Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 13

HIRD DIVISION MMC appealed the above orders of April 11, 1988 and April 15,

1988 to the Office of the President, docketed as O.P. Case No.


3802. In an Order dated May 2, 1988, the Office of the President
denied MMCs requests for issuance of restraining orders against the
orders of the PAB. Consequently, MMC filed an Urgent Ex-Parte
[G.R. No. 137174. July 10, 2000] Partial Motion for Reconsideration dated May 6, 1988, seeking the
reconsideration of the above Order. In an Order dated May 13, 1988,
REPUBLIC OF THE PHILIPPINES, Represented by the POLLUTION the Office of the President granted the above partial motion for
ADJUDICATION BOARD (DENR), petitioner, reconsideration, thus:
vs. MARCOPPER MINING CORPORATION, respondent.

WHEREFORE, the instant Urgent Ex-Parte Motion for Reconsideration


DECISION is hereby GRANTED, and the Order of this Office, dated May 2, 1988,
is hereby set aside insofar as it denies respondent-appellants requests
GONZAGA-REYES, J.:
for issuance of restraining orders.
In this petition for review on certiorari, petitioner REPUBLIC OF
THE PHILIPPINES through the Pollution Adjudication Board of the Accordingly, the Pollution Adjudication Board, its agents, deputies or
Department of Environment and Natural Resources seeks to annul the representatives are hereby enjoined from enforcing its cease and
Decision[1] of the Court of Appeals [2] in CA-G.R. SP No. 44656 setting desist order of April 15, 1988 pending resolution by this Office of
aside the Order[3] of the Pollution Adjudication Board [4] in DENR-PAB respondent-appellants appeal from said orders.
Case No. 04-00597-96; as well as the Resolution[5] denying
reconsideration of said Decision.
It is further directed that the status quo obtaining prior to the issuance
The following antecedent facts are undisputed: of said cease and desist order be maintained until further orders from
this Office.
Respondent Marcopper Mining Corporation (MMC) was issued a
temporary permit to operate a tailings [6] sea disposal system under
TPO No. POW-85-454-EJ for the period October 31, 1985 to October It is understood, however, that during the efficacy of this restraining
21, 1986. Before it expired, MMC filed an application for the renewal order, respondent-appellant shall immediately undertake, at a cost of
thereof with the National Pollution Control Commission (NPCC). On not less than P30,000.00 a day, the building of artificial reefs and
September 20, 1986, MMC received a telegraphic order from the planting of sea grass, mangroves and vegetation on the causeway of
NPCC directing the former to (i)mmediately cease and desist from Calancan Bay under the supervision of the Pollution Adjudication
discharging mine tailings into Calancan Bay. The directive was brought Board and subject to such guidelines as the Board may impose.
about through the efforts of certain religious groups which had been
protesting MMCs tailings sea disposal system. MMC requested the SO ORDERED.[10]
NPCC to refrain from implementing the aforesaid directive until its
adoption of an alternative tailings disposal system. The NPCC granted In line with the directive from the Office of the President, the
MMCs request and called a conference to discuss possible alternative Calancan Bay Rehabilitation Project (CBRP) was created, and MMC
disposal systems. Consequently, an Environmental Technical remitted the amount of P30,000.00 a day, starting from May 13, 1988
Committee, composed of representatives from the NPCC, the Bureau to the Ecology Trust Fund (ETF) thereof. However, on June 30, 1991,
of Mines and Geo-Sciences, and MMC was created to study the MMC stopped discharging its tailings in the Bay, hence, it likewise
feasibility of various tailings disposal systems that may be appropriate ceased from making further deposits to the ETF.
for utilization by MMC and to submit its findings and recommendations
thereon. From the issuance of the Order on May 13, 1988 until the
cessation of the tailings disposal on June 30, 1991, MMC made its
Meanwhile, after the expiration of MMCs TPO No. POW-85-454- contribution to the ETF in the total amount of Thirty-Two Million Nine
EJ on October 21, 1986, the NPCC issued to MMC a new temporary Hundred and Seventy-Five Thousand Pesos
permit, TPO No. POW-86-454-EJ dated November 11, 1986, to expire (P32,975,000.00). Thereafter, MMC filed a Motion dated July 9, 1991
on February 10, 1987, with the condition that [t]he tailings disposal manifesting that it would discontinue its contributions/deposits to the
system shall be transferred to San Antonio Pond within two (2) months ETF since it had stopped dumping tailings in the Bay. MMC prayed
from the date of this permit. MMC moved for the deletion of the that the Order issued by the Office of the President on May 13, 1988
condition stating that it needed to develop and mine be lifted.
the ore deposits underneath the San Antonio pond for it to continue its
mining operations. In a letter-manifestation dated February 5, 1987, On February 5, 1993, the Office of the President rendered a
MMC requested the NPCC for an extension of TPO No. POW-86-454- decision in O.P. Case No. 3802 dismissing the appeal; affirming the
EJ and the indefinite suspension of the condition in said permit until cease and desist Order issued by the PAB; and lifting the TRO dated
such time that the NPCC shall have finally resolved the NPCC case May 13, 1988. The Office of the President resolved the appeal in this
entitled Msgr. Rolly Oliverio, et al. vs. Marcopper Mining Corporation. wise:

In the meantime, the NPCC was abolished by Executive Order


This brings to the fore the primordial issue of whether or not the
No. 192[7] dated June 10, 1987, and its powers and functions were
Secretary of Environment and Natural Resources gravely erred in
integrated into the Environmental Management Bureau and into the
declaring the TPO No. POW-86-454-EJ issued to respondent-appellant
Pollution Adjudication Board (PAB).[8]
MMC expired on February 10, 1987, and in ordering the latter to cease
On April 11, 1988, the Secretary of Environment and Natural and desist from discharging mine tailings into Calancan Bay.
Resources, in his capacity as Chairman of the PAB, issued an Order
directing MMC to cease and desist from discharging mine tailings into Respondent-appellant argues that the cease and desist orders were
Calancan Bay. The order reads: issued by the PAB ex-parte, in violation of its procedural and
substantive rights provided for under Section 7 (a) of P.D. No. 984
The Temporary Permit to Operate issued to Marcopper Mining requiring a public hearing before any order or decision for the
Corporation expired on February 10, 1987. discontinuance of discharge of a sewage or industrial wastes into the
water, air or land could be issued by the PAB.

Section 96 of the National Pollution Control Commission (NPCC) Rules


and Regulations, which were adopted by the Board, provides that in no We are not persuaded.
case can a permit be valid for more than one (1) year.
Section 7(a) of P.D. No. 984, reads in part:
Records show that Marcopper Mining Corporation has not filed any
application for renewal of the permit. Sec. 7(a) Public Hearing. Public hearing shall be conducted by the
Commissioner, Deputy Commissioner or any senior official duly
Marcopper Mining Corporation is hereby ordered to cease and desist designated by the Commissioner prior to issuance or promulgation of
from discharging mine tailings into Calancan Bay immediately upon any order or decision by the Commissioner requiring the
receipt of this Order. discontinuance of discharge of sewage, industrial wastes and other
wastes into the water, air or land resources of the Philippines as
provided in the Decree: provided, that whenever the Commission finds
SO ORDERED.[9] a prima facie evidence that the discharged sewage or wastes are of
immediate threat to life, public health, safety or welfare, or to animal or
Immediately thereafter, the DENR Undersecretary for plant life, or exceeds the allowable standards set by the Commission,
Environment and Research issued a telegraphic order dated April 15, the Commissioner may issue an ex-parte order directing the
1988, enjoining immediate compliance by MMC of the cease and discontinuance of the same or the temporary suspension or cessation
desist order of April 11, 1988.
1
of operation of the establishment or person generating such sewage or In view of the foregoing, the instant petition is hereby GRANTED and,
wastes without the necessity of a prior public hearing. x x x . accordingly, the questioned Order of respondent Pollution Adjudication
(underscoring supplied). Board dated 23 April 1997 is hereby SET ASIDE. Respondents are
ordered to REFRAIN and DESIST from enforcing aforesaid Order. The
injunctive bond filed by the petitioner in the amount of Five Hundred
Clearly then, it is self-indulgent nonsense to assume that the DENR
Thousand (P500,000.00) is hereby RELEASED.
Secretary, acting as PAB Chairman, is absolutely without authority to
issue an ex-parte order requiring the discontinuance of discharge of The motion for reconsideration of the above decision was denied
sewage or other industrial wastes without public hearing. As can be in a Resolution dated January 13, 1999 of the Court of Appeals.
gleaned from the afroequoted proviso, this authority to issue an ex-
parte order suspending the discharge of industrial wastes is postulated Hence, the instant petition on the following grounds:
upon his finding of prima-facie evidence of an imminent threat to life,
public health, safety or welfare, to animal or plant life or exceeds the I
allowable standards set by the Commission.[11]
The Court of Appeals erred in ruling that Republic Act No. 7942
In a letter dated January 22, 1997 [12], Municipal Mayor Wilfredo
(otherwise known as the Philippine Mining Act of 1995) repealed the
A. Red of Sta. Cruz, Marinduque informed the PAB that MMC stopped
provisions of Republic Act No. 3931, as amended by Presidential
remitting the amount of 30,000.00 per day as of July 1, 1991 to the
Decree No. 984, (otherwise known as the National Pollution Control
ETF of the CBRP. This letter-complaint of Mayor Red was docketed as
Decree of 1976), with respect to the power and function of petitioner
DENR-PAB Case No. 04-00597-96, for violation of P.D. 984 [13] and its
Pollution Adjudication Board to issue, renew or deny permits for the
implementing Rules and Regulations.
discharge of the mine tailings.
In an order dated April 23, 1997, the PAB ruled that the
II
obligation of MMC to deposit P30,000.00 per day to the ETF of the
CBRP subsists, as provided for in the Order of the Office of the
President dated May 13, 1988, during the efficacy of said order Respondent Marcopper Mining Corporation bound itself to pay the
restraining the PAB from enforcing its cease and desist order against amount of P30,000.00 a day for the duration of the period starting May
MMC. Since the Order was lifted only on February 5, 1993, the 13, 1988 up to February 5, 1993.
obligation of MMC to remit was likewise extinguished only on said date
and not earlier as contended by MMC from the time it ceased dumping III
tailings into the Bay on July 1, 1991. We quote in part:
Respondent Marcopper Mining Corporation was not deprived of due
The issue before this Board is whether Marcopper Mining Corporation process of law when petitioner Pollution Adjudication Board directed it
is still obliged to remit the amount of P30,000.00 to the CBRP. The to comply with its long-existing P30,000.00 per day obligation under
answer by the Order from the Office of the President dated 13 May the Order of the Office of the President dated May 13, 1988. [15]
1988, which states that the obligation on the part of Marcopper Mining
to pay the amount of P30,000.00 per day for the rehabilitation of In setting aside the Order of the PAB dated April 23, 1997,
Calancan Bay is binding only during the efficacy of the said Order. requiring MMC to pay its arrears in deposits, the Court of Appeals
ruled that the PAB exceeded its power and authority in issuing the
subject Order for the following reasons:
The record further shows that on 05 February 1993, the Office of the
President lifted its Order dated 13 May 1988. This means that as of the
date of the lifting, Marcopper Mining Corporation no longer had any The applicable and governing law in this petition is Republic Act No.
obligation to remit the amount of P30,000.00 to the CBRP. Thus, 7942 otherwise known as the Philippine Mining Act of 1995 (Mining
Marcoppers obligation only runs from 13 May 1988 to 05 February Act, approved on March 3, 1995).
1993. Beyond the cut-off date of 05 February 1993, Marcopper is no
longer obligated to remit the amount of P30,000.00 per day to the Chapter XI of the Mining Act contains a series of provisions relating to
CBRP. safety and environmental protection on mining and quarrying
operations. More specifically, Section 67 of the Mining Act in essence,
It does not matter whether Marcopper was no longer dumping its tail grants the mines regional director the power to issue orders or to take
minings into the sea even before the cut-off date of 05 February appropriate measures to remedy any practice connected with mining or
1993. The obligation of Marcopper to pay the amount of P30,000.00 to quarrying operations which is not in accordance with safety and anti-
the CBRP arises from the Office of the President Order dated 13 May pollution laws and regulations.
1988, not from it dumping of mine tailings.
From a reading of that provision, it would appear therefore that prior to
WHEREFORE, Marcopper Mining Corporation is hereby ordered to the passage of the Mining Act, the Pollution Adjudication Board had
pay the CBRP the amount of P30,000.00 per day, computed from the jurisdiction to act on pollution-related matters in the mining
date Marcopper Mining Corporation stopped paying on 01 July business. With the effectivity of the Mining Act and in congruence with
1991, up to the formal lifting of the subject Order from the Office of the its Sec. 115 (i.e., Repealing and Amending Clause), the power to
President on 05 February 1993. impose measures against violations of environmental policies by
mining operators is now vested on the mines regional director. Be that
as it may, we are constrained to enunciate that the PAB had no
SO ORDERED.[14] authority to issue the challenged Order dated 23 April 1997. More so,
respondent PAB as petitioner argued and We note, had remained
MMC assailed the aforequoted Order dated April 23, 1997 of the perplexingly silent on the matter for almost six (6) years from July 1991
PAB as null and void for having been issued without jurisdiction or with when MMC ceased to make its deposits up to April 1997 when
grave abuse of discretion in a petition for Certiorari and Prohibition respondent PAB precipitately issued the Order requiring MMC to pay
(with prayer for temporary restraining order and preliminary injunction) its arrears in deposits to the ETF. And PAB, apparently oblivious to
before the Court of Appeals which was docketed as CA-G.R. No. SP- MMCs economic quandary had issued said Order ex-parte without
44656. In a Resolution dated July 15, 1997, the Court of Appeals hearing or notice.
required the PAB and its members to comment on said petition.
x x x
On November 19, 1997, the Office of the Solicitor General, on
behalf of the PAB and its members, filed with the Court of Appeals the
required comment. As a general rule, the adjudication of pollution cases pertains to the
Pollution Adjudication Board (PAB), except in cases where the special
On September 15, 1997, for purposes of determining whether or law, expressly or impliedly, provides for another forum, as in the instant
not to grant MMCs prayer for a temporary restraining order and petition.
preliminary injunction, the Court of Appeals conducted a hearing where
counsel for the parties were heard on oral arguments.
Thus under Republic Act No. 7942 and its implementing rules and
In a Resolution dated September 19, 1997, the Court of Appeals regulations, the mines regional director, in consultation with
issued a writ of preliminary injunction, conditioned upon the filing of a the Environmental Management Bureau (italics ours), is specifically
bond by MMC in the amount of P500,000.00 enjoining the PAB and its mandated to carry out and make effective the declared national policy
members to cease and desist from enforcing the assailed Order dated that the State shall promote the rational exploration, development,
April 23, 1997, until it had made a full determination on the merits of utilization and conservation of all mineral resources in public and
the case. private lands within the territory and exclusive economic zone of the
Republic of the Philippines, through the combined efforts of
On January 7, 1998, the Court of Appeals promulgated a government and the private sector in order to enhance national growth
Decision in CA-G.R. SP No. 44656, the dispositive portion of which and protect the rights of affected communities. (Sec. 2, R.A. 7942).
reads:

