PROJECT: PROPOSED TWO STOREY BUILDING WITH ROOF DECK

PROJECT LOCATION: COCATOO, BANCAO BANCAO, PUERTO PRINCESA CITY


PROJECT DESCRIPTION: 8.8 m X 35 m
DESCRIPTION: ESTIMATED TIME TABLE

WORK DESCRIPTION SCHEDULE NO. OF DAY REMARKS

Formworks Installation of Plywood for Feb 4 - Feb 12 9 Just waited for the billing
flooring of second floor so the materials can be delivered on site

Steelworks Installation of Steel Reinforcents Feb 7 - Feb 14 8

Concrete Works Pouring of Concrete at second floor Feb 15 - Feb 16 2


Columns at Roofdeck

Roofing Works Fabrication of Steel trusses 10 Depend on the delivery of materials on site
Installation of Steel trusses 5 Can fabricate the trust anytime
and install it after finishing the column
Masonry Works Plastering of Wall Mar-01 8 to 10 at roofdeck
Can do 14 days after pouring
(We will remove some of horizontal braces.)

Tile Works After Curing Period 28 days Mar 15-20 5

Ceiling Works Installation of Ceiling Mar 15-20 5

Painting Works Painting of Walls and Ceiling Mar 15-20 12

Doors and Windows Installation of Doors and Windows Mar 18-20 2

Roel S. Asperas Engr. Ornel C. Asperas ME1


Contractor Contractor/Engineer