Professional Documents
Culture Documents
Case Study On 3D Printing Implementation Strategies
Case Study On 3D Printing Implementation Strategies
William J. Leonard
California Polytechnic State University
San Luis Obispo, California
The construction industry is one of the slowest to adapt and utilize new technologies. As a result,
the construction industry has remained stagnant while almost all others are improving efficiency.
It is becoming incredibly important for the construction industry to adapt to new technologies in
order to counter the current worldwide shortage in skilled labor. 3D printing is one of the most
advanced technologies that can help increase efficiency and reduce cost across all sectors of the
construction industry. This paper will analyze implementation strategies used on three different
construction projects using 3D printing and will evaluate what made them successful and what
challenges were faced. When analyzing the implementation strategies, this paper will focus on
what collaboration between the design and construction team was most effective, and how the use
of 3D printing changed the construction process. The purpose of this paper is to provide
suggestions regarding witch of the strategies are most effective for differing project types.
Introduction
As the technologies have advanced and become more cost efficient, they have been implemented to build complete
buildings. The first of these notable advances was in 2014, when a firm in Amsterdam printed a complete canal
house out of plastic using a printer connected to a large crane arm. Second in 2015, a different Dutch firm, MX3D,
printed a full-scale steel bridge in downtown Amsterdam that aims to make steel construction faster and more cost
efficient. Third in 2016, a Chinese company named HuaShang Tengda began construction on a 3D printed mansion
made entirely of structural concrete. This mansion boasts to be earthquake safe and was completed in 45 days.
Most recently, a Chinese company named Winsun printed 10 houses in 24 hours. After completing 10 houses in 24
hours, Winsun also printed the first 3D printed commercial office building. (I would sum up this section of the intro
somehow, ends a little awkwardly)
Case Study
[Project specifics on how they implemented 3DP. What this changed about the process from traditional
construction. Describe advances in technology and how it allowed these strategies, and what changed in scheduling
etc.]
I analyzed three different construction projects that all successfully implemented 3D printing in different ways and
for different scopes of work.
Although the cladding shroud in not a structural element of the building, the nodes must perform as structural
components to ensure the cladding system stays in place. These nodes were tested for 1000 mph winds for 2000
hours and tested for extreme weather conditions before they were approve and installed. These components passed
with flying colors and the roof specialist who installed the canopy included these components in their warranty of
the system. According to Skanska: “traditional methods, such as case steel nodes, would have been much more
expensive and difficult to produce.” Skanska also is aiming to utilize this success on the 6 Bevis Marks to start a 3D
printing supply chain to print complex parts for all of their clients.
This project was the first of its kind to be completely printed on site, rather than shipping preprinted parts from
factories. The project first prepared a pre-poured concrete foundation complete with all necessary reinforcement
and plumbing installed for the complete 3D printed mansion. Once 3D printing commenced, the mansion was
completed using a combination of four different systems: an electronic ingredient formulation system, a concrete
mixing system, a transmission system and a 3D printing system. The traditional concrete reinforcement system used
does not require any additives in the concrete and allows for locally produced concrete. The use of locally produced
concrete greatly reduces the transportation costs and simplifies delivery logistics, however HuaShang Tengda claims
that the greatest benefit is the increased speed. HuaShang Tengda estimates that constructing this mansion would
have taken three months if conventional techniques were used. The company claimed that this competitive
advantage would provide them the extra edge they need to compete internationally when bidding on projects. Once
completing the 3D printing process, the crews painted and decorated the interior of the Mansion.
One of the largest challenges on this project was acquiring the permits for the bridge. Integrity of the bridge is of
paramount concern and so MX3D must prove that the bridge is and will continue to be structurally sound. They
have used advanced pieces of technology used on this project is the sensors observing how the steel reacts to the
pedestrians crossing the bridge. These sensors monitor the number of pedestrians on the bridge and the speed that
they walk across at. The sensors will also measure the temperature and the condition of the steel. All of these
sensors then are imported into the bridge’s “digital twin” where tests can be done on the live condition of the bridge.
Figure 3: MX3D Project Photos
Another success on the project was the use of 3D nylon sintered technology when printing these nodes. This
material choice not only achieved the engineering standards required, but also was a much cheaper alterative to
conventional steel welding and splicing. 3D printing has provided a plethora of available materials and the architect
showed a perfect example of how to utilize these materials for any use on the project.
One of the challenges overcome on this project was an unexpected concern about the structural integrity of the
existing canal walls. Although this is not surprising due to the age and historic significance of the Oudezijds
Achterburgwal canal, it still restricted MX3D from printing the bridge onsite. Although this specific bridge was
unable to be printed onsite due to site conditions it had the technology to be printed from both sides of the canal and
to meet in the middle. This allows for the bridge to be printed at double the speed than originally expected. By
implementing this new technology, MX3D cut their printing time in half, which was significantly faster than
conventional steel construction.
Technology Challenges
The implementation of new 3D printing technologies can be incredibly challenging throughout all stages of a
project. All three of the project schedules were completely revised to allow for increased time to collaborate with
3D printing specialists and successfully employ these new technologies. First, on the 6 Bevis Mark project, they
faced challenges choosing which material would provide the desired finish and quality project required by the
architect. Second, on the HuaShang Tengda Mansion the technology challenges came when designing the correct
concrete mix to use to meet structural requirements to achieve earthquake resistance. Third, on the MX3D Bridge,
they faced challenges with getting the desired directional mobility out of their 3D printing welders. To achieve this,
they upgraded the robotic arm giving the welder the range of motion it required. MX3D was the most successful
implementing the new 3D printing technology and overcoming any questions doubting the ability of the machines to
print the desired project.