2
Under this expansive authority, the Mines Regional Director, by virtue authority to try and hear pollution cases connected with mining
of this special law, has the primary responsibility to protect the operations by virtue of the subsequent enactment of RA 7942
communities surrounding a mining site from the deleterious effects of (Philippine Mining Act of 1995)? As mentioned earlier, the PAB took
pollutants emanating from the dumping of tailing wastes from the cognizance and ruled on the letter-complaint (for violation of PD 984
surrounding areas. Thus, in the exercise of its express powers under and its implementing rules and regulations) filed against MMC by
this special law, the authority of the Mines Regional Director to impose Marinduque Mayor Wilfredo Red. In the subject Order dated April 23,
appropriate protective and/or preventive measures with respect to 1997, the PAB ruled that MMC should pay its arrears in deposits to the
pollution cases within mining operations is perforce, ETF of the CBRP computed from the day it stopped dumping and
implied. Otherwise, the special law granting this authority may well be paying on July 1, 1991 up to the lifting of the Order of the Office of the
relegated to a mere paper tiger talking protection but allowing pollution. President dated May 13, 1988 on February 5, 1993.

The answer is in the negative. We agree with the Solicitor


It bears mention that the Pollution Adjudication Board has the power to General that the Court of Appeals committed reversible error in ruling
issue an ex-parte order when there is prima facie evidence of an that the PAB had no authority to issue the Order dated April 23, 1997.
establishment exceeding the allowable standards set by the anti-
pollution laws of the country. (Pollution Adjudication Board v. Court of Republic Act No. 3931 (An Act Creating The National Water And
Appeals, et al., 195 SCRA 112). However, with the passage of R.A. Air Pollution Control Commission) was passed in June 18, 1964 to
7942, insofar as the regulation, monitoring and enforcement of anti- maintain reasonable standards of purity for the waters and air of the
pollution laws are concerned with respect to mining establishments, country with their utilization for domestic, agricultural, industrial and
the Mines Regional Director has a broad grant of power and other legitimate purposes. Said law was revised in 1976 by
authority. Clearly, pollution-related issues in mining operations are Presidential Decree No. 984 (Providing For The Revision Of Republic
addressed to the Mines Regional Director, not the Pollution Act No. 3931, Commonly Known As The Pollution Control Law, And
Adjudication Board. For Other Purposes) to strengthen the National Pollution Control
Commission to best protect the people from the growing menace of
environmental pollution. Subsequently, Executive Order No. 192, s.
This being the case, the questioned Order dated 23 April 1997
1987 (The Reorganization Act of the DENR) was passed. The internal
requiring MMC to pay its arrears in deposits was beyond the power
structure, organization and description of the functions of the new
and authority of the Pollution Adjudication Board to issue and as such,
DENR, particularly the Mines and Geosciences Bureau, reveals no
petitioner may seek appropriate injunctive relief from the court. Thus,
provision pertaining to the resolution of cases involving violations of the
certiorari lies against public respondent PAB.[16]
pollution laws.[18] The Mines and Geo-Sciences Bureau was created
The Court of Appeals likewise ruled that the obligation of MMC to under the said EO 192 to absorb the functions of the abolished Bureau
contribute to the ETF of the CBRP ceased inasmuch as the latter of Mines and Geo-Sciences, Mineral Reservations Development Board
discontinued dumping tailings into the Bay and the actual funds in the and the Gold Mining Industry Development Board to, among others,
ETF are sufficient to rehabilitate the Bay. It ratiocinated thus: recommend policies, regulations and programs pertaining to mineral
resources development; assist in the monitoring and evaluation of the
Bureaus programs and projects; and to develop and promulgate
In the instant case, it is of record that petitioner MMC undertakes its standards and operating procedures on mineral resources
obligation to provide for the rehabilitation of the Bay waters. This development.[19]
obligation, through its monetary contribution to the ETF, is however
anchored on its continuing disposal of the mines tailings waste into the On the other hand, the PAB was created and granted under the
Bay. Hence, since it ceased its mining operations in the affected area same EO 192 broad powers to adjudicate pollution cases in
as of July 1991 and had not been discharging any tailings wastes since general. Thus,
then, its consequent duty to rehabilitate the polluted waters, if any, no
longer exists.
SEC. 19. Pollution Adjudication Board. There is hereby created a
x x x Pollution Adjudication Board under the Office of the Secretary. The
Board shall be composed of the Secretary as Chairman, two (2)
Undersecretaries as may be designated by the Secretary, the Director
Be that as it may, this Court observes that out of the approximate sum of Environmental management, and three (3) others to be designated
of thirty-two (32) million pesos contributed by the petitioner to the ETF by the Secretary as members. The Board shall assume the powers
there is admittedly an existing estimated balance of fourteen (14) and functions of the Commission/Commissioners of the National
million pesos in the Fund. For its part, petitioner does not renege on its Pollution Control Commission with respect to the adjudication of
obligation to rehabilitate and in fact undertakes to continue the pollution cases under Republic Act 3931 and Presidential Decree 984,
rehabilitation process until its completion within two (2) years time and particularly with respect to Section 6 letters e, f, g, j, k, and p of P.D.
which would only cost six (6) million pesos. Thus, as petitioner 984. The Environmental Management Bureau shall serve as the
convincingly argued and which respondent unsatisfactorily rebuked, Secretariat of the Board. These powers and functions may be
the existing fourteen (14) million pesos in the ETF is more than enough delegated to the regional offices of the Department in accordance with
to complete the rehabilitation project. (TSN, Hearing dated 15 rules and regulations to be promulgated by the Board. [20]
September 1997, at pp. 56 to 62, Rollo).
Section 6 letters e, f, g, j, k, and p of PD 984 referred to above
are quoted as follows:
xxx. Without much ado, the Court concurs with the finding that to
demand a daily deposit of thirty thousand (P30, 000.00) pesos even if SEC. 6. Powers and Functions. The Commission shall have the
the root of the obligation, that is, the dumping of tailings waste, had following powers and functions:
ceased to exist, is indubitably of a herculean and onerous burden on
the part of petitioner amounting to a deprivation of its property and a (e) Issue orders or decision to compel compliance with the
denial of its right to due process.[17] provisions of this Decree and its implementing rules
and regulations only after proper notice and hearing.
Unsatisfied, the OSG argues that the Philippine Mining Act of
1995 did not amend or repeal the provisions of Republic Act No. 3931, (f) Make, alter or modify orders requiring the
as amended by Presidential Decree No. 984 (otherwise known as the discontinuance of pollution specifying the conditions
National Pollution Control Decree of 1976); that the Mines Regional and the time within which such discontinuance must
Director has no power over areas outside mining installations and over be accomplished.
areas which are not part of the mining or quarrying operations such as
Calancan Bay; that the powers of the Mines Regional Director cannot (g) Issue, renew, or deny permits, under such conditions
be exercised to the exclusion of other government agencies; that the as it may determine to be reasonable, for the
jurisdiction of a Mines Regional Director with respect to anti-pollution prevention and abatement of pollution, for the
laws is limited to practices committed within the confines of a mining or discharge of sewage, industrial waste, or for the
quarrying installation; that the dumping of mine tailings into Calancan installation or operation of sewage works and industrial
Bay occurred long before the effectivity of the Philippine Mining Act disposal system or parts thereof: Provided, however,
and that MMC cannot hide under cover of this new law. The OSG That the Commission, by rules and regulations, may
further argues that theportion of the Order of May 13, 1988, setting the require subdivisions, condominium, hospitals, public
period of time within which MMC shall pay P30,000.00 per day, which buildings and other similar human settlements to put
is during the efficacy of the restraining order was never questioned or up appropriate central sewerage system and sewage
appealed by MMC. Finally, the OSG argues that PAB did not violate treatment works, except that no permits shall be
MMCs right to due process by the issuance of the Order dated April required to any sewage works or changes to or
23, 1988 without notice and hearing as it was simply requiring MMC to extensions of existing works that discharge only
comply with an obligation in an Order which has long become final and domestic or sanitary wastes from a singles residential
executory. building provided with septic tanks or their
equivalent. The Commission may impose reasonable
In the context of the established facts, the issue that actually fees and charges for the issuance or renewal of all
emerges is: Has the PAB under RA 3931 as amended by PD 984 permits required herein.
(National Pollution Control Decree of 1976) been divested of its
3
(h) and not have enacted conflicting statutes. Hence, all doubts must be
resolved against any implied repeal, and all efforts should be exerted
(i) in order to harmonize and give effect to all laws on the subject.[22]
(j) Serve as arbitrator for the determination of reparations, There is no irreconcilable conflict between the two laws. Section
or restitution of the damages and losses resulting from 19 of EO 192 vested the PAB with the specific power to adjudicate
pollution. pollution cases in general. Sec. 2, par. (a) of PD 984 defines the term
pollution as referring to any alteration of the physical, chemical and
(k) Deputize in writing or request assistance of appropriate biological properties of any water, air and/or land resources of the
government agencies or instrumentalities for the Philippines , or any discharge thereto of any liquid, gaseous or solid
purpose of enforcing this Decree and its implementing wastes as will or is likely to create or to render such water, air and land
rules and regulations and the orders and decisions of resources harmful, detrimental or injurious to public health, safety or
the Commission. welfare or which will adversely affect their utilization for domestic,
(l) commercial, industrial, agricultural, recreational or other legitimate
purposes.
(m)
On the other hand, the authority of the mines regional director is
(n) complementary to that of the PAB. Section 66 of RA 7942 gives the
mines regional director exclusive jurisdiction over the safety inspection
(o) of all installations, surface or underground in mining
operations. Section 67 thereof vests upon the regional director power
(p) Exercise such powers and perform such other to issue orders requiring a contractor to remedy any practice
functions as may be necessary to carry out its duties connected with mining or quarrying operations which is not in
and responsibilities under this Decree. accordance with safety and anti-pollution laws and regulations; and to
summarily suspend mining or quarrying operations in case of imminent
Section 7(a) of P.D. No. 984 further provides in part: danger to life or property. The law likewise requires every contractor to
