Project : Proposed Two Storey Residential

Location : San Marino South 1 Subd., Brgy. Salawag, Dasmari ñas, Cavite
Subject : BAR CHART

WEIGHT DATE
ITEM WORK DESCRIPTION
FACTOR Start End MARCH 2015 APRIL 2015 MAY 2015 JUNE 2015

I. General Requirements 8.84 3/16/2015 8/15/2015 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21

II. Structural Works


2.1 Structural Concrete, cast in place
2.1.1 Footings 1.36 4/6/2015 4/11/2015 0.68 0.68

2.1.2 Columns 2.29 4/20/2015 4/25/2015 1.15 1.15

2.1.3 Suspended Slabs (First Floor) 1.10 5/11/2015 5/16/2015 0.55 0.55

2.1.4 Slab on Grade (Ground Floor) 1.10 6/1/2015 6/6/2015 0.55 0.55

2.1.5 Extended Fire Wall column 2.48 5/25/2015 5/29/2015 1.24 1.24

72.48%
2.2 Concrete Forming Accessories
2.2.1 Footings 0.40 3/30/2015 4/4/2015 0.20 0.20

2.2.2 Columns 0.25 4/8/2015 4/17/2015 0.00 0.00

2.2.3 Suspended Slabs (First Floor) 1.62 4/27/2015 5/2/2015 0.81 0.81 61.77%

2.2.4 Extended Fire Wall column 2.43 5/18/2015 5/22/2015 1.22 1.22

2.3 Concrete Reinforcing Steel Bars 53.81%


2.3.1 Footings 2.14 3/23/2015 3/28/2015 1.07 1.07

2.3.2 Suspended Slabs 5.98 5/4/2015 5/9/2015 2.99 2.99 47.41%

2.4 I-Beams
42.36%
2.4.1 Columns 13.55 4/6/2015 4/17/2015 3.39 3.39 3.39 3.39
39.10%
2.4.2 Beams 6.41 4/20/2015 5/2/2015 1.60 1.60 1.60 1.60

III. Architectural Works


3.1 Masonry Works 2.81 5/18/2015 6/27/2015 30.96% 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23

3.2 Metal Works 6.47 5/25/2015 6/27/2015 0.65 0.65 0.65 0.65 0.65 0.65
25.72%
IV. Roofing and Tinsmitry
4.1 Trusses 5.87 6/1/2015 6/13/2015 1.47 1.47 1.47 1.47

4.2 C-Purlins 7.72 6/8/2015 6/20/2015 1.93 1.93

4.3 Roofing 2.88 6/22/2015 6/27/2015 13.03%

V. Plumbing Works 10.21 5/4/2015 8/15/2015 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36

VI. ELECTRICAL WORKS 14.09 5/4/2015 8/15/2015 5.83% 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
4.05%
2.56%
0.00%

TOTAL 100.00

WEEKLY PROJECTED ACCOMPLISHMENT 2.56% 1.49% 1.78% 7.20% 12.69% 5.25% 8.14% 3.26% 5.06% 6.40% 7.95% 10.71%

WEEKLY CUMMULATIVE ACCOMPLISHMENT 2.56% 4.05% 5.83% 13.03% 25.72% 30.96% 39.10% 42.36% 47.41% 53.81% 61.77% 72.48%
JUNE 2015 JULY 2015 AUGUST 2015

100.00%
0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21
97.84%
95.68%
93.53%
91.37%
89.21%
87.06%

81.70%

72.48%

0.23 0.23 0.23 0.23

0.65 0.65 0.65 0.65

1.93 1.93

0.72 0.72 0.72 0.72

0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36

0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50

9.22% 5.36% 2.16% 2.16% 2.16% 2.16% 2.16% 2.16%

81.70% 87.06% 89.21% 91.37% 93.53% 95.68% 97.84% 100.00%