We are ready to carry out SAT for the system.

Find below DCS/PLC SAT agenda.

Period from 28 Aug to 31 Aug 10

28 Aug 10

Time : 10:00 am to 1:00 pm

Activity :

1) DCS/PLC Bill of Material Verification for all units (including Common Area).

Time : 2:30 pm to 6:00 pm

Activity:

1) DCS/PLC cabinet GA/IGA physical verification.


2) Console G/A IGA check.
3) Software Installation check.

30 Aug 10

Time : 10:00 am to 1:00 pm

Activity :

1) DCS/PLC Power & I/O Redundancy check for all units.

Time : 2:30 am to 6:00 pm

Activity :

1) SCAN time/Processor Loading check for PLC/DCS.


2) PLC/DCS System Diagnostic checks.
3) SOE Functionality and station interchangeability check.
4) Graphic Check Record Verification
5) Third party Interface on MODBUS Check.

31 Aug 10

Time : 10:00 am to 1:00 pm

Activity :

Common area Functionality

1) AIMS/DON functionality.
2) OPC connectivity, Report Generation.
3) GPS Time Syncroniasation check.
4) HMS Installation check.

Time : 2:30 am to 6:00 pm


Activity :

1) Loop Check Record verification.


2) Graphic Check Record Verification.
3) Interlock/Sequence Check record verification.