example, being proactive in their roles to ensure that projects run
have been blamed publicly as being unfair and un- smoothly.
healthy (bid shopping, e.g.) in the country’s media. This
has led to contracts being awarded to incapable de- 6.3. Social and technological issues
signers and contractors. Moreover, open competitive
bidding sometimes proves to be more costly due to ex- Included in this factor are obsolete technology, bu-
cessive time delays and claims from the contractor who reaucracy, and fraudulent practices and kickbacks.
has put in a low bid in the hope of obtaining extra Technology is indispensable in any large construction
claims to compensate for the low price [28]. Therefore, project. Possession of modern technology is one of the
although pre-qualification of tenders and selective bid- most critical factors to succeed and sustain in today’s
ding may be a better alternative to open competitive business environment and construction is not an ex-
bidding to ensure awarding the bids to the right de- ception. When access to technological knowledge and/or
signers/contractors [28], both the public and private timely and relevant information is not available,
sectors in Vietnam have yet to take full advantage of this construction projects invariably use obsolete technol-
practice. ogy. A serious challenge to construction industries in
560 N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561

developing countries is their inability to adopt or adapt project management, the aim of which is to achieve a
established best practices already working in other defined objective within defined temporal and financial
countries [32]. Although public-sector clients in devel- constraints [37]. Thus, project outcomes are likely to be
oping countries and some donor agencies support con- low if planning and scheduling is not well done. Like
struction technology transfer, there are several problems other developing countries, Vietnam does not have ad-
associated with the transfer [33,34]. Large construction equate trained professionals in project management.
projects in Vietnam, as a developing country, usually Current managerial skills are not being fully utilized for
purchase and obtain technologies from other countries. construction management. The finding in this research
However, knowledge on whether or not the technologies accords with other reports on the situation in Vietnam
are suitable to the country’s conditions is missing. In [38].
addition, bureaucracy and fraudulent practices and
kickbacks have been publicly blamed in Vietnam. It has
been estimated elsewhere [35] that 20–40 percent of
capital investment in construction is lost due to poor 7. Conclusions
management for which bureaucracy and briberies are
mainly responsible. Therefore, professionals executing The major objective of this paper was to identify
large construction projects need to be prepared to face problems, together with the extent to which they occur
this problem. and influence performance on large construction pro-
jects in Vietnam. Sixty-two problems were identified as a
6.4. Site related issues result of a comprehensive literature survey and extensive
contributions of industry professionals in Vietnam. The
Slow site clearance and unsatisfactory site compen- construction participants accorded inaccurate time es-
sation constitute the fourth factor grouping, namely site timating, slow site clearance, slow government permits,
related issues. Project site clearance usually faces many lack of capable owner’s representatives, obsolete tech-
conflicts – internal and interface conflicts [36], between nology and unsatisfactory site compensation, high rat-
project teams and communities. This is a major cause of ings in terms of degree of occurrence and level of
interruptions in large construction projects. Compre- influence. There was strong agreement towards these
hensive site investigation such as topographical surveys rankings of problems among the different respondent
and geotechnical investigations have visible and con- groups.
siderable benefits [28]. It is, however, inadequate that In order to uncover their root causes, the problems
site issues of a large scale construction project are lim- were classified into seven categories. It was found that
ited to those tasks but they include considerations of problems under the purview of consultants, contractors
other natural, cultural and socioeconomic factors sur- and coordination were highly ranked in terms of degree
rounding the project site. Therefore, it is recommended of occurrence. Problems attributable to owners and the
that the project site should be well prepared before environment were perceived not to be as important in
commencing construction or mobilizing facilities and occurrence as their influence on performance is. In ad-
equipment. The affected people near the project site dition, problems attributed to financiers and project
should be well informed about projects and satisfactory attributes were rated low both for occurrence and
compensation offered for their properties. Environ- influence.
mental and social impact assessments should be fairly Deeper analysis revealed that there were certain in-
carried out when necessary. These will ensure that pro- terrelationships among the problems. The top-ranked
jects run smoothly and without interruptions during the problems in terms of occurrence were grouped under
construction phases. five major factors: (1) incompetent designers and con-
tractors, (2) poor estimation and change management,
6.5. Improper techniques and tools (3) social and technological issues, (4) site related issues,
and (5) improper techniques and tools. Again, it is noted
This factor consisting of inadequate modern equip- that the findings confirmed previous studies that most of
ment and improper planning and scheduling is consid- problems in construction projects are human and man-
ered in terms of the two domains of engineering and agement problems, not technical in nature [4,24].
management. Inadequate modern equipment can incur By foreseeing the common problems identified in this
problems in engineering, construction methods, e.g. the paper and maybe others in future projects, the authors
possibility to accelerate the project work is limited. hope that construction participants in Vietnam can both
Vietnamese contractors do not have enough modern avoid problems for which they are responsible and
equipment and plant to implement large and complex mitigate severe effects of the other problems. The simi-
projects. Additionally, improper project planning and larity of several findings in this research to previous
scheduling is another problem. Planning is the essence of research finding from other developing countries
N.D. Long et al. / International Journal of Project Management 22 (2004) 553–561 561