undertake an environmental protection and enhancement program
which shall be incorporated in the work program which the contractor
Sec. 7(a) Public Hearing. Public hearing shall be conducted by the shall submit as an accompanying document to the application for a
Commissioner, Deputy Commissioner or any senior official duly mineral agreement or permit. In addition, an environmental clearance
designated by the Commissioner prior to issuance or promulgation of certificate is required based on an environment impact
any order or decision by the Commissioner requiring the assessment. The law also requires contractors and permittees to
discontinuance of discharge of sewage, industrial wastes and other rehabilitate the mined-out areas, and set up a mine rehabilitation
wastes into the water, air or land resources of the Philippines as fund. Significantly, the law allows and encourages peoples
provided in the Decree: provided, that whenever the Commission finds organizations and non-governmental organizations to participate in
a prima facie evidence that the discharged sewage or wastes are of ensuring that contractors/permittees shall observe all the requirements
immediate threat to life, public health, safety or Welfare, or to animal or of environmental protection.
plant life, or exceeds the allowable standards set by the Commission,
the Commissioner may issue and ex-parte order directing the From the foregoing, it readily appears that the power of the
discontinuance of the same or the temporary suspension or cessation mines regional director does not foreclose PABs authority to determine
of operation of the establishment or person generating such sewage or and act on complaints filed before it. The power granted to the mines
wastes without the necessity of a prior public hearing. x x x . regional director to issue orders requiring the contractor to remedy any
(underscoring supplied). practice connected with mining or quarrying operations or to summarily
suspend the same in cases of violation of pollution laws is for purposes
The ruling of the Court of Appeals that the PAB has been of effectively regulating and monitoring activities within mining
divested of authority to act on pollution-related matters in mining operations and installations pursuant to the environmental protection
operations is anchored on the following provisions of RA 7942 and enhancement program undertaken by contractors and permittees
(Philippine Mining Act of 1995): in procuring their mining permit. While the mines regional director has
express administrative and regulatory powers over mining operations
SEC. 67. Power to Issue Orders. The mines regional director shall, in and installations, it has no adjudicative powers over complaints for
consultation with the Environmental Management Bureau, forthwith or violation of pollution control statutes and regulations.
within such time as specified in his order, require the contractor to
True, in Laguna Lake Development Authority vs. Court of
remedy any practice connected with mining or quarrying operations,
Appeals,[23] this Court held that adjudication of pollution cases generally
which is not in accordance with safety and anti-pollution laws and
pertains to the Pollution Adjudication Board (PAB) except where the
regulations. In case of imminent danger to life or property, the mines
special law provides for another forum. However, contrary to the ruling
regional director may summarily suspend the mining or quarrying
of the Court of Appeals, RA 7942 does not provide for another forum
operations until the danger is removed, or appropriate measures are
inasmuch as RA 7942 does not vest quasi-judicial powers in the Mines
taken by the contractor or permittee.
Regional Director. The authority is vested and remains with the PAB.
And
Neither was such authority conferred upon the Panel of
Arbitrators and the Mines Adjudication Board which were created by
SEC. 115. Repealing and Amending Clause. All laws, executive the said law. The provisions creating the Panel of Arbitrators for the
orders, presidential decrees, rules and regulations, or parts thereof settlement of conflicts refers to disputes involving rights to mining
which are inconsistent with any of the provisions of this Act are hereby areas, mineral agreements or permits and those involving surface
repealed or amended accordingly. owners, occupants and claim-holders/concessionaires.[24] The scope of
authority of the Panel of Arbitrators and the Mines Adjudication Board
The other provisions in Chapter XI on Safety and Environmental conferred by RA 7942 clearly exclude adjudicative responsibility over
Protection found in RA 7942 promote the safe and sanitary upkeep of pollution cases. Nowhere is there vested any authority to adjudicate
mining areas to achieve waste-free and efficient mine development cases involving violations of pollution laws and regulations in general.
with particular concern for the physical and social rehabilitation of
areas and communities affected by mining activities [21], without Thus, there is no genuine conflict between RA 7942 and RA
however, arrogating unto the mines regional director any adjudicative 3931 as amended by PD 984 that precludes their co-existence.
responsibility. Moreover, it has to be conceded that there was no intent on the part of
the legislature to repeal the said law. There is nothing in the
From a careful reading of the foregoing provisions of law, we sponsorship speech[25] of the laws proponent, Representative Renato
hold that the provisions of RA 7942 do not necessarily repeal RA 3931, Yap, and the deliberations that followed thereafter, to indicate a
as amended by PD 984 and EO 192. RA 7942 does not contain any legislative intent to repeal the pollution law. Instead, it appears that the
provision which categorically and expressly repeals the provisions of legislature intended to maximize the exploration, development and
the Pollution Control Law. Neither could there be an implied repeal. It utilization of the countrys mineral resources to contribute to the
is well-settled that repeals of laws by implication are not favored and achievement of national economic and social development with due
that courts must generally assume their congruent application. Thus, it regard to the social and environmental cost implications relative
has been held: thereto. The law intends to increase the productivity of the countrys
mineral resources while at the same time assuring its sustainability
The two laws must be absolutely incompatible, and a clear finding through judicious use and systematic rehabilitation. Henceforth, the
thereof must surface, before the inference of implied repeal may be Department of Environment and Natural Resources as the primary
drawn. The rule is expressed in the maxim, interpretare et concordare government agency responsible for the conservation, management,
leqibus est optimus interpretendi, i.e., every statute must be so development, and proper use of the States mineral resources, through
interpreted and brought into accord with other laws aas to form a its Secretary, has the authority to enter into mineral agreements on
uniform system of jurisprudence.The fundament is that the legislature behalf of the Government upon the recommendation of the Director,
should be presumed to have known the existing laws on the subject and to promulgate such rules and regulations as may be necessary to
carry out the provisions of RA 7942. [26] The PAB and the Mines
4
Regional Director, with their complementary functions and through Well Your Honor, I cannot comment on the amount Your Honor.
their combined efforts, serve to accomplish the mandate of RA 3931
(National Pollution Control Decree of 1976) as amended by PD 984 JUSTICE RASUL:
and EO 192 and that of RA 7942 (Philippine Mining Act of 1995).
You have already made your comment, but you received some
That matter settled, we now go to the issue of whether the signal from your lawyer.
appellate court erred in ruling that there is no basis for further
ATTY. HERNANDEZ:
payments by MMC to the Ecology Trust Fund of the Calancan Bay
Rehabilitation Project considering that MMC convincingly argued and Your Honor . . .
which respondent unsatisfactorily rebuked, the existing fourteen (14)
million pesos in the ETF is more than enough to complete the MR. EDEL GENATO:
rehabilitation project. Indeed, the records reveal that witness for PAB,
Mr. Edel Genato, who is the Technical Resource person of the PAB for No, no Your Honor. . .
the project admitted that the funds in the ETF amounting to about
Fourteen Million Pesos are more than sufficient to cover the costs of JUSTICE RASUL:
rehabilitation. Hereunder are excerpts from the transcript of
My question is, do you agree with him that the 14 million fund will
stenographic notes taken during the hearing held on September 15,
be enough to sustain the construction up to the end?
1997:
MR. EDEL GENATO:
ATTY. HERNANDEZ:[27]
Two years?
I would like your Honor, if the court will allow, our witness from the
EBRB Your Honor would attest to that . . . JUSTICE RASUL:
JUSTICE JACINTO: Yes.
Is it not being taken from the 14 million? MR. EDEL GENATO:
ATTY. HERNANDEZ: Your Honor. . .
Yes, Your Honor. JUSTICE AMIN:
JUSTICE RASUL: Categorical answer.
What is his role? JUSTICE RASUL:
ATTY. HERNANDEZ: You just answer, is it enough, in your own honest way, on your
honor?
He is our Technical Resource person Your Honor, of the project.
MR. EDEL GENATO:
JUSTICE RASUL:
I think so Your Honor.[28]
In other words, he has participated in the . . (inaudible)?
We must sustain the appellate court on this point on account of
ATTY. HERNANDEZ:
the testimony of Mr. Edel Genato. Further, we note that the Office of
Yes, Your Honor. the President never objected nor ruled on themanifestation dated July
9, 1991 filed by MMC that it would stop paying since it already ceased
JUSTICE RASUL: dumping mine tailings into the bay. Still further, the order of the OP
directing MMC to rehabilitate at a cost of P30,000.00 a day during the
Do you agree with him? efficacy of the restraining order had become functus officio since MMC
voluntarily stopped dumping mine tailings into the bay.
MR. EDEL GENATO:
To sum up, PAB has jurisdiction to act and rule on the letter-
Yes, Your Honor, that the Calancan rehabilitation program is being complaint of Mayor Wilfredo Red of Marinduque for violation of PD 984
funded by Marcopper through the Ecology Trust Fund. and its implementing rules and regulations which jurisdiction was not
lost upon the passage of RA 7942 (the Philippine Mining Act of
JUSTICE RASUL:
1995). Nevertheless, MMC must be declared not to have arrears in
Will the construction be finished in two years time? deposits as admittedly, the ETF already has more than sufficient funds
to undertake the rehabilitation of Calancan Bay.
MR. EDEL GENATO:
WHEREFORE, the petition is hereby partially GRANTED. The
Presently, under the Steering Committee of the Calancan Bay assailed Decision is REVERSED insofar as the jurisdiction of the PAB
Rehabilitation, there is another phase that is being to act on the complaint is concerned; but AFFIRMED insofar as
proposed. Actually the two years time will definitely cover the Marcopper Mining Corporation has no arrears in deposits with the
other phase of the . .(inaudible) Ecology Trust Fund of the Calancan Bay Rehabilitation Project.

JUSTICE RASUL: SO ORDERED.

Never mind that. Will the amount be sufficient to the end of the ORGE GONZALES and G.R. No. 161957
construction? PANEL OF ARBITRATORS,
Petitioners, Present:
MR. EDEL GENATO:
 
Yes, Sir. PUNO, C. J.,
Chairperson,
JUSTICE RASUL: -        versus AUSTRIA-MARTINEZ,
C
Enough? ALLEJO,
SR.,
MR. EDEL GENATO: TINGA,
Yes, Sir. and
NAZARIO, JJ.
JUSTICE RASUL: CLIMAX MINING LTD.,
CLIMAX-ARIMCO MINING CORP.,
There is no more need for collecting the 30 thousand a and AUSTRALASIAN PHILIPPINES Promulgated:
day? . . . Do not . . . I will hold you for contempt . . . MINING INC.,
Respondents. January 22, 2007
ATTY. HERNANDEZ:  
x--------------------------------------------------------------------------------- x
Im sorry Your Honor.
 
