Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Back to Basics

An Engineer's Guide to
Management of Change
R. WAYNE GARLAND Using a formal change procedure promotes
EASTMAN CHEMICAL Co.
safe operations and prevents
injuries and deaths, and it will also
favorably impact the bottom line.

e small town of Flixborough, England, has become the review and approval of proposed changes by persons

11 known for the fatal explosion that occurred there in


974 at a caprolactum production plant owned by
Nypro, a joint venture of Dutch State Mines and the British
with the appropriate expertise. This is especially impottant
for processes that contain a large inventory of flammable or
toxic chemicals at high temperature and pressure. Had the
National Coal Board. The explosion took place in a part of team conducted an MOC procedure, it would have discov-
the plant that involved the oxidation of cyclohexane to cyclo- ered the problem with this short-tenn fix and the explosion
hexanone in a series of six reactors. According to Ref. 1: might not have occurred.
On Mar. 27, 1974, a crack was detected on Reactor
No. 5. A maintenance engineer recommended complete
TESTYOUR KNOWLEDGE
closure for three weeks. The maintenance manager, whose
role had been carried out for several months by the head of 1. According to the PSM regulation's definition of
the laboratory while a company reorganization was pending, change, which of the following is considered a change?
A 1\dding a new control valve
instead proposed dismantling Reactor No. 5 and connect- B. Relocating an electrical outlet or light fixture in an
ing Reactors No. 4 and No. 6. He suggested doing this with office area
a 20-in.-dia. (500-mm) temporary connection using piping C. Modifying an operating procedure to correct
bellows units supported on a structure made :fi·om conven- misspelled words
tional construction industry scaffolding. On May 29, a leak D. An emergency action in response to an accidental
forced the plant to shut down. During restart on June 1, the discharye, which is discontinued immediately upon
temporary piping ruptured at the bellows, releasing 30 tons termination of the erneryency
E. Replacing a worn-out valve with a new, essentially
of cyclohexane in 30 seconds. A vapor cloud 200m across identical valve that meets the same specifications
and 100m high formed and was ignited by a furnace. The
2. Which of the following is usually not considered a
investigation concluded that the rupture of the temporary
change?
piping was due to excessive fatigue of the bellows, which A Temporarily bypassing an interlock
were only designed to work in compression-expansion, and B. Using a different schedule of pipe in a pipeline
not with transverse loads. than is called for in the current piping specification
The Nypro incident illustrates the importance of a good for that service
management of change (MOC) process, one that requires C. Adding a new nozzle to a tank
D. Changing a temperature target or alarm limit
within the range defined in a standard operating
This article is based on a paper presented at the American Instib..ite of procedure or control strategy
Chemical Engineers 2011 Spring Meeting and 7th Global Congress on
Process Safety, Chicago, n.,, Mar. 13-17, 201 LA webcast of the presenta- E. Adding a new step to an operating procedure
tion is available through ChernE on Demand at http//apps.aiche.org/ Ans~rs appear at the end of the article (p. 53).
chemeondemandihome.aspx (search for"Garland MOC")

Copyright© 2012 American Institute of Chemical Engineers (AIChE) CEP March 2012 www.aiche.org/cep 49
Back to Basics

Table 1. Many serious accidents at chemical facilities occurred in the years before the PSM regulation was implemented.
Year of Location of Resulting Resulting
Incident Incident Plant Operator/Owner Incident Details Deaths Injuries
1974 Flixborough, Nypro Temporary piping ruptured, releasing 28 89
England cyclohexane, which was ignited by a
furnace.
1976 Seveso, Italy lcmesa Chemical Co. A bursting disc ruptured, leading to the 0 -200
release of chemicals, including trichloro-
isocyanuric acid (TCCA), which is highly
toxic.
1984 Mexico City, PEMEX LPG Terminal A ruptured pipe released liquefied -600 -7,000
Mexico petroleum gas (LPG), which led to a fire
and series of explosions
1984 Bhopal, India Union Carbide India. Ltd. A large volume of water was introduced -2,000 -100,000
into a tank of methyl isocyanate (MIG),
causing a chemical reaction that forced a
relief valve to open and allowed MIG gas
to leak.
1985 Institute, VW Union Carbide A release of methylene chloride and 0 135
aldicarb oxide occured.

1988 Norca, LA Royal Dutch Shell, PLC An elbow at the depropanizer column 5 23
piping system in a fluid catalytic crack-
ing (FCC) unit failed, causing the release
of C3 hydrocarbons, which ignited and
caused the FCC unit to explode
1988 Henderson, NV Pacific Engineering Sparks from a welder's torch ignited 2 350
Production Co. ammonium perchlorate, the facility's
of Nevada (PEPCON) main product, which led to a series of
explosions

1989 Richmond, CA Chevron A weld on a line carrying hydrogen failed, 0 9


causing a high-pressure hydrogen fire
and a subsequent reactor failure.
1989 Pasadena. TX Phillips Petroleum Co. A series of explosions and fires erupted at 24 132
a petrochemical plant when a seal on an
ethylene loop reactor blew out, releasing
ethylen e-i sobu tane
1990 Channelview, TX Arