New Incinerator Estimates - Mech

Items Description Days Man-Day Materials Labour


Fuel Tank & fuel line
1 Fuel tank relocation 1 3 $ - $ 137.50
2 Fuel tank installation 1 3 $ - $ 137.50
3 Fuel oil piping & configuration 2 4 $ 200.00 $ 137.50

Incinerator Installation & Commissioning


1 Fabrication & temporary work 2 4 $ 500.00 $ 137.50
2 Assist crane team 2 4 $ - $ 137.50
3 Installation & alignment 2 4 $ - $ 137.50
4 Assist commissioning 3 4 $ - $ 137.50

Sump pump & pipework


1 Sump pump support fabrication 3 2 $ 500.00 $ 137.50
2 Sump pump installation 1 3 $ 3,000.00 $ 137.50
3 Pipework 3 3 $ 700.00 $ 137.50

Safety Shower
1 Portable pipe installation 4 3 $ 800.00 $ 137.50
2 Safety Shower installation & insulation 2 3 $ 1,000.00 $ 137.50

Process water & Air line


1 Process water & Air line by Maintenance 0 0 $ - $ -
2 Plumbing work by others 0 0 $ - $ -

Other
1 Crane by crabe team 0 0 $ - $ -
2 General steel works support 5 4 $ 1,000.00 $ 137.50
$ 22,275.00
Total

$ 412.50
$ 412.50
$ 1,300.00

$ 1,600.00
$ 1,100.00
$ 1,100.00
$ 1,650.00

$ 1,325.00
$ 3,412.50
$ 1,937.50

$ 2,450.00
$ 1,825.00

$ -
$ -

$ -
$ 3,750.00
$ 16,500.00 per month
$ 687.50 per day
$ 57.29 per hour

$ 137.50 per man