confirmed that project stakeholders in developing [18] Ling YY, Lau BSY. A case study on the management of the
countries face similar problems in spite of different development of a large-scale power plant project in East Asia
based on design-build arrangement. Int J Project Manage
natural, economic, political and social backgrounds. As 2002;20(4):413–23.
such, they should benefit from learning from each [19] Bloomberg News. Vietnam growth hits 7%, fastest in Southeast
other’s experiences. Asia. International Herald Tribune January 2, 2003.
[20] Ogunlana SO, Olomolaiye PO. A survey of site management
practice on some selected sites in Nigeria. Build Environ
1989;24(2):191–6.
References [21] Chua DKH, Wang Y, Tan WT. Impacts of obstacles in East
Asian cross-border construction. J Construct Eng Manage, ASCE
[1] Baldwin JR, Manthei JM. Causes of delays in the construction 2003;129(2):131–41.
industry. J Construct Div ASCE 1971;97(1):00–87. [22] Cheung SO, Tam CM, Ndekugri I, Harris FC. Factors affecting
[2] Arditi RD, Akan GT, Gurdamar S. Reasons for delays in public clients’ project dispute resolution satisfaction in Hong Kong.
projects in Turkey. Construct Manage Econom 1985;3:171–81. Construct Manage Econom 2000;18:281–94.
[3] Sullivan A, Harris FC. Delays on large construction projects. Int J [23] Chan DWM, Kumaraswary MM. Compressing construction
Operat Product Manage 1986;6(1):25–33. durations: lessons learned from Hong Kong building projects.
[4] Mansfield NR, Ugwu OO, Doran T. Causes of delay and cost Int J Project Manage 2002;20(1):23–35.
overruns in Nigerian construction projects. Int J Project Manage [24] Lim CS, Mohamed MZ. An exploratory study into recurring
1994;12(4):254–60. construction problems. Int J Project Manage 2000;18(3):267–73.
[5] Assaf SA, Al-Khalil M, Al-Hazmi M. Causes of delay in large [25] Zhi H. Risk management for overseas construction projects. Int J
building construction projects. J Manage Eng 1995;(March/ Project Manage 1995;13(4):231–7.
April):45–50. [26] Santoso DS, Ogunlana SO, Minato T. Perceptions of risk based
[6] Ogunlana SO, Promkuntong K, Jearkjirm V. Construction delays on level of experience for high-rise building contractors. Int J
in a fast-growing economy: comparing Thailand with other Construct Manage 2003;3(1):49–62.
economies. Int J Project Manage 1996;14(1):37–45. [27] Hair JF, Anderson RE, Tatham RL, Black WC. Multivariate data
[7] Chan DWM, Kumaraswary MM. A study of causes of the factors analysis. Fifth ed. New Jersey, USA: Prentice Hall; 1998.
affecting construction durations in Hong Kong. Construct Man- [28] Chan APC, Yeong CM. A comparison of strategies for reducing
age Econom 1995;13:319–33. variations. Construct Manage Econom 1995;13:467–73.
[8] Chan DWM, Kumaraswary MM. A comparative study of causes [29] Akintoye A. Analysis of factors influencing project cost estimating
of time overruns in Hong Kong construction projects. Int J practice. Construct Manage Econom 2000;18:77–89.
Project Manage 1997;15(1):53–63. [30] Thomas HR, Napolitan CL. Quantitative effects of construction
[9] Dissanayaka SM, Kumaraswamy MM. Evaluation of factors changes on labor productivity. J Construct Eng Manage, ASCE
affecting time and cost performance in Hong Kong building 1995;121(3):290–6.
projects. Eng, Construct Architect Manage 1999;6(3):287–98. [31] Hanna AS, Russell JS, Nordheim EV, Bruggink MJ. Impact of
[10] Al-Moumani HA. Construction delay: a quantitative analysis. Int change orders on labor efficiency for electrical construction. J
J Project Manage 2000;18(1):51–9. Construct Eng Manage, ASCE 1999;125(4):224–32.
[11] Odeh AM, Battaineh HT. Causes of construction delay: tradi- [32] Ngowi A. Challenges facing construction industries in developing
tional contracts. Int J Project Manage 2002;20(1):67–73. countries. Build Res Informat 2002;30(3):149–51.
[12] Arditi D, Gunaydin HM. Factors that affect process quality in the [33] Ofori G. Construction technology development: role of appropri-
life cycle of building projects. J Construct Eng Manage, ASCE ate policies. Eng, Construct Architect Manage 1994;1(2):147–68.
1998;124(3):194–203. [34] Carrillo P. Technology transfer: a survey of international
[13] Hinze J, Gordon F. Supervisor–worker relationship affects injury construction companies. Construct Manage Econom 1994;12(1):
rate. J Construct Div, ASCE 1979;105(3):253–62. 45–54.
[14] Oglesby CH, Parker HW, Howell GA. Productivity improvement [35] Trung X. An interview with the General Inspector of the
in construction. New York: Mc GrawHill; 1989. government. Tuoi Tre Newspaper April 27 2002;77:3 [in Viet-
[15] Sawacha E, Naoum S, Fong D. Factors affecting safety perfor- namese].
mance on construction sites. Int J Project Manage 1999;17(5):309– [36] Awakul P, Ogunlana SO. The effect of attitudinal differences on
15. interface conflicts in large scale construction projects: a case study.
[16] Sanders SR, Thomas HR. Factors affecting masonry labor Construct Manage Econom 2002;20(4):365–77.
productivity. J Construct Eng Manage, ASCE 1991;117(3):626– [37] Partington D. The project management of organizational change.
44. Int J Project Manage 1996;14(1):13–21.
[17] Chritamara S, Ogunlana SO. Problems experienced on design and [38] UNDP-VN. Country strategy note for cooperation with the
build projects in Thailand. J Construct Procurement 2001;7(1):73– United Nations system. UNDP Country Office, retrieved Febru-
86. ary 22, 2003, from website: http://www.un.org.vn.

You might also like