This document provides a job risk assessment for post-weld heat treatment work at a 2x30MW coal-fired power plant project in Tanjung Tabalong, Indonesia. It identifies the tasks assessed, which include heating work and post-weld heat treatment. It notes that interface with other field operations needs to be reviewed during work permit submission. Mandatory rules from PT. PLI are listed, including requirements for equipment certification, PPE, safety briefings, permitting competent personnel, and applying for work permits. Signatures from the RCM, QA/QC Manager, HSE Coordinator, and QA/QC Supervisor are provided to approve the assessment.
Original Description:
Original Title
Front page R_A_ JRA for General Work Activity Rev. A
This document provides a job risk assessment for post-weld heat treatment work at a 2x30MW coal-fired power plant project in Tanjung Tabalong, Indonesia. It identifies the tasks assessed, which include heating work and post-weld heat treatment. It notes that interface with other field operations needs to be reviewed during work permit submission. Mandatory rules from PT. PLI are listed, including requirements for equipment certification, PPE, safety briefings, permitting competent personnel, and applying for work permits. Signatures from the RCM, QA/QC Manager, HSE Coordinator, and QA/QC Supervisor are provided to approve the assessment.
This document provides a job risk assessment for post-weld heat treatment work at a 2x30MW coal-fired power plant project in Tanjung Tabalong, Indonesia. It identifies the tasks assessed, which include heating work and post-weld heat treatment. It notes that interface with other field operations needs to be reviewed during work permit submission. Mandatory rules from PT. PLI are listed, including requirements for equipment certification, PPE, safety briefings, permitting competent personnel, and applying for work permits. Signatures from the RCM, QA/QC Manager, HSE Coordinator, and QA/QC Supervisor are provided to approve the assessment.
PT. PUNJ LLOYD INDONESIA PT. MAKMUR SEJAHTERA WISESA JOB RISK ASSESSMENT – FRONT SHEET th Date: 17 Sep’12 Job: Post Weld Heat Treatment No. of sheet Revision: Status: 1 of 2 0A IFA
Rev Date: 10th Dec ‘12
Installation/Site: Power Plant Ref No: PLI-EDP-JRA-CFPPP-Add-04 Discipline: HSSE
Project Site Overall Risk Assessed Acceptable/Unacceptable Re-Assessment Yes/No required? LMRA Notes: Task assessed as follows: 1. Heating Work / pekerjaan pemanasan bahan - Post Weld Heat Treatment / pemanasan material terpusat
Tasks not assessed in this JRA
Interface with other field operations activities to be reviewed during work permit submission Berkaitan dengan aktivitas pihak lain dilapangan yang harus diperiksa pada saat pengajuan izin kerja
PT. PLI Mandatory Rules
New equipment must have valid certifications issued and approved Peralatan yang baru harus memiliki sertifikat yang masih berlaku dan syah Mandatory PPE should be used as per HSE Plan TT-PLL-HSE-001 Rev. B Alat pelindung diri yang wajib harus dipakai berdasarkan HSE Plan TT-PLL-HSE-001 Rev. B Safety briefing/tool box meeting and last minutes risk assessment to conducted prior to start of activity Pengarahan keselamatan/rapat keselamatan dan penilaian resiko terakhir harus dilakukan sebelum memulai kegiatan Only competent personnel to be deployed in the activity Hanya orang yang berkompeten yang harus melakukan kegiatan tersebut Work permit shall be applied before starting activity as per PLI.OCP 04.06 C Ijin kerja harus dikeluarkan sebelum memulai pekerjaan.
PT. PUNJ LLOYD INDONESIA
PRINT NAME DESIGNATION SIGNATURE DATE VT. Muruguan RCM 10th Dec’12 Henry Amalraj QA / QC Manager 10th Dec’12 Ikroman HSE Coordinator 10th Dec’12 Bukhari QA/QC Supervisor 10th Dec’12