Fountain MTO
Fountain MTO
NUMBER
2.12
2.12.1
2.12.1
2.12.3
DESCRIPTION
Fountain , the item include all the exacvation & backfilling, concrete,
waterproofing, supply and drainage pipework, fountain pumps, electrical power and
lighting, and all associated works including installation and testing as per
drawings, specification and Engineer instructions as shown in detail 1 on drawing
XL-303
Structural Excavation
Structural Backfill
Concrete
Rebar
Formworks
Waterproofing
Structural Excavation
Structural Backfill
Concrete
Rebar
Formworks
Waterproofing
Nozzle
Structural Excavation
Structural Backfill
Concrete
Rebar
Formworks
Waterproofing
Nozzle
UNIT QUANTITY
nr 1.00
m3 37.06
m3 3.18
m3 56.49
kg 5,366.13
m2 239.05
m2 164.33
m2 114.05
m2 73.65
m2 26.46
nr 32.00
nr 9.00
nr 1.00
m3 79.09
m3 4.06
m3 56.19
kg 5,337.91
m2 159.25
m2 275.53
m2 253.66
m2 24.55
m2 47.56
nr 12.00
2.00
m3 79.94
m3 5.29
m3 40.32
kg 3,830.77
m2 111.67
m2 191.70
m2 167.11
m2 24.59
m2 28.20
nr 8.00
WATER FOUNTAIN TYPE 1 MTO:
SUMMARY
DESCRIPTION UNIT
Structural Excavation m3
Structural Backfill m3
Concrete m3
Rebar kg
Formworks m2
Waterproofing m2
Stone Cladding Textured Fin Colors m2
25x25 Ceramic Mosaic Tiles Colors m2
Granite Finish Tiles m2
Stainless Steel opening for Water Feature nr
Jumping Jet Water Feature w/varies Height (600 mm Max) nr
0.20
CONCRETE
QTY BOTTOM SLAB EXCAVATION
37.06 DEPTH WIDTH 1 WIDTH 2 THK AREA VOLUME DEPTH
3.18 6.70 10.00 24.00 0.20 113.90 22.78 7.10
56.49
5,366.13 BOTTOM WALL BACKFILL
239.05 DEPTH WIDTH 1 WIDTH 2 HEIGHT AREA VOLUME
164.33 5.90 9.84 23.00 0.40 17.01 6.81
114.05
73.65 TRAPEZIODAL SIDE SLOPE
26.46 NAME SLANT W RATIO AREA THK VOLUME
32.00 SLOPE-1 2.91 1.77 31.66 0.20 11.18
9.00 SLOPE-2 2.91 1.77 22.53 0.20 7.95
Assumed Ratio:
MWORKS REINFORCEMENT BARS WATERPROOFING
REINFORCEMENT BOTTOM SLAB
RATIO AREA' CONC VOL RATIO EST Kg AREA-1
1.37 31.20 56.49 95.00 5,366.13 21.96
BOTTOM WALL
THK AREA' PRMTR-1 PRMTR-2
0.40 41.78 12.73 25.90
AREA 2 AREA'
9.20 11.72
9.20 11.72
NOS RATIO
13.00 1.37
rcement Ratio:
Unit Wt T Wt
0.89 1,075.06
0.89 1,075.06
2,150.12
Assumed Ratio: 95.00
ROOFING INDISE CLADDING OUTSIDE CLAD
BOTTOM SLAB CERAMIC MOSAIC TILES
AREA-2 AREA' AREA-1 AREA-2 AREA'
10.88 32.84 21.96 10.88 32.84
SUMMARY
DESCRIPTION UNIT
Structural Excavation m3
Structural Backfill m3
Concrete m3
Rebar kg
Formworks m2
Waterproofing m2
25x25 Ceramic Mosaic Tiles Light Blue m2
25x25 Ceramic Mosaic Tiles Dark Blue m2
Granite Finish Tiles m2
Nozzle nr
0.20
CONCRETE EAR
QTY BOTTOM SLAB 1 EXCAVATION 1
79.09 DEPTH WIDTH 1 WIDTH 2 THK AREA VOLUME
4.06 0.20 148.88 29.78
56.19
5,337.91 BOTTOM SLAB 2 EXCAVATION 2
