TANGEDCO , KONULAMPALLAM

Report to Accompany the Estimate

SCOPE :- This proposal envisages for replacement of 2 Nos Corroded RCC Poles
in Andiramapuram - V - D.T in AE / O&M / Konulampallam Section of
AEE / O&M / North / Sub-Division, Kumbakonam North Division.

SALIENT FEATURES :- This proposal involves with the following works


1.Replacement of Corroded RCC Poles -- by Erection of New
7.5 Mts RCC Poles -- 2 Nos.

ESTIMATE COST :- This Estimate works out to a cost of Rs. 10198 (G) &
Rs. 9758 (N).

CONCLUSION :- This Estimate has been prepared under improvement scheme to avoid
accidents and to maintain Un-interrupted supply to the consumers.

CERTIFICATE :- Certified that the poles were inspected by me on …………………..


and found that the damages are not due to the carelessness / negligence
of any Board officials or staff, falling of Branch of tree belonging to private
person or hit by private vehicle or Article. It is only due to Normal
wear and tear, and also due to ageing.
So, I request that the estimate may kindly be sanctioned early please.

CREDIT ESTIMATE
Amount
Description Qty Rate Per
Sl.No Rs Pe
1 7.5 Mts RCC Pole 2 10 20 Kg 400

Total Cost of Materials 400


Original Erection Charges10% 40
Total 440
or Say Rs. 440
Dismantling Charges 5 % 22

LABOUR STATEMENT
Sl Amount
Description QTY Per Rate
No Rs Pe
1 Surveying L.S 150
2 Tree Cutting L.S 198
3 Transport of Pole and other Line
Materials from Store to Site 2 E 123 246
4 Excavation of Pole Pit 2 E 71 142
5 Fixing of Insulators and Cross Arms 3 E 72 216
6 Erection of Pole 2 E 118 236
7 Erection of Stay set Complete 1 E 195 195
8 Paving and Stringing of Conductor 0
including Transport. Km 570 0
9 Resagging of Lines L.S 150
10 Earthing Loc 218 0

Cost of Un-skilled Labour 1533


Add : 40 % towards cost of Skilled Labour 613
2146
Or Say Rs 2146
B.TRANSPORT STATEMENT ( Cost Data -- 2011 - 2012 )
1 Transportation of 9.14 Mts RCC Pole Span 247 0
2 Transportation of 7.5 Mts RCC Pole 2 Span 180 360
3 Transportation of Line conductor 0
7/132 (7/3.35 Sq.mm) ACSR Span 85 0
4 Transportation of Line conductor 0
7/102 (7/2.59 Sq.mm) ACSR Span 51 0
0
Total 360
Or Say Rs 360

DETAILED ESTIMATE - L.T.OH.FEEDER


SL B.S B.S
NO: Description Qty Rate Per Amount
1 9.14 Mts RCC Pole 5203 Each 0
2 7.5 Mts RCC Pole 2 2401 Each 4802
3 Base Plate 2 83 Each 166
4 Three Phase Cross Arm 685 Each 0
5 Single Phase Cross Arm 220 Each 0
6 Back Clamp 9.14 Mts Pole 108 Each 0
7 Back Clamp 7.5 Mts Pole 67 Each 0
8 Stay set Complete 1 787 Set 787
9 Stay Clamp 129 Pair 0
10 Guy Shackle 1 11 Each 11
11 L.T. Shackle with Hardware 44 Set 0
12 L.T. Pin and Insulator 46 Set 0
13 L.T. TI Fitting 260 Each 0
14 Alu Knob 21 Each 0
15 7/132(7/3.35 Sq.mm)ACSR 42348 Km 0
16 7/102(7/2.59 Sq.mm)ACSR 19527 Km 0
17 M.S. Bolt and Nut 376 Loc 0
18 Earthing 829 Loc 0
19 Guarding X Arm 808 No 0
20 No: 8 G.I.Wire 58000 0

TOTAL COST OF MATERIALS 5766


Contingencies 1 % 577
6343
Labour ( A ) 2146
Transport ( B ) 360
Estt and Supervision Charges 15 % 1327
10176
Dismantling Charges 22
10198

Gross Rs 10198
Less Credit 440
Net Rs 9758
PART - II Transfer to Provision for Depreciation of Old Asset
( Credit to A/C No : 12-6 )

Life Period of the Asset as per Supply Act 25 Years


Cost of Original Asset Replaced
Less 10 % Value
or Say Rs
Life Served Years
Depreciation
25 0 or Say Rs

PART - III Chargeable to Stock


( Credit to A/C No : 22-3 )

Original cost of Asset Replaced Rs


Less Depreciation Rs

Written Down Value Rs


( Devolution to be Prepared )

PART - IV Chargeable to Fixed Asset


( Credit to A/C No : 10-601 )

Original cost of Asset Withdrawn Rs


Debit to Provision for Depreciation Rs
Debit to Stock on Devolution Rs

SUMMARY OF ESTIMATE

PART -Detailed Estimate Gross Rs


( Debit to A/C No : 14-656 ) Nett Rs
Newly Acquired Asset

PART - Transfer to Provision for Depreciation


on Old Asset Rs
( Debit to A/C No : 12-6 )

PART - Chargeable to Stock Rs


( Debit to A/C No : 22-300 )

PART - Chargeable to Fixed Asset Rs


( Debit to A/C No : 10-601 )
2
1
Sl No

LOC. NO

E2
E1
1
1
7.5 Mts RCC pole

L.T.3 Ф X Arm

L.T TI Fitting

Back Clamp

1
Stay set Complete

Stay Clamp Pair

1
Guy Shackle

L.T. Shackle

L.T. Metal Parts

L.T Pin
L.T. POLE SCHEDULE

L.T. Pin Insulator

Alu Knob

No: 8, G.I.Wire

Span Length

No. of Run

7/2.59 Sq.mm ACSR

M.S Bolt & Nuts


1
1

7.5 Mts RCC pole

L.T.S Ф X Arm

L.T Pin
CREDIT

L.T Pin Insulator


Total 2 0 0 0 1 0 1 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0