JUSTICE RASUL:  
JORGE GONZALES, G.R. No. 167994
Again. Petitioner,
 
MR. EDEL GENATO:  
5
-        versus acts of fraud, oppression and violation of the Constitution. Thus, the
  arbitration clause, Clause 19.1, contained in the Addendum Contract is also
  null and void ab initioand legally inexistent.
HON. OSCAR B. PIMENTEL, in his  
capacity as PRESIDING JUDGE of BR. 148 On 18 May 2000, the RTC issued an order declaring Gonzaless motion to
of the REGIONAL TRIAL COURT of dismiss moot and academic in view of the filing of his Answer with
MAKATI CITY, and CLIMAX-ARIMCO Counterclaim.[13]
MINING CORPORATION,  
Respondents. On 31 May 2000, Gonzales asked the RTC to set the case for pre-trial. [14] This
x-------------------------- --------------------------------------------------- x the RTC denied on 16 June 2000, holding that the petition for arbitration is a
  special proceeding that is summary in nature. [15] However, on 7 July 2000, the
  RTC granted Gonzaless motion for reconsideration of the 16 June 2000 Order
  and set the case for pre-trial on 10 August 2000, it being of the view that
R E S O L U T I ON Gonzales had raised in his answer the issue of the making of the arbitration
  agreement.[16]
TINGA, J.:  
  Climax-Arimco then filed a motion to resolve its pending motion to compel
This is a consolidation of two petitions rooted in the same disputed arbitration. The RTC denied the same in its 24 July 2000 order.
Addendum Contract entered into by the parties. In G.R. No. 161957, the Court  
in its Decision of 28 February 2005[1] denied the Rule 45 petition of petitioner On 28 July 2000, Climax-Arimco filed a Motion to Inhibit Judge Herminio I.
Jorge Gonzales (Gonzales). It held that the DENR Panel of Arbitrators had no Benito for not possessing the cold neutrality of an impartial judge. [17] On 5
jurisdiction over the complaint for the annulment of the Addendum Contract August 2000, Judge Benito issued an Order granting the Motion to Inhibit and
on grounds of fraud and violation of the Constitution and that the action ordered the re-raffling of the petition for arbitration. [18] The case was raffled to
should have been brought before the regular courts as it involved judicial the sala of public respondent Judge Oscar B. Pimentel of Branch 148.
issues. Both parties filed separate motions for reconsideration. Gonzales avers  
in his Motion for Reconsideration[2] that the Court erred in holding that the On 23 August 2000, Climax-Arimco filed a motion for reconsideration of
DENR Panel of Arbitrators was bereft of jurisdiction, reiterating its argument the 24 July 2000 Order.[19] Climax-Arimco argued that R.A. No. 876 does not
that the case involves a mining dispute that properly falls within the ambit of authorize a pre-trial or trial for a motion to compel arbitration but directs the
the Panels authority. Gonzales adds that the Court failed to rule on other court to hear the motion summarily and resolve it within ten days from
issues he raised relating to the sufficiency of his complaint before the DENR hearing. Judge Pimentel granted the motion and directed the parties to
Panel of Arbitrators and the timeliness of its filing. arbitration. On 13 February 2001, Judge Pimentel issued the first assailed
  order requiring Gonzales to proceed with arbitration proceedings and
Respondents Climax Mining Ltd., et al., (respondents) filed their Motion for appointing retired CA Justice Jorge Coquia as sole arbitrator.[20]
Partial Reconsideration and/or Clarification[3] seeking reconsideration of that  
part of the Decision holding that the case should not be brought for arbitration Gonzales moved for reconsideration on 20 March 2001 but this was denied in
under Republic Act (R.A.) No. 876, also known as the Arbitration Law. the Order dated 7 March 2005.[21]
[4]
 Respondents, citing American jurisprudence [5] and the UNCITRAL Model  
Law,[6] argue that the arbitration clause in the Addendum Contract should be Gonzales thus filed the Rule 65 petition assailing the Orders
treated as an agreement independent of the other terms of the contract, and dated 13 February 2001 and 7 March 2005 of Judge Pimentel. Gonzales
that a claimed rescission of the main contract does not avoid the duty to contends that public respondent Judge Pimentel acted with grave abuse of
arbitrate. Respondents add that Gonzaless argument relating to the alleged discretion in immediately ordering the parties to proceed with arbitration
invalidity of the Addendum Contract still has to be proven and adjudicated on despite the proper, valid, and timely raised argument in his Answer with
in a proper proceeding; that is, an action separate from the motion to compel Counterclaim that the Addendum Contract, containing the arbitration clause,
arbitration. Pending judgment in such separate action, the Addendum Contract is null and void. Gonzales has also sought a temporary restraining order to
remains valid and binding and so does the arbitration clause prevent the enforcement of the assailed orders directing the parties to arbitrate,
therein. Respondents add that the holding in the Decision that the case should and to direct Judge Pimentel to hold a pre-trial conference and the necessary
not be brought under the ambit of the Arbitration Law appears to be premised hearings on the determination of the nullity of the Addendum Contract.
on Gonzaless having impugn[ed] the existence or validity of the addendum  
contract. If so, it supposedly conveys the idea that Gonzaless unilateral In support of his argument, Gonzales invokes Sec. 6 of R.A. No.
repudiation of the contract or mere allegation of its invalidity is all it takes to 876:
avoid arbitration. Hence, respondents submit that the courts holding that the  
case should not be brought under the ambit of the Arbitration Law be SEC. 6. Hearing by court.A party
understood or clarified as operative only where the challenge to the arbitration aggrieved by the failure, neglect or refusal of another
agreement has been sustained by final judgment. to perform under an agreement in writing providing
  for arbitration may petition the court for an order
Both parties were required to file their respective comments to the other partys directing that such arbitration proceed in the manner
motion for reconsideration/clarification.[7] Respondents filed their Comment provided for in such agreement. Five days notice in
on 17 August 2005,[8] while Gonzales filed his only on 25 July 2006.[9] writing of the hearing of such application shall be
  served either personally or by registered mail upon
On the other hand, G.R. No. 167994 is a Rule 65 petition filed on 6 May the party in default. The court shall hear the parties,
2005, or while the motions for reconsideration in G.R. No. 161957[10] were and upon being satisfied that the making of the
pending, wherein Gonzales challenged the orders of the Regional Trial Court agreement or such failure to comply therewith is not
(RTC) requiring him to proceed with the arbitration proceedings as sought by in issue, shall make an order directing the parties to
Climax-Arimco Mining Corporation (Climax-Arimco). proceed to arbitration in accordance with the terms of
  the agreement. If the making of the agreement or
On 5 June 2006, the two cases, G.R. Nos. 161957 and 167994, were default be in issue the court shall proceed to
consolidated upon the recommendation of the Assistant Division Clerk of summarily hear such issue. If the finding be that no
Court since the cases are rooted in the same Addendum Contract. agreement in writing providing for arbitration was
  made, or that there is no default in the proceeding
We first tackle the more recent case which is G.R. No. 167994. It stemmed thereunder, the proceeding shall be dismissed. If the
from the petition to compel arbitration filed by respondent Climax-Arimco finding be that a written provision for arbitration was
before the RTC of Makati City on 31 March 2000 while the complaint for the made and there is a default in proceeding thereunder,
nullification of the Addendum Contract was pending before the DENR Panel an order shall be made summarily directing the
of Arbitrators. On 23 March 2000, Climax-Arimco had sent Gonzales a parties to proceed with the arbitration in accordance
Demand for Arbitration pursuant to Clause 19.1[11] of the Addendum Contract with the terms thereof.
and also in accordance with Sec. 5 of R.A. No. 876. The petition for  
arbitration was subsequently filed and Climax-Arimco sought an order to The court shall decide all motions,
compel the parties to arbitrate pursuant to the said arbitration clause. The case, petitions or applications filed under the provisions of
docketed as Civil Case No. 00-444, was initially raffled to Br. 132 of the RTC this Act, within ten (10) days after such motions,
of Makati City, with Judge Herminio I. Benito as Presiding petitions, or applications have been heard by it.
Judge. Respondent Climax-Arimco filed on 5 April 2000 a motion to set the  
application to compel arbitration for hearing.  
  Gonzales also cites Sec. 24 of R.A. No. 9285 or the Alternative
  Dispute Resolution Act of 2004:
   
On 14 April 2000, Gonzales filed a motion to dismiss which he however SEC. 24. Referral to Arbitration.A court
failed to set for hearing. On 15 May 2000, he filed an Answer with before which an action is brought in a matter which is
Counterclaim,[12] questioning the validity of the Addendum Contract the subject matter of an arbitration agreement shall, if
containing the arbitration clause. Gonzales alleged that the Addendum at least one party so requests not later than the pre-
Contract containing the arbitration clause is void in view of Climax-Arimcos trial conference, or upon the request of both parties

6
thereafter, refer the parties to arbitration unless it  
finds that the arbitration agreement is null and void, xxxx
inoperative or incapable of being performed.  
   
  The grounds Gonzales invokes for the revocation of the Addendum
According to Gonzales, the above-quoted provisions of law outline the Contractfraud and oppression in the execution thereofare also not grounds for
procedure to be followed in petitions to compel arbitration, which the RTC the revocation of the arbitration clause in the Contract, Climax-Arimco
did not follow. Thus, referral of the parties to arbitration by Judge Pimentel notes. Such grounds may only be raised by way of defense in the arbitration
despite the timely and properly raised issue of nullity of the Addendum itself and cannot be used to frustrate or delay the conduct of arbitration
Contract was misplaced and without legal basis. Both R.A. No. 876 and R.A. proceedings. Instead, these should be raised in a separate action for rescission,
No. 9285 mandate that any issue as to the nullity, inoperativeness, or it continues.
incapability of performance of the arbitration clause/agreement raised by one  
of the parties to the alleged arbitration agreement must be determined by the Climax-Arimco emphasizes that the summary proceeding to compel
court prior to referring them to arbitration. They require that the trial court arbitration under Sec. 6 of R.A. No. 876 should not be confused with the
first determine or resolve the issue of nullity, and there is no other venue for procedure in Sec. 24 of R.A. No. 9285. Sec. 6 of R.A. No. 876 refers to an
this determination other than a pre-trial and hearing on the issue by the trial application to compel arbitration where the courts authority is limited to
court which has jurisdiction over the case. Gonzales adds that the assailed 13 resolving the issue of whether there is or there is no agreement in writing
February 2001 Order also violated his right to procedural due process when providing for arbitration, while Sec. 24 of R.A. No. 9285 refers to an ordinary
the trial court erroneously ruled on the existence of the arbitration agreement action which covers a matter that appears to be arbitrable or subject to
despite the absence of a hearing for the presentation of evidence on the nullity arbitration under the arbitration agreement. In the latter case, the statute is
of the Addendum Contract. clear that the court, instead of trying the case, may, on request of either or
  both parties, refer the parties to arbitration, unless it finds that the arbitration
Respondent Climax-Arimco, on the other hand, assails the mode of review agreement is null and void, inoperative or incapable of being
availed of by Gonzales. Climax-Arimco cites Sec. 29 of R.A. No. 876: performed. Arbitration may even be ordered in the same suit brought upon a
  matter covered by an arbitration agreement even without waiting for the
SEC. 29. Appeals.An appeal may be taken from an outcome of the issue of the validity of the arbitration agreement. Art. 8 of the
order made in a proceeding under this Act, or from a UNCITRAL Model Law[24]states that where a court before which an action is
judgment entered upon an award through certiorari brought in a matter which is subject of an arbitration agreement refers the
proceedings, but such appeals shall be limited to parties to arbitration, the arbitral proceedings may proceed even while the
questions of law. The proceedings upon such an action is pending.
appeal, including the judgment thereon shall be  
governed by the Rules of Court in so far as they are Thus, the main issue raised in the Petition for Certiorari is whether it was
applicable. proper for the RTC, in the proceeding to compel arbitration under R.A. No.
  876, to order the parties to arbitrate even though the defendant therein has
  raised the twin issues of validity and nullity of the Addendum Contract and,
Climax-Arimco mentions that the special civil action for certiorari employed consequently, of the arbitration clause therein as well.The resolution of both
by Gonzales is available only where there is no appeal or any plain, speedy, Climax-Arimcos Motion for Partial Reconsideration and/or Clarification in
and adequate remedy in the ordinary course of law against the challenged G.R. No. 161957 and Gonzaless Petition for Certiorari in G.R. No. 167994
orders or acts. Climax-Arimco then points out that R.A. No. 876 provides for essentially turns on whether the question of validity of the Addendum
an appeal from such orders, which, under the Rules of Court, must be filed Contract bears upon the applicability or enforceability of the arbitration clause
within 15 days from notice of the final order or resolution appealed from or of contained therein. The two pending matters shall thus be jointly resolved.
the denial of the motion for reconsideration filed in due time.Gonzales has not  
denied that the relevant 15-day period for an appeal had elapsed long before We address the Rule 65 petition in G.R. No. 167994 first from the
he filed this petition for certiorari. He cannot use the special civil action of remedial law perspective. It deserves to be dismissed on procedural grounds,
certiorari as a remedy for a lost appeal. as it was filed in lieu of appeal which is the prescribed remedy and at that far
  beyond the reglementary period. It is elementary in remedial law that the use
Climax-Arimco adds that an application to compel arbitration under Sec. 6 of of an erroneous mode of appeal is cause for dismissal of the petition for
R.A. No. 876 confers on the trial court only a limited and special certiorari and it has been repeatedly stressed that a petition for certiorari is not
jurisdiction, i.e., a jurisdiction solely to determine (a) whether or not the a substitute for a lost appeal. As its nature, a petition for certiorari lies only
parties have a written contract to arbitrate, and (b) if the defendant has failed where there is no appeal, and no plain, speedy and adequate remedy in the
to comply with that contract. Respondent cites La Naval Drug Corporation v. ordinary course of law.[25] The Arbitration Law specifically provides for an
Court of Appeals,[22] which holds that in a proceeding to compel arbitration, appeal by certiorari, i.e., a petition for review under certiorari under Rule 45
[t]he arbitration law explicitly confines the courts authority only to pass upon of the Rules of Court that raises pure questions of law. [26] There is no merit to
the issue of whether there is or there is no agreement in writing providing for Gonzaless argument that the use of the permissive term may in Sec. 29, R.A.
arbitration, and [i]n the affirmative, the statute ordains that the court shall No. 876 in the filing of appeals does not prohibit nor discount the filing of a
issue an order summarily directing the parties to proceed with the arbitration petition for certiorari under Rule 65.[27] Proper interpretation of the aforesaid
in accordance with the terms thereof. [23] Climax-Arimco argues that R.A. No. provision of law shows that the term may refers only to the filing of an appeal,
876 gives no room for any other issue to be dealt with in such a proceeding, not to the mode of review to be employed. Indeed, the use of may merely
and that the court presented with an application to compel arbitration may reiterates the principle that the right to appeal is not part of due process of law
order arbitration or dismiss the same, depending solely on its finding as to but is a mere statutory privilege to be exercised only in the manner and in
those two limited issues. If either of these matters is disputed, the court is accordance with law.
required to conduct a summary hearing on it. Gonzaless proposition  
contradicts both the trial courts limited jurisdiction and the summary nature of Neither can BF Corporation v. Court of Appeals[28] cited by
the proceeding itself. Gonzales support his theory. Gonzales argues that said case recognized and
  allowed a petition for certiorari under Rule 65 appealing the order of the
Climax-Arimco further notes that Gonzaless attack on or repudiation of the Regional Trial Court disregarding the arbitration agreement as an acceptable
Addendum Contract also is not a ground to deny effect to the arbitration remedy.[29] The BF Corporation case had its origins in a complaint for
clause in the Contract. The arbitration agreement is separate and severable collection of sum of money filed by therein petitioner BF Corporation against
from the contract evidencing the parties commercial or economic transaction, Shangri-la Properties, Inc. (SPI). SPI moved to suspend the proceedings
it stresses. Hence, the alleged defect or failure of the main contract is not a alleging that the construction agreement or the Articles of Agreement between
ground to deny enforcement of the parties arbitration agreement. Even the the parties contained a clause requiring prior resort to arbitration before
party who has repudiated the main contract is not prevented from enforcing its judicial intervention. The trial court found that an arbitration clause was
arbitration provision. R.A. No. 876 itself treats the arbitration clause or incorporated in the Conditions of Contract appended to and deemed an
agreement as a contract separate from the commercial, economic or other integral part of the Articles of Agreement. Still, the trial court denied the
transaction to be arbitrated. The statute, in particular paragraph 1 of Sec. 2 motion to suspend proceedings upon a finding that the Conditions of Contract
thereof, considers the arbitration stipulation an independent contract in its own were not duly executed and signed by the parties. The trial court also found
right whose enforcement may be prevented only on grounds which legally that SPI had failed to file any written notice of demand for arbitration within
make the arbitration agreement itself revocable, thus: the period specified in the arbitration clause. The trial court denied SPI's
  motion for reconsideration and ordered it to file its responsive
SEC. 2. Persons and matters subject to pleading. Instead of filing an answer, SPI filed a petition for certiorari under
arbitration.Two or more persons or parties may Rule 65, which the Court of Appeals, favorably acted upon. In a petition for
submit to the arbitration of one or more arbitrators review before this Court, BF Corporation alleged, among others, that the
any controversy existing, between them at the time of Court of Appeals should have dismissed the petition for certiorari since the
the submission and which may be the subject of an order of the trial court denying the motion to suspend proceedings is a
action, or the parties to any contract may in such resolution of an incident on the merits and upon the continuation of the
contract agree to settle by arbitration a controversy proceedings, the trial court would eventually render a decision on the merits,
thereafter arising between them.Such submission or which decision could then be elevated to a higher court in an ordinary appeal.
[30]
contract shall be valid, enforceable and irrevocable,
save upon such grounds as exist at law for the  
revocation of any contract.