159.25 DEPTH WIDTH 1 WIDTH 2 THK AREA VOLUME
275.53 0.20 84.38 16.88
253.66
24.55 WALL BACK FILL 1
47.56 NAME NAME AREA DEPTH VOLUME AREA 1
12.00 WALL-1 7.11 0.60 4.26 148.88
WALL-2 5.43 0.50 2.71
WALL-3 5.11 0.50 2.56
BACK FILL 2
AREA 1
79.22
T
TOTAL CONCRETE: 56.19
1.10
EARTHWORKS FORMWORKS
EXCAVATION 1 BOTTOM SLAB 1
THK CAD AREA VOLUME VOLUME RATIO
0.40 154.51 61.80 29.78 1.37
Assumed Ratio:
REINFORCEMENT BARS WATERPROOFING
REINFORCEMENT BOTTOM SLAB 1
AREA CONC VOL RATIO EST Kg CAD AREA AREA
40.78 56.19 95.00 5,337.91 138.29 138.29
BOTTOM SLAB 2
AREA CAD AREA AREA
23.11 72.16 72.16
WALL
AREA PRMTR 1 PRMTR 2 DEPTH 1 DEPTH 2 AREA
42.64 34.91 - 0.60 - 20.95
27.15 26.90 - 0.50 - 13.45
25.57 25.55 25.58 0.50 0.70 30.68
RATIO
1.37
T Wt
1,075.06
1,075.06
2,150.12
95.00
INSIDE CLADDING OUTSIDE CLADDING
CERAMIC MOSAIC TILES BOTTOM SLAB 1
NOS L W DARK LIGHT
48.00 0.25 0.25 3.00 135.29
Tiles Ratio:
NOS CUT L CUT W W D RATIO
39 0.25 0.25 10.0409 0.5 0.20
IDE CLADDING
ES WALL
OUTSIDE T AREA
21.69 28.80
8.22 13.65
- 5.11
SUMMARY
DESCRIPTION UNIT
Structural Excavation m3
Structural Backfill m3
Concrete m3
Rebar kg
Formworks m2
Waterproofing m2
25x25 Ceramic Mosaic Tiles Light Blue m2
25x25 Ceramic Mosaic Tiles Dark Blue m2
Granite Finish Tiles m2
Nozzle nr
0.20
CONCRETE
QTY BOTTOM SLAB 1 EXCAVATION 1
79.94 DEPTH WIDTH 1 WIDTH 2 THK AREA VOLUME DEPTH
5.29 7.50 9.50 24.50 0.20 127.50 25.50 7.70
40.32
3,830.77 BOTTOM SLAB 2 EXCAVATION 2
111.67 DEPTH WIDTH 1 WIDTH 2 THK AREA VOLUME DEPTH
191.70 3.80 7.30 14.50 0.20 41.42 8.28 3.80
167.11
24.59 WALL EXCAVATION 3
28.20 NAME NAME AREA DEPTH VOLUME
8.00 WALL-1 7.92 0.50 3.96
WALL-2 3.42 0.50 1.71
WALL-3 2.90 0.30 0.87
BACK FILL 1
BACK FILL 2
EXCAVATION 3 WALL
LENGTH WIDTH DEPTH AREA VOLUME PRMTR 1 PRMTR 2
14.50 0.20 0.20 2.90 0.58 38.45 40.71
16.75 17.48
14.5 14.5
BACK FILL 1
AREA 1 AREA 2 AREA' THK VOLUME
127.50 133.98 6.48 0.40 2.59
BACK FILL 2
AREA 1 AREA 2 AREA' THK VOLUME
39.24 42.94 3.70 0.60 2.22
Assumed Ratio:
MWORKS REINFORCEMENT BARS WATERPROOFING
REINFORCEMENT BOTTOM SLAB 1
RATIO AREA CONC VOL RATIO EST Kg CAD AREA
1.37 34.93 40.32 95.00 3,830.77 116.68
BOTTOM SLAB 2
RATIO AREA CAD AREA
1.37 11.35 35.82
WALL
DEPTH AREA PRMTR 1 PRMTR 2 DEPTH 1 DEPTH 2
0.50 39.58 38.45 - 0.50 -
0.50 17.12 16.75 - 0.50 -
0.30 8.70 14.50 14.50 0.30 0.50
NOS RATIO
13.00 1.37
rcement Ratio:
Unit Wt T Wt
0.89 1,075.06
0.89 1,075.06
2,150.12
Assumed Ratio: 95.00
FING INSIDE CLADDING OUTSIDE CLADDIN
CERAMIC MOSAIC TILES BOTTOM SLAB 1
AREA NOS L W DARK LIGHT
116.68 216.00 0.25 0.25 13.50 103.18
Tiles Ratio:
NOS CUT L CUT W W D RATIO
39 0.25 0.25 10.0409 0.5 0.20
OUTSIDE CLADDING