Installation Procedure For Cable Trays
Installation Procedure For Cable Trays
Ensure the work area is ready and safe to start the Installation of cable trays.
Ensure Installation of cable trays are carried in accordance with Manufacture
Installations Recommendation and applicable standards.
Ensure the Project technical Specification of the Installation and complies with
requirements.
Prior to start the installation, refer the approved shop drawing and coordinated
drawings related to the area of installation.
Ensure the required materials are available at site as per approved material.
Ensure the material are stored properly and there is no mark of damage.
All the materials and accessories should be free from dust.
Ensure the Issued material are as per approved specification and the area of
shop drawings (Type, Size, make & Model).
Site Engineer/Site Supervisor has to ensure all civil works completed for the
area of installation.
The area shall be released from civil department to proceed on with cable tray
installation and also the area should be clean and safe to carried out the
activities.
Mark and line out the route of cable tray as per approved shop drawing and
coordinated drawing with marking threads.
Level thread shall be installed and adjusted to the above level of the ceiling.
The Route of cable tray and cable ladder shall be coordinated with other
service.
Ensure the availability of manlift, Scaffolding and other accessories prior to
carried out the cable tray Installation.
Minimum space from the building structure and other service to be maintained
to facilitate easy handling and maintenance of cables.
Fabricate the cable tray support for required size and installed as approved
shop drawings.
The Interval of the of the cable tray support not more than 1.2 meters between
the supports.
The cable tray shall be fixed with metal brackets at an interval of 1200mm or
as per manufacture recommendation.
Expansion connection shall be made wherever applicable.
All straight joints, bend and offset connection shall be made neatly. Wherever
fabricated one required to be use.
Cutting portion of cable trays and supports shall be made free of sharp edges
and coated with Zinc paint.
Cable tray joints are to be positioned close to the support as much possible.
Install the earth flat externally between the length of the cable trays.
Ensure the all the cable tray earth flats connected to the nearest point of main
earthing system.