7
The Court did not uphold BF Corporations argument. The issue SEC. 6. Hearing by court.A party
raised before the Court was whether SPI had taken the proper mode of appeal aggrieved by the failure, neglect or refusal of another
before the Court of Appeals.The question before the Court of Appeals was to perform under an agreement in writing providing
whether the trial court had prematurely assumed jurisdiction over the for arbitration may petition the court for an order
controversy. The question of jurisdiction in turn depended on the question of directing that such arbitration proceed in the manner
existence of the arbitration clause which is one of fact. While on its face the provided for in such agreement. Five days notice in
question of existence of the arbitration clause is a question of fact that is not writing of the hearing of such application shall be
proper in a petition for certiorari, yet since the determination of the question served either personally or by registered mail upon
obliged the Court of Appeals as it did to interpret the contract documents in the party in default. The court shall hear the parties,
accordance with R.A. No. 876 and existing jurisprudence, the question is and upon being satisfied that the making of the
likewise a question of law which may be properly taken cognizance of in a agreement or such failure to comply therewith is
petition for certiorari under Rule 65, so the Court held.[31] not in issue, shall make an order directing the parties
  to proceed to arbitration in accordance with the terms
The situation in B.F. Corporation  is not availing in the present of the agreement. If the making of the agreement or
petition. The disquisition in B.F. Corporation led to the conclusion that in default be in issue the court shall proceed to
order that the question of jurisdiction may be resolved, the appellate court had summarily hear such issue. If the finding be that
to deal first with a question of law which could be addressed in a certiorari no agreement in writing providing for
proceeding. In the present case, Gonzaless petition raises a question of law, arbitration was made, or that there is no default in
but not a question of jurisdiction. Judge Pimentel acted in accordance with the the proceeding thereunder, the proceeding shall be
procedure prescribed in R.A. No. 876 when he ordered Gonzales to proceed dismissed. If the finding be that a written provision
with arbitration and appointed a sole arbitrator after making the determination for arbitration was made and there is a default in
that there was indeed an arbitration agreement. It has been held that as long as proceeding thereunder, an order shall be made
a court acts within its jurisdiction and does not gravely abuse its discretion in summarily directing the parties to proceed with the
the exercise thereof, any supposed error committed by it will amount to arbitration in accordance with the terms thereof.
nothing more than an error of judgment reviewable by a timely appeal and not  
assailable by a special civil action of certiorari.[32] Even if we overlook the The court shall decide all motions,
employment of the wrong remedy in the broader interests of justice, the petitions or applications filed under the provisions of
petition would nevertheless be dismissed for failure of Gonzalez to show this Act, within ten days after such motions, petitions,
grave abuse of discretion. or applications have been heard by it.[Emphasis
  added.]
Arbitration, as an alternative mode of settling disputes, has long been  
recognized and accepted in our jurisdiction. The Civil Code is explicit on the  
matter.[33] R.A. No. 876 also expressly authorizes arbitration of domestic This special proceeding is the procedural mechanism for the enforcement of
disputes. Foreign arbitration, as a system of settling commercial disputes of an the contract to arbitrate. The jurisdiction of the courts in relation to Sec. 6 of
international character, was likewise recognized when the Philippines adhered R.A. No. 876 as well as the nature of the proceedings therein was expounded
to the United Nations "Convention on the Recognition and the Enforcement of upon in La Naval Drug Corporation v. Court of Appeals.[39] There it was held
Foreign Arbitral Awards of 1958," under the 10 May 1965 Resolution No. 71 that R.A. No. 876 explicitly confines the court's authority only to the
of the Philippine Senate, giving reciprocal recognition and allowing determination of whether or not there is an agreement in writing providing for
enforcement of international arbitration agreements between parties of arbitration. In the affirmative, the statute ordains that the court shall issue an
different nationalities within a contracting state. [34] The enactment of R.A. No. order "summarily directing the parties to proceed with the arbitration in
9285 on 2 April 2004 further institutionalized the use of alternative dispute accordance with the terms thereof." If the court, upon the other hand, finds
resolution systems, including arbitration, in the settlement of disputes. that no such agreement exists, "the proceeding shall be dismissed." [40] The
  cited case also stressed that the proceedings are summary in nature. [41] The
Disputes do not go to arbitration unless and until the parties have agreed to same thrust was made in the earlier case of Mindanao Portland Cement Corp.
abide by the arbitrators decision. Necessarily, a contract is required for v. McDonough Construction Co. of Florida[42] which held, thus:
arbitration to take place and to be binding. R.A. No. 876 recognizes the  
contractual nature of the arbitration agreement, thus:  
  Since there obtains herein a written
SEC. 2. Persons and matters subject to provision for arbitration as well as failure on
arbitration.Two or more persons or parties respondent's part to comply therewith, the court a
may submit to the arbitration of one or more quo rightly ordered the parties to proceed to
arbitrators any controversy existing, between arbitration in accordance with the terms of their
them at the time of the submission and which may be agreement (Sec. 6, Republic Act 876). Respondent's
the subject of an action, or the parties to any contract arguments touching upon the merits of the dispute are
may in such contract agree to settle by arbitration a improperly raised herein. They should be addressed
controversy thereafter arising between them. Such to the arbitrators. This proceeding is merely a
submission or contract shall be valid, enforceable summary remedy to enforce the agreement to
and irrevocable, save upon such grounds as exist arbitrate. The duty of the court in this case is not to
at law for the revocation of any contract. resolve the merits of the parties' claims but only to
  determine if they should proceed to arbitration or not.
Such submission or contract may include question x x x x[43]
arising out of valuations, appraisals or other  
controversies which may be collateral, incidental,  
precedent or subsequent to any issue between the Implicit in the summary nature of the judicial proceedings is the
parties. separable or independent character of the arbitration clause or agreement. This
  was highlighted in the cases of Manila Electric Co. v. Pasay Trans. Co.
[44]
   and Del Monte Corporation-USA v. Court of Appeals.[45]
A controversy cannot be arbitrated where one of the  
parties to the controversy is an infant, or a person The doctrine of separability, or severability as other writers call
judicially declared to be incompetent, unless the it, enunciates that an arbitration agreement is independent of the main
appropriate court having jurisdiction approve a contract. The arbitration agreement is to be treated as a separate agreement
petition for permission to submit such controversy to and the arbitration agreement does not automatically terminate when the
arbitration made by the general guardian or contract of which it is part comes to an end.[46]
guardian ad litem of the infant or of the  
incompetent. [Emphasis added.]  
  The separability of the arbitration agreement is especially
  significant to the determination of whether the invalidity of the main contract
Thus, we held in Manila Electric Co. v. Pasay Transportation Co. also nullifies the arbitration clause.Indeed, the doctrine denotes that the
[35]
 that a submission to arbitration is a contract. A clause in a contract invalidity of the main contract, also referred to as the container contract,
providing that all matters in dispute between the parties shall be referred to does not affect the validity of the arbitration agreement. Irrespective of the
arbitration is a contract,[36] and in Del Monte Corporation-USA v. Court of fact that the main contract is invalid, the arbitration clause/agreement still
Appeals[37] that [t]he provision to submit to arbitration any dispute arising remains valid and enforceable.[47]
therefrom and the relationship of the parties is part of that contract and is itself  
a contract. As a rule, contracts are respected as the law between the The separability of the arbitration clause is confirmed in Art. 16(1)
contracting parties and produce effect as between them, their assigns and of the UNCITRAL Model Law and Art. 21(2) of the UNCITRAL Arbitration
heirs.[38] Rules.[48]
   
The special proceeding under Sec. 6 of R.A. No. 876 recognizes The separability doctrine was dwelt upon at length in the U.S. case
the contractual nature of arbitration clauses or agreements. It provides: of Prima Paint Corp. v. Flood & Conklin Manufacturing Co. [49] In that case,
  Prima Paint and Flood and Conklin (F & C) entered into a consulting

