Leakage Test Procedure For Crude Oil Storage Tank: (Arial 12)
Leakage Test Procedure For Crude Oil Storage Tank: (Arial 12)
Leakage Test Procedure For Crude Oil Storage Tank: (Arial 12)
Name: Signature:
Date:
License TWK
LEAKAGE TEST PROCEDURE FOR
Cleaning & Relocating Crude Oil Storage Tank
Project Title
Storage Tank
Contractor Project No. Contractor Doc. No.
COMPANY Project No. KU-AAA-NNN COMPANY Doc. No.
REVISION RECORD
DNO Originated Checked
Date Description Approved by
Rev. by by
0 26.03.19 Issued for Review S.H.Fatemi A.soleyman A.Poursohrab
i
Proprietary Information
This document is the property of DNO. It must NOT be reproduced or transmitted to others
without authorization from the COMPANY.
CONTENT
1) SCOPE ------------------------------------------------------------------------------------4
2) REFERENCES --------------------------------------------------------------------------4
4) GENERAL -------------------------------------------------------------------------------4
9) PERFORMANCE ---------------------------------------------------------------------6
1) SCOPE
2) REFERENCES
2.1) API 650.
3) GENERAL REQUIREMENTS
3.1) Company shall be notified about any deviation from specification and related
standards.
3.2) Fabrication and welding shall be completed prior to system testing.
3.3) Welding clean up, non-destructive examination, shall be completed before
leakage testing is performed.
3.3.1) Leakage testing shall be performed after cleaning of storage tank. The
storage tanks shall thoroughly cleaned and free from dirt, debris, loses, and slag,
pieces of metal, weld spatter, oil and grease.
3.3.2) Leakage testing shall be performed after any cold and hot forming.
4) GENERAL
4.1) The area shall be continuously monitored by test personnel while testing in
being performed so that any change in test procedures or conditions will be
noted immediately and corrective action taken as required.
5) TEST MEDIUM
6) PRESSURE TEST
To perform a leak test, the tank should be completely filled with pure water and
left to remain full of water for 24 hours. During this time, observation and
inspection should be done. If there is any discrepancy between drawing
requirements and this procedure, the drawing requirements shall govern.
7) TEST DURATION
The test shall be maintained for an adequate time (24 hours) to detect small
and slow seepage leaks and to permit a thorough inspection.
8) TEST PREPARATION
8.1) At first, make sure the outside surface is completely dry. For this propose,
the storage tank shall be protected against rainy weather. In case of dew, test
shall be carried out after temperature balance between test fluid and vessel wall.
8.1.1) For leakage testing, all supports shall be in position and completed before
testing.
8.1.2) All lines shall be cleared of debris by flushing with water or blowing with
steam or air.
8.1.3) The executor of test shall consider temporary gasket when making
connections that will be broken for testing or reassembly after testing.
8.2) The storage tank shall be tested in the preliminary of the inspection
agency, before being painting.
9) PERFORMANCE
9.1) During filling the storage tank, the interior air shall be completely vent.
Then all shall be sealed.
9.2) The temperature of storage tank wall and testing water shall be controlled
during test.
9.3) The test conditions shall not be applied until the component and its
contents are at about same temperature.
9.4) Leakage test pressure shall normally be maintained for 24 hour.
9.5) After leakage testing is completed and approved by the inspector, the
system shall be dried.
9.6) No leakage or sweating of water from all welding joint and connections
during the leakage test shall be permitted.
9.7) System shall be dried thoroughly, immediately after draining. The drying
process may be accomplished by blowing compressed Air through the system or
by another method approved by the inspector.
9.8) All deposits including rust, mud sand etc shall be removed from inside of the
vessel.
9.9) All temporary blinds shall be removed after leakage test.
9.10) After any repair, storage tank shall be tested according to
approved leakage test procedure.