Professional Documents
Culture Documents
New Incinerator Estimates - Mech: Items Description Days Man-Day Materials Labour Fuel Tank & Fuel Line
New Incinerator Estimates - Mech: Items Description Days Man-Day Materials Labour Fuel Tank & Fuel Line
Safety Shower
1 Portable pipe installation 4 3 $ 800.00 $ 137.50
2 Safety Shower installation & insulation 2 3 $ 1,000.00 $ 137.50
Other
1 Crane by crabe team 0 0 $ - $ -
2 General steel works support 5 4 $ 1,000.00 $ 137.50
$ 22,275.00
Total
$ 412.50
$ 412.50
$ 1,300.00
$ 1,600.00
$ 1,100.00
$ 1,100.00
$ 1,650.00
$ 1,325.00
$ 3,412.50
$ 1,937.50
$ 2,450.00
$ 1,825.00
$ -
$ -
$ -
$ 3,750.00
$ 16,500.00 per month
$ 687.50 per day
$ 57.29 per hour