8
agreement whereby F & C undertook to act as consultant to Prima Paint for The question of whether Gonzales had ceded his claims over the
six years, sold to Prima Paint a list of its customers and promised not to sell mineral deposits in the Addendum Area of Influence is a factual question
paint to these customers during the same period. The consulting agreement which is not proper for determination before this Court. At all events,
contained an arbitration clause. Prima Paint did not make payments as moreover, the question is irrelevant to the issue of jurisdiction of the DENR
provided in the consulting agreement, contending that F & C had fraudulently Panel of Arbitrators. It should be pointed out that the DENR Panel of
misrepresented that it was solvent and able for perform its contract when in Arbitrators made a factual finding in its Order dated 18 October 2001, which
fact it was not and had even intended to file for bankruptcy after executing the it reiterated in its Order dated 25 June 2002, that Gonzales had, through the
consultancy agreement. Thus, F & C served Prima Paint with a notice of various agreements, assigned his interest over the mineral claims all in favor
intention to arbitrate. Prima Paint sued in court for rescission of the consulting of [Climax-Arimco] as well as that without the complainant [Gonzales]
agreement on the ground of fraudulent misrepresentation and asked for the assigning his interest over the mineral claims in favor of [Climax-Arimco],
issuance of an order enjoining F & C from proceeding with arbitration. F & C there would be no FTAA to speak of. [52] This finding was affirmed by the
moved to stay the suit pending arbitration. The trial court granted F & Cs Court of Appeals in its Decision dated 30 July 2003resolving the petition for
motion, and the U.S. Supreme Court affirmed. certiorari filed by Climax-Arimco in regard to the 18 October 2001 Order of
  the DENR Panel.[53]
The U.S. Supreme Court did not address Prima Paints argument  
that it had been fraudulently induced by F & C to sign the consulting The Court of Appeals likewise found that Gonzaless complaint
agreement and held that no court should address this argument. Relying on alleged fraud but did not provide any particulars to substantiate it. The
Sec. 4 of the Federal Arbitration Actwhich provides that if a party [claims to complaint repeatedly mentioned fraud, oppression, violation of the
be] aggrieved by the alleged failure x x x of another to arbitrate x x x, [t]he Constitution and similar conclusions but nowhere did it give any ultimate
court shall hear the parties, and upon being satisfied that the making of the facts or particulars relative to the allegations.[54]
agreement for arbitration or the failure to comply therewith is not in issue, the  
court shall make an order directing the parties to proceed to arbitration x x Sec. 5, Rule 8 of the Rules of Court specifically provides that in all
x. If the making of the arbitration agreement or the failure, neglect, or refusal averments of fraud, the circumstances constituting fraud must be stated with
to perform the same be in issue, the court shall proceed summarily to the trial particularity. This is to enable the opposing party to controvert the particular
thereofthe U.S. High Court held that the court should not order the parties to facts allegedly constituting the same. Perusal of the complaint indeed shows
arbitrate if the making of the arbitration agreement is in issue. The parties that it failed to state with particularity the ultimate facts and circumstances
should be ordered to arbitration if, and only if, they have contracted to submit constituting the alleged fraud. It does not state what particulars about Climax-
to arbitration. Prima Paint was not entitled to trial on the question of whether Arimcos financial or technical capability were misrepresented, or how the
an arbitration agreement was made because its allegations of fraudulent misrepresentation was done. Incorporated in the body of the complaint are
inducement were not directed to the arbitration clause itself, but only to the verbatim reproductions of the contracts, correspondence and government
consulting agreement which contained the arbitration agreement. [50] Prima issuances that reportedly explain the allegations of fraud and
Paint held that arbitration clauses are separable from the contracts in which misrepresentation, but these are, at best, evidentiary matters that should not be
they are embedded, and that where no claim is made that fraud was directed to included in the pleading.
the arbitration clause itself, a broad arbitration clause will be held to  
encompass arbitration of the claim that the contract itself was induced by As to the issue of prescription, Gonzaless claims of fraud and
fraud.[51] misrepresentation attending the execution of the Addendum Contract are
  grounds for the annulment of a voidable contract under the Civil Code.
[55]
There is reason, therefore, to rule against Gonzales when he alleges  Under Art. 1391 of the Code, an action for annulment shall be brought
that Judge Pimentel acted with grave abuse of discretion in ordering the within four years, in the case of fraud, beginning from the time of the
parties to proceed with arbitration. Gonzaless argument that the Addendum discovery of the same. However, the time of the discovery of the alleged fraud
Contract is null and void and, therefore the arbitration clause therein is void as is not clear from the allegations of Gonzaless complaint. That being the
well, is not tenable. First, the proceeding in a petition for arbitration under situation coupled with the fact that this Court is not a trier of facts, any ruling
R.A. No. 876 is limited only to the resolution of the question of whether the on the issue of prescription would be uncalled for or even unnecessary.
arbitration agreement exists. Second, the separability of the arbitration clause  
from the Addendum Contract means that validity or invalidity of the WHEREFORE, the Petition for Certiorari in G.R. No. 167994 is
Addendum Contract will not affect the enforceability of the agreement to DISMISSED. Such dismissal effectively renders superfluous formal action on
arbitrate. Thus, Gonzaless petition for certiorari should be dismissed. the Motion for Partial Reconsideration and/or Clarification filed by Climax
  Mining Ltd., et al. in G.R. No. 161957.
This brings us back to G.R. No. 161957. The adjudication of the  
petition in G.R. No. 167994 effectively modifies part of the Decision dated 28 The Motion for Reconsideration filed by Jorge Gonzales in G.R.
February 2005 in G.R. No. 161957. Hence, we now hold that the validity of No. 161957 is DENIED WITH FINALITY.
the contract containing the agreement to submit to arbitration does not affect  
the applicability of the arbitration clause itself. A contrary ruling would SO ORDERED.
suggest that a partys mere repudiation of the main contract is sufficient to
avoid arbitration. That is exactly the situation that the separability doctrine, as
well as jurisprudence applying it, seeks to avoid. We add that when it was
declared in G.R. No. 161957 that the case should not be brought for G.R. No. 87958               April 26, 1990
arbitration, it should be clarified that the case referred to is the case actually
filed by Gonzales before the DENR Panel of Arbitrators, which was for the NATIONAL UNION FIRE INSURANCE COMPANY OF PITTSBURG,
nullification of the main contract on the ground of fraud, as it had already PA/AMERICAN INTERNATIONAL UNDERWRITER (PHIL.)
been determined that the case should have been brought before the regular INC., petitioners, 
courts involving as it did judicial issues. vs.
  STOLT-NIELSEN PHILIPPINES, INC. and COURT OF
The Motion for Reconsideration of Gonzales in G.R. No. 161957 APPEALS, respondents.
should also be denied. In the motion, Gonzales raises the same question of
jurisdiction, more particularly that the complaint for nullification of the
Addendum Contract pertained to the DENR Panel of Arbitrators, not the Fajardo Law Offices for petitioners. 
regular courts. He insists that the subject of his complaint is a mining dispute Sycip, Salazar, Hernandez & Gatmaitan for Stolt-Nielsen Phil., Inc.
since it involves a dispute concerning rights to mining areas, the Financial and
Technical Assistance Agreement (FTAA) between the parties, and it also
involves claimowners. He adds that the Court failed to rule on other issues he
raised, such as whether he had ceded his claims over the mineral deposits
located within the Addendum Area of Influence; whether the complaint filed MELENCIO-HERRERA, J.:
before the DENR Panel of Arbitrators alleged ultimate facts of fraud; and
whether the action to declare the nullity of the Addendum Contract on the We uphold the ruling of respondent Court of Appeals that the claim or
ground of fraud has prescribed. dispute herein is arbitrable.
 
 
  On 9 January 1985, United Coconut Chemicals, Inc. (hereinafter
  referred to as SHIPPER) shipped 404.774 metric tons of distilled C6-
These are the same issues that Gonzales raised in his Rule 45 C18 fatty acid on board MT "Stolt Sceptre," a tanker owned by Stolt-
petition in G.R. No. 161957 which were resolved against him in the Decision Nielsen Philippines Inc. (hereinafter referred to as CARRIER), from
of 28 February 2005. Gonzales does not raise any new argument that would Bauan, Batangas, Philippines, consigned to "Nieuwe Matex" at
sway the Court even a bit to alter its holding that the complaint filed before Rotterdam, Netherlands, covered by Tanker Bill of Lading BL No. BAT-
the DENR Panel of Arbitrators involves judicial issues which should properly 1. The shipment was insured under a marine cargo policy with
be resolved by the regular courts. He alleged fraud or misrepresentation in the Petitioner National Union Fire Insurance Company of Pittsburg
execution of the Addendum Contract which is a ground for the annulment of a (hereinafter referred to as INSURER), a non-life American insurance
voidable contract. Clearly, such allegations entail legal questions which are corporation, through its settling agent in the Philippines, the American
within the jurisdiction of the courts. International Underwriters (Philippines), Inc., the other petitioner
  herein.

