Ministry Of Electricity Monthly Progress Report Completion Period: 730 day

General Directorate of Transmission S/S Name: BAHIRKA Commencement Date: 2015

Contract NO: KRG –MOE/NES -02/2013 Current Date: Sep-2016

Previous Current Month Accumulative


ITEM
Description Weighting Progress
NO
Share Rate of
Completion Weighting Rate of Weighting Rate of Weighting
Share Completion Share Completion Share
1 Engineer and 10% -
Design( E+C) 0.51% 0% 0.5% 1.01%
2 Civil Work 35% 4% 0% 1% - 5%

3 Manufacturing 15% 2.5% 0% 0% - 2.5%


and Deliveries
4 Erection 30% 0% 0% 0% - 0

5 Testing and 10% 0% 0% 0% - 0


Commissioning
7.01% 0% 1.5% 8.51%
Total

Site Engineer: Project Manager:


Electric ENG.: Tana Tahr Azeez ENG. Dilawor Arif

Civil ENG. : RAWAND SADIQ