Coordination Challenges
3D printing requires immense amounts of coordination by both the design team and the construction team to learn
and successfully implement this new construction method. This coordination flows through all parties including the
Contractor, Architect, Engineers, 3D Printing Specialists, and Software Specialists. The coordination between
parties when building the MX3D Bridge was most successful, allowing them the smoothest implementation of new
technology on the project. MX3D utilized their advantage of being a 3D printing firm to help overcome many of the
challenges of changing conventional construction techniques to accommodate 3D printing. However, on the
HuaShang Tengda Mansion they showed the opportunity for construction companies to impart their knowledge in
site logistics to provide the smoothest operation of large-scale 3D printers on-site. They specifically coordinated
this utilizing their four different systems: an electronic ingredient formulation system, a concrete mixing system, a
transmission system and a 3D printing system. This coordination on-site allowed for the largest schedule advantage
on any of the projects analyzed.
Design Challenges
Although 3D printing provides incredible opportunity for complex designs, it also provides challenges for designers
who are unfamiliar with 3D printing. These challenges arose when designing the structural components for the
HuaShang Tengda Mansion and the MX3D Bridge. When designing the mansion to withstand such harsh seismic
conditions as an 8 on the Richter scale, challenges arose of how to shape the wall successfully so that is can be
efficiently be printed, and still meet structural requirements. When designing the MX3D Bridge, they also had
trouble ensuring the structural integrity of the bridge over time. The initial design called for regular steel, coated to
protect from the elements, however MX3D had to revise their design to stainless steel to allow for the 3D printed
elements to be visible without a coating. Although these design challenges have caused hiccups for these early 3D
printing projects, they were all quickly surpassed and have given the construction industry endless opportunity to
design without conventional shape constraints.
References
B. (2017, September 20). MX3D says 3D printed steel bridge in Amsterdam 'one-third printed,' expects June 2018
finish. Retrieved June 11, 2018, from https://www.3ders.org/articles/20170920-mx3d-says-3d-printed-
steel-bridge-in-amsterdam-one-third-printed-expects-june-2018-finish.html
Gosselin, C., Duballet, R., Roux, P., Gaudillière, N., Dirrenberger, J., & Morel, P. (2016). Large-scale 3D printing
of ultra-high performance concrete – a new processing route for architects and builders. Materials &
Design, 100, 102-109. doi:10.1016/j.matdes.2016.03.097
Griffiths, A. (2013, December 06). "First architectural application" of 3D printing claimed | technology. Retrieved
June 14, 2018, from https://www.dezeen.com/2013/12/02/first-architectural-application-of-3d-printing-
adrian-priestman-6-bevis-marks/
Hager, I., Golonka, A., & Putanowicz, R. (2016). 3D Printing of Buildings and Building Components as the Future
of Sustainable Construction? Procedia Engineering, 151, 292-299. doi:10.1016/j.proeng.2016.07.357
Head, H. (2017, May 19). A History of 3D Printing in Construction & What You Need to Know. Retrieved June 10,
2018, from https://connect.bim360.autodesk.com/3d-printing-in-construction
Laubier, R. D., Wunder, M., Witthöft, S., & Rothballer, C. (2018, January 23). Will 3D Printing Remodel the
Construction Industry? Retrieved June 10, 2018, from https://www.bcg.com/publications/2018/will-3d-
printing-remodel-construction-industry.aspx
McCanna, J., & Townsend, H. (2018, February 01). A Dutch startup planned to 3D print a stainless-steel bridge over
a canal, but not all has gone to plan. Retrieved from http://www.eurekamagazine.co.uk/design-engineering-
features/technology/a-dutch-startup-planned-to-3d-print-a-stainless-steel-bridge-over-a-canal-but-not-all-
has-gone-to-plan/168105/
Moltich-Hou, M. (2016, June 16). 400-Square-Meter Villa 3D Printed Onsite in Just 45 Days. Retrieved June 10,
2018, from https://www.engineering.com/3DPrinting/3DPrintingArticles/ArticleID/12415/400-Square-
Meter-Villa-3D-Printed-Onsite-in-Just-45-Days.aspx
Scott, C. (2016, June 16). Chinese Construction Company 3D Prints an Entire Two-Story House On-Site in 45 Days.
Retrieved June 10, 2018, from https://3dprint.com/138664/huashang-tengda-3d-print-house/
Stella, R. (2016, July 09). It's hideous, but this 3D-printed villa in China can withstand a major quake. Retrieved
from https://www.digitaltrends.com/home/3d-printed-chinese-villas-huashang-tenda/
World's First 3D Printed Bridge Paves Way to New Era of Construction. (2016, April 19). Retrieved June 11, 2018,
from https://www.forconstructionpros.com/profit-matters/article/12196489/worlds-first-3d-printed-bridge-
paves-way-to-new-era-of-construction
Wu, P., Wang, J., & Wang, X. (2016). A critical review of the use of 3-D printing in the construction
industry. Automation in Construction, 68, 21-31. doi:10.1016/j.autcon.2016.04.005
Xu, J., Ding, L., & Love, P. E. (2017). Digital reproduction of historical building ornamental components: From 3D
scanning to 3D printing. Automation in Construction, 76, 85-96. doi:10.1016/j.autcon.2017.01.010