9
It appears that the Bill of Lading issued by the CARRIER contained a The pertinent portion of the Bill of Lading in issue provides in part:
general statement of incorporation of the terms of a Charter Party
between the SHIPPER and Parcel Tankers, Inc., entered into in
This shipment is carried under and pursuant to the terms of
Greenwich, Connecticut, U.S.A.
the Charter dated December 21st 1984 at Greenwich,
Connecticut, U.S.A. between Parcel Tankers. Inc. and
Upon receipt of the cargo by the CONSIGNEE in the Netherlands, it United Coconut Chemicals, Ind. as Charterer and all the
was found to be discolored and totally contaminated. The claim filed by terms whatsoever of the said Charter except the rate and
the SHIPPER-ASSURED with the CARRIER having been denied, the payment of freight specified therein apply to and govern the
INSURER indemnified the SHIPPER pursuant to the stipulation in the rights of the parties concerned in this shipment. Copy of the
marine cargo policy covering said shipment. Charter may be obtained from the Shipper or Charterer.
(Emphasis supplied)
On 21 April 1986, as subrogee of the SHIPPER-ASSURED, the
INSURER filed suit against the CARRIER, before the Regional Trial While the provision on arbitration in the Charter Party reads:
Court of Makati, Branch 58 (RTC), for recovery of the sum of
P1,619,469.21, with interest, representing the amount the INSURER
H. Special Provisions.
had paid the SHIPPER-ASSURED. The CARRIER moved to
dismiss/suspend the proceedings on the ground that the RTC had no
jurisdiction over the claim the same being an arbitrable one; that as x x x           x x x          x x x
subrogee of the SHIPPER-ASSURED, the INSURER is subject to the
provisions of the Bill of Lading, which includes a provision that the
4. Arbitration. Any dispute arising from the making,
shipment is carried under and pursuant to the terms of the Charter
performance or termination of this Charter Party shall be
Party, dated 21 December 1984, between the SHIPPER-ASSURED
settled in New York, Owner and Charterer each appointing
and Parcel Tankers, Inc. providing for arbitration.
an arbitrator, who shall be a merchant, broker or individual
experienced in the shipping business; the two thus chosen, if
The INSURER opposed the dismissal/suspension of the proceedings they cannot agree, shall nominate a third arbitrator who shall
on the ground that it was not legally bound to submit the claim for be an admiralty lawyer. Such arbitration shall be conducted
arbitration inasmuch as the arbitration clause provided in the Charter in conformity with the provisions and procedure of the United
Party was not incorporated into the Bill of Lading, and that the States arbitration act, and a judgment of the court shall be
arbitration clause is void for being unreasonable and unjust. On 28 July entered upon any award made by said arbitrator. Nothing in
1987, the RTC 1 denied the Motion, but subsequently reconsidered its this clause shall be deemed to waive Owner's right to lien on
action on 19 November 1987, and deferred resolution on the Motion to the cargo for freight, deed of freight, or demurrage.
Dismiss/Suspend Proceedings until trial on the merits "since the
ground alleged in said motion does not appear to be indubitable."
Clearly, the Bill of Lading incorporates by reference the terms of the
Charter Party. It is settled law that the charter may be made part of the
The CARRIER then resorted to a Petition for Certiorari and Prohibition contract under which the goods are carried by an appropriate
with prayer for Preliminary Injunction and/or Temporary Restraining reference in the Bill of Lading (Wharton Poor, Charter Parties and
Order before the respondent Appellate Court seeking the annulment of Ocean Bills of Lading (5th ed., p. 71). This should include the provision
the 19 November 1987 RTC Order. On 12 April 1989, the respondent on arbitration even without a specific stipulation to that effect. The
Court 2 promulgated the Decision now under review, with the following entire contract must be read together and its clauses interpreted in
dispositive tenor: relation to one another and not by parts. Moreover, in cases where a
Bill of Lading has been issued by a carrier covering goods shipped
aboard a vessel under a charter party, and the charterer is also the
WHEREFORE', the order of respondent Judge dated
holder of the bill of lading, "the bill of lading operates as the receipt for
November 19, 1987 deferring resolution on petitioner Stolt-
the goods, and as document of title passing the property of the goods,
Nielsen's Motion to Dismiss/Suspend Proceedings is hereby
but not as varying the contract between the charterer and the
SET ASIDE; private respondent NUFIC (the INSURER) is
shipowner" (In re Marine Sulphur Queen, 460 F 2d 89, 103 [2d Cir.
ordered to refer its claims for arbitration; and respondent
1972]; Ministry of Commerce vs. Marine Tankers Corp. 194 F. Supp
Judge is directed to suspend the proceedings in Civil case
161, 163 [S.D.N.Y. 1960]; Greenstone Shipping Co., S.A. vs.
No. 13498 pending the return of the corresponding arbitral
Transworld Oil, Ltd., 588 F Supp [D.El. 1984]). The Bill of Lading
award.
becomes, therefore, only a receipt and not the contract of carriage in a
charter of the entire vessel, for the contract is the Charter Party (Shell
On 21 August 1989, we resolved to give due course and required the Oil Co. vs. M/T Gilda, 790 F 2d 1209, 1212 [5th Cir. 1986]; Home
parties to submit their respective Memoranda, which they have done, Insurance Co. vs. American Steamship Agencies, Inc., G.R. No. L-
the last filed having been Noted on 23 October 1989. 25599, 4 April 1968, 23 SCRA 24), and is the law between the parties
who are bound by its terms and condition provided that these are not
contrary to law, morals, good customs, public order and public policy
First, herein petitioner-INSURER alleges that the RTC Order deferring
(Article 1306, Civil Code).
resolution of the CARRIER's Motion to Dismiss constitutes an
interlocutory order, which can not be the subject of a special civil action
on certiorari and prohibition. As the respondent Appellate Court found, the INSURER "cannot feign
ignorance of the arbitration clause since it was already charged with
notice of the existence of the charter party due to an appropriate
Generally, this would be true. However, the case before us falls under
reference thereof in the bill of lading and, by the exercise of ordinary
the exception. While a Court Order deferring action on a motion to
diligence, it could have easily obtained a copy thereof either from the
dismiss until the trial is interlocutory and cannot be challenged until
shipper or the charterer.
final judgment, still, where it clearly appears that the trial Judge or
Court is proceeding in excess or outside of its jurisdiction, the remedy
of prohibition would lie since it would be useless and a waste of time to We hold, therefore, that the INSURER cannot avoid the binding effect
go ahead with the proceedings (University of Sto. Tomas vs. of the arbitration clause. By subrogation, it became privy to the Charter
Villanueva, 106 Phil. 439, [1959] citing Philippine International Fair, Party as fully as the SHIPPER before the latter was indemnified,
Inc., et al., vs. Ibanez, et al., 94 Phil. 424 [1954]; Enrique vs. because as subrogee it stepped into the shoes of the SHIPPER-
Macadaeg, et al., 84 Phil. 674 [1949]; San Beda College vs. CIR, 97 ASSURED and is subrogated merely to the latter's rights. It can
Phil. 787 [1955]). Even a cursory reading of the subject Bill of Lading, recover only the amount that is recoverable by the assured. And since
in relation to the Charter Party, reveals the Court's patent lack of the right of action of the SHIPPER-ASSURED is governed by the
jurisdiction to hear and decide the claim. provisions of the Bill of Lading, which includes by reference the terms
of the Charter Party, necessarily, a suit by the INSURER is subject to
the same agreements (see St. Paul Fire and Marine Insurance Co. vs.
We proceed to the second but more crucial issue: Are the terms of the
Macondray, G.R. No. L-27796, 25 March 1976, 70 SCRA 122).
Charter Party, particularly the provision on arbitration, binding on the
INSURER?
Stated otherwise, as the subrogee of the SHIPPER, the INSURER is
contractually bound by the terms of the Charter party.1âwphi1 Any
The INSURER postulates that it cannot be bound by the Charter Party
claim of inconvenience or additional expense on its part should not
because, as insurer, it is subrogee only with respect to the Bill of
render the arbitration clause unenforceable.
Lading; that only the Bill of Lading should regulate the relation among
the INSURER, the holder of the Bill of Lading, and the CARRIER; and
that in order to bind it, the arbitral clause in the Charter Party should Arbitration, as an alternative mode of settling disputes, has long been
have been incorporated into the Bill of Lading. recognized and accepted in our jurisdiction (Chapter 2, Title XIV, Book
IV, Civil Code). Republic Act No. 876 (The Arbitration Law) also
expressly authorizes arbitration of domestic disputes. Foreign
We rule against that submission.
10
arbitration as a system of settling commercial disputes of an the general owner in possession of the ship as owner for the voyage,
international character was likewise recognized when the Philippines the rights, responsibilities of ownership rest on the owner and the
adhered to the United Nations "Convention on the Recognition and the charterer is usually free from liability to third persons in respect of the
Enforcement of Foreign Arbitral Awards of 1958," under the 10 May ship.
1965 Resolution No. 71 of the Philippine Senate, giving reciprocal
recognition and allowing enforcement of international arbitration
5. ID.; ID.; ID.; ID.; LIABILITY TO THIRD PERSONS FOR GOODS
agreements between parties of different nationalities within a
SHIPPED ON BOARD A VESSEL. — Responsibility to third persons
contracting state. Thus, it pertinently provides:
for goods shipped on board a vessel follows the vessel's possession
and employment; and if possession is transferred to the charterer by
1. Each Contracting State shall recognize an agreement in virtue of a demise, the charterer, and not the owner, is liable as carrier
writing under which the parties undertake to submit to on the contract of affreightment made by himself or by the master with
arbitration all or any differences which have arisen or which third persons, and is answerable for loss, damage or non-delivery of
may arise between them in respect of a defined legal goods received for transportation. An owner who retains possession of
relationship, whether contractual or not, concerning a subject the ship, though the hold is the property of the charterer, remains liable
matter capable of settlement by arbitration. as carrier and must answer for any breach of duty as to the care,
loading or unloading of the cargo.
2. The term "agreement in writing" shall include an arbitral
clause in a contract or an arbitration agreement, signed by 6. ID.; ID.; ID.; ID.; BILLS OF LADING; ARBITRATION PROVISION
the parties or contained in an exchange of letters or THEREOF, CONSIDERED AND RESPECTED. — Whether the liability
telegrams. of respondent should be based on the same contract or that of the bill
of lading, the parties are nevertheless obligated to respect the
arbitration provisions on the sales contract and/or the bill of lading.
3. The court of a Contracting State, when seized of an action
Petitioner being a signatory and party to the sales contract cannot
in a matter in respect of which the parties have made an
escape from his obligation under the arbitration clause as stated
agreement within the meaning of this article, shall, at the
therein. Arbitration has been held valid and constitutional. Even before
request of one of the parties, refer the parties to arbitration,
the enactment of Republic Act No. 876, this Court has countenanced
unless it finds that the said agreement is null and void,
the settlement of disputes through arbitration. The rule now is that
inoperative or incapable of being performed.
unless the agreement is such as absolutely to close the doors of the
courts against the parties, which agreement would be void, the courts
It has not been shown that the arbitral clause in question is null and will look with favor upon such amicable arrangements and will only
void, inoperative, or incapable of being performed. Nor has any conflict interfere with great reluctance to anticipate or nullify the action of the
been pointed out between the Charter Party and the Bill of Lading. arbitrator. As pointed out in the case of Mindanao Portland Cement
Corp. v. McDough Construction Company of Florida 18 wherein the
plaintiff sued defendant for damages arising from a contract, the Court
In fine, referral to arbitration in New York pursuant to the arbitration said: "Since there obtains herein a written provision for arbitration as
clause, and suspension of the proceedings in Civil Case No. 13498 well as failure on respondent's part to comply therewith, the court a
below, pending the return of the arbitral award, is, indeed called for. quo rightly ordered the parties to proceed to their arbitration in
accordance with the terms of their agreement (Sec. 6 Republic Act
WHEREFORE, finding no reversible error in respondent Appellate 876). Respondent's arguments touching upon the merits of the dispute
Court's 12 April 1989 Decision, the instant Petition for Review are improperly raised herein. They should be addressed to the
on certiorari is DENIED and the said judgment is hereby AFFIRMED. arbitrators. This proceeding is merely a summary remedy to enforce
Costs against petitioners. the agreement to arbitrate. The duty of the court in this case is not to
resolve the merits of the parties' claims but only to determine if they
should proceed to arbitration or not. And although it has been ruled
SO ORDERED. that a privolous or patently baseless claim should not be ordered to
arbitration it is also recognized that the mere fact that a defense exist
G.R. No. 91228. March 22, 1993. against a claim does not make it frivolous or baseless."

PUROMINES, INC., petitioner, vs. COURT OF APPEAL and PHILIPP 7. REMEDIAL LAW; CIVIL PROCEDURE; PLEADINGS; COMPLAINT;
BROTHERS OCEANIC, INC., respondents. ANNEXES ATTACHED THEREOF, PART OF THE RECORD. —
Petitioner contend that the arbitration provision in the bills of lading
should not have been discussed as an issue in the decision of the
SYLLABUS Court of Appeals since it was not raised as a special or affirmative
defense. The three bills of lading were attached to the complaint as
1. CIVIL LAW; OBLIGATIONS OF VENDOR; DAMAGES ARISING Annexes "A," "B," and "C," and are therefore parts thereof and may be
FROM CARRIAGE AND DELIVERY. — We agree with the court a quo considered as evidence although not introduced as such. Hence, it
that the sales contract is comprehensive enough to include claims for was then proper for the court a quo to discuss the contents of the bills
damages arising from carriage and delivery of the goods. As a general of lading, having been made part of the record.
rule, the seller has the obligation to transmit the goods to the buyer,
and concomitant thereto, the contracting of a carrier to deliver the DECISION
same.

NOCON, J p:
2. COMMERCIAL LAW; MARITIME TRANSPORTATION; MARITIME
COMMERCE; CHARTER PARTIES, CONSTRUED. — American
jurisprudence defines charter party as a contract by which an entire This is a special civil action for certiorari and prohibition to annul and
ship or some principal part thereof is let by the owner to another set aside the Decision of the respondent Court of Appeals dated
person for a specified time or use. Charter or charter parties are of two November 16, 1989 1 reversing the order of the trial court and
kinds. Charter of demise or bareboat and contracts of affreightment. dismissing petitioner's compliant in Civil Case No. 89-47403, entitled
Puromines, Inc. v. Maritime Factors, Inc. and Philipp Brothers Oceanic,
Inc.
3. ID.; ID.; ID.; ID.; KINDS; CHARTER OF DEMISE, CONSTRUED. —
Under the demise or bareboat charter of the vessel, the charterer will
generally be considered as owner for the voyage or service stipulated. Culled from the records of this case, the facts show that petitioner,
The charterer mans the vessel with his own people and becomes, in Puromines, Inc. (Puromines for brevity) and Makati Agro Trading, Inc.
effect, the owner pro hac vice, subject to liability to others for damages (not a party in this case) entered into a contract with private
caused by negligence. To create a demise the owner of a vessel must respondents Philipp Brothers Oceanic, Inc. for the sale of prilled Urea
completely and exclusively relinquish possession, anything short of in bulk. The Sales Contract No. S151.8.01018 provided, among others
such a complete transfer is a contract of affreightment (time or voyage an arbitration clause which states, thus:
charter party) or not a charter party at all.
"9. Arbitration
4. ID.; ID.; ID.; ID.; ID.; CONTRACT OF AFFREIGNMENT,
CONSTRUED. — A contract of affreightment is in which the owner of "Any disputes arising under this contract shall be settled by arbitration
the vessel leases part or all of its space to haul goods for others. It is a in London in accordance with the Arbitration Act 1950 and any
contract for a special service to be rendered by the owner of the vessel statutory amendment or modification thereof. Each party is to appoint
and under such contract the general owner retains the possession, an Arbitrator, and should they be unable to agree, the decision of an
command and navigation of the ship, the charterer or freighter merely Umpire appointed by them to be final. The Arbitrators and Umpire are
having use of the space in the vessel in return for his payment of the all to be commercial men and resident in London. This submission may
charter hire. If the charter is a contract of affreightment, which leaves

11
be made a rule of the High Court of Justice in England by either party." Petitioner states in its complainants that Philipp Brothers "was the
2 charterer of the vessel MV 'Liliana Dimitrova' which transported the
shipment from Yuzhny USSR to Manila." Petitioner further alleged that
the caking and hardening, wetting and melting, and contamination by
On or about May 22, 1988, the vessel M/V "Liliana Dimitrova" loaded
rust and dirt of the damaged portions of the shipment were due to the
on board at Yuzhny, USSR a shipment of 15,500 metric tons prilled
improper ventilation and inadequate storage facilities of the vessel; that
Urea in bulk complete and in good order and condition for transport to
the wetting of the cargo was attributable to the failure of the crew to
Iloilo and Manila, to be delivered to petitioner. Three bills of lading
close the hatches before and when it rained while the shipment was
were issued by the ship-agent in the Philippines, Maritime Factors Inc.,
being unloaded in the Port of Manila; and that as a direct and natural
namely: Bill of Lading No. dated May 12, 1988 covering 10,000 metric
consequence of the unseaworthiness and negligence of the vessel
tons for discharge Manila; Bill of Lading No. 2 of even date covering
(sic), petitioner suffered damages in the total amount of P683, 056.29
4,000 metric tons for unloading in Iloilo City; and Bill of Lading No. 3,
Philippine currency." 8 (Emphasis supplied)
also dated May 12, 1988, covering 1,500 metric tons likewise for
discharged in Manila
Moreover, in its Opposition to the Motion to Dismiss, petitioner said
that "[t]he cause of action of the complaint arose from breach of
The shipment covered by Bill of Lading No. 2 was discharged in Iloilo
contract of carriage by the vessel that was chartered by defendant
City complete and in good order and condition. However, the
Philipp Brothers." 9
shipments covered by Bill of Lading Nos. 1 and 3 were discharged in
Manila in bad order and condition, caked, hardened and lumpy,
discolored and contaminated with rust and dirt. Damages were valued In the present petition, petitioner argues that the sales contract does
at P683, 056. 29 including additional discharging expenses. not include the contract of carriage which is a different contract entered
into by the carrier with the cargo owners. That it was an error for the
respondent court to touch upon the arbitration provision of the bills
Consequently, petitioner filed a complaint 3 with the trial court 4 for
lading in its decision inasmuch as the same was not raised as an issue
breach of contract of carriage against Maritime Factors Inc. (which was
by private respondent who was not a party in the bills of lading
not included as respondent in this petition) as ship-agent in the
(emphasis Ours). Petitioner contradicts itself.
Philippines for the owners of the vessel MV "Liliana Dimitrova," while
private respondent, Philipp Brothers Oceanic Inc., was impleaded as
charterer of the said vessel and proper party to accord petitioner We agree with the court a quo that the sales contract is comprehensive
complete relief. Maritime Factors, Inc. filed its Answer 5 to the enough to include claims for damages arising from carriage and
complaint, while private respondent filed a motion to dismiss, dated delivery of the goods. As a general rule, the seller has the obligation to
February 9, 1989, on the grounds that the complaint states no cause of transmit the goods to the buyer, and concomitant thereto, the
action; that it was prematurely filed; and that petitioner should comply contracting of a carrier to deliver the same. Art. 1523 of the Civil Code
with the arbitration clause in the sales contract. 6 provides:

The motion to dismiss was opposed by petitioner contending the "Art. 1523. Where in pursuance of a contract of sale, the seller in
inapplicability of the arbitration clause inasmuch as the cause of action authorized or required to send the goods to the buyer, delivery of the
did not arise from a violation of the terms of the sales contract but goods to a carrier, whether named by the buyer or not, for the purpose
rather for claims of cargo damages where there is no arbitration of transmission to the buyer is deemed to be a delivery of the goods to
agreement. On April 26, 1989, the trial court denied respondent's the buyer, except in the cases provided for in article 1503, first, second
motion to dismiss in this wise: and third paragraphs, or unless a contrary intent appear.

"The sales contract in question states in part: "Unless otherwise authorized by the buyer, the seller must take such
contract with the carrier on behalf of the buyer as may be reasonable,
having regard to the nature of the goods and the other circumstances
'Any disputes arising under this contract shall be settled by
of the case. If the seller omit so to do, and the goods are lost or
arbitration . . .(emphasis supplied)
damaged in course of transit, the buyer may decline to treat the
delivery to the carrier as a delivery to himself,, or may hold the seller
"A perusal of the facts alleged in the complaint upon which the responsible in damages."
question of sufficiency of the cause of action of the complaint arose
from a breach of contract of carriage by the vessel chartered by the
xxx xxx xxx
defendant Philipp Brothers Oceanic, Inc. Thus, the aforementioned
arbitration clause cannot apply to the dispute in the present action
which concerns plaintiff's claim for cargo loss/damage arising from The disputed sales contact provides for conditions relative to the
breach of contract of carriage. delivery of goods, such as date of shipment, demurrage, weight as
determined by the bill of lading at load port and more particularly the
following provisions:
"That the defendant is not the ship owner or common carrier and
therefore plaintiff does not have legal right against it since every action
must be brought against the real party in interest has no merit either for "3. Intention is to ship in one bottom, approximately 5,000 metrics tons
by the allegations in the complaint the defendant herein has been to Puromines and approximately 15,000 metric tons to Makati Agro.
impleaded as charterer of the vessel, hence, a proper party." 7 However, Sellers to have right to ship material as partial shipment or
co-shipment in addition to above. In the event of co-shipment to a third
party within Philippines same to be discussed with and acceptable to
Elevating the matter to the Court of Appeals, petitioner's complaint was
both Puromines and Makati Agro.
dismissed. The appellate court found that the arbitration provision in
the sales contract and/or the bills of lading is applicable in the present
case. Said the court: "4. Sellers to appoint neutral survey for Seller's account to conduct
initial draft survey at first discharge port and final survey at last
discharge port. Surveyors results to be binding and final. In the event
"An examination of the sales contract No. S151.8.01018 shows that it
draft survey results show a quantity less than the combined Bills of
is broad enough to include the claim for damages arising from the
Lading quantity for both Puromines and Makati Agro, Sellers to refund
carriage and delivery of the goods subject-matter thereof.
the difference. In the event that draft survey results show a quantity in
excess of combined Bills of Lading of quantity of both Puromines and
"It is also noted that the bills of lading attached as Annexes 'A', 'B' and Makati Agro then Buyers to refund the difference.
'C' to the complaint state, in part, 'any dispute arising under this Bill of
Lading shall be referred to arbitration of the Maritime Arbitration
"5. It is expressly and mutually agreed that neither Sellers nor vessel's
Commission at the USSR Chamber of Commerce and Industry, 6
Owners have any liability to separate cargo or to deliver cargo
Kuibyshevskaia Str., Moscow, USSR, in accordance with the rules of
separately or to deliver minimum/maximum quantities stated on
procedure of said commission.'
individual Bills of Lading. At each port vessel is to discharge in
accordance with Buyers local requirements and it is Buyer's
Considering that the private respondent was one of the signatories to responsibility to separate individual quantities required by each of them
the sales contract . . . all parties are obliged o respect the terms and at each port during or after discharged."
conditions of the said sales contract, including the provision thereof on
'arbitration.' "
As argued by respondent on its motion to dismiss, "the (petitioner)
derives his right to the cargo from the bill of lading which is the contract
Hence, this petition The issue raised is: Whether the phrase "any of affreightment together with the sales contract. Consequently, the
dispute arising under this contract" in the arbitration clause of the sales (petitioner) is bound by the provisions and terms of said bill of lading
contract covers a cargo claim against the vessel (owner and/or and of the arbitration clause incorporated in the sales contract."
charterers) for breach of contract of carriage.
12
Assuming arguendo that the liability of respondent is not based on the raised herein. They should be addressed to the arbitrators. This
sales contract, but rather on the contract of carriage, being the proceeding is merely a summary remedy to enforce the agreement to
charterer of the vessel MV "Liliana Dimitrova," it would, therefore, be arbitrate. The duty of the court in this case is not to resolve the merits
material to show what kind of charter party the respondent had with the of the parties' claims but only to determine if they should proceed to
shipowner to determine respondent's liability. arbitration or not. And although it has been ruled that a frivolous or
patently baseless claim should not be ordered to arbitration it is also
recognized that the mere fact that a defense exist against a claim does
American jurisprudence defines charter party as a contract by which an
not make it frivolous or baseless." 19
entire ship or some principal part thereof is let by the owner to another
person for a specified time or use. 10 Charter or charter parties are of
two kinds. Charter of demise or bareboat and contracts of In the case of Bengson v. Chan, 20 We upheld the provision of a
affreightment. contract which required the parties to submit their disputes to
arbitration and We held as follows:
Under the demise or bareboat charter of the vessel, the charterer will
generally be considered as owner for the voyage or service stipulated. "The trial court sensibly said that 'all the causes of action alleged in the
The charterer mans the vessel with his own people and becomes, in plaintiffs amended complaint are based upon the supposed violations
effect, the owner pro hac vice, subject to liability to others for damages committed by the defendants of the 'Contract of Construction of a
caused by negligence. 11 To create a demise the owner of a vessel Building' and that 'the provisions of paragraph 15 hereof leave a very
must completely and exclusively relinquish possession, anything short little room for doubt that the said causes of action are embraced within
of such a complete transfer is a contract of affreightment (time or the phrase 'any and all questions, disputes or differences between the
voyage charter party) or not a charter party at all. parties hereto relative to the construction of the building,' which must
be determined by arbitration of two persons and such determination by
the arbitrators shall be 'final, conclusive and binding upon both parties
On the other hand, a contract of affreightment is in which the owner of
unless they to court, in which the case the determination by arbitration
the vessel leases part or all of its space to haul goods for others. It is a
is a condition precedent 'for taking any court action."
contract for a special service to be rendered by the owner of the vessel
12 and under such contract the general owner retains the possession,
command and navigation of the ship, the charterer or freighter merely xxx xxx xxx
having use of the space in the vessel in return for his payment of the
charter hire. 13 If the charter is a contract of affreightment, which
"We hold that the terms of paragraph 15 clearly express the intention
leaves the general owner in possession of the ship as owner for the
of the parties that all disputes between them should first be arbitrated
voyage, the rights, responsibilities of ownership rest on the owner and
before court action can be taken by the aggrieved party." 21
the charterer is usually free from liability to third persons in respect of
the ship. 14
Premises considered, We uphold the validity and applicability of the
arbitration clause as stated in Sales Contract No. S151.8.01018 to the
Responsibility to third persons for goods shipped on board a vessel
present dispute.
follows the vessel's possession and employment; and if possession is
transferred to the charterer by virtue of a demise, the charterer, and
not the owner, is liable as carrier on the contract of affreightment made WHEREFORE, petition is hereby DISMISSED and decision of the
by himself or by the master with third persons, and is answerable for court a quo is AFFIRMED.
loss, damage or non-delivery of goods received for transportation. An
owner who retains possession of the ship, though the hold is the
SO ORDERED.
property of the charterer, remains liable as carrier and must answer for
any breach of duty as to the care, loading or unloading of the cargo. 15

Assuming that in the present case, the charter party is a demise or


bareboat charter, then Philipp Brothers is liable to Puromines, Inc.,
subject to the terms and conditions of the sales contract. On the other
hand, if the contract between respondent and the owner of the vessel
MV "Liliana Dimitrova" was merely that of affreightment, then it cannot
be held liable for the damages caused by the breach of contract of
carriage, the evidence of which is the bills of lading

In any case, whether the liability of respondent should be based on the


same contract or that of the bill of lading, the parties are nevertheless
obligated to respect the arbitration provisions on the sales contract
and/or the bill of lading. Petitioner being a signatory and party to the
sales contract cannot escape from his obligation under the arbitration
clause as stated therein.

Neither can petitioner contend that the arbitration provision in the bills
of lading should not have been discussed as an issue in the decision of
the Court of Appeals since it was not raised as a special or affirmative
defense. The three bills of lading were attached to the complaint as
Annexes "A," "B," and "C," and are therefore parts thereof and may be
considered as evidence although not introduced as such. 16 Hence, it
was then proper for the court a quo to discuss the contents of the bills
of lading, having been made part of the record.

Going back to the main subject of this case, arbitration has been held
valid and constitutional. Even before the enactment of Republic Act
No. 876, this Court has countenanced the settlement of disputes
through arbitration. The rule now is that unless the agreement is such
as absolutely to close the doors of the courts against the parties, which
agreement would be void, the courts will look with favor upon such
amicable arrangements and will only interfere with great reluctance to
anticipate or nullify the action of the arbitrator. 17

As pointed out in the case of Mindanao Portland Cement Corp. v.


McDonough Construction Company of Florida 18 wherein the plaintiff
sued defendant for damages arising from a contract, the Court said:

"Since there obtains herein a written provision for arbitration as well as


failure on respondent's part to comply therewith, the court a quo rightly
ordered the parties to proceed to their arbitration in accordance with
the terms of their agreement (Sec. 6 Republic Act 876). Respondent's
arguments touching upon the merits of the dispute are improperly

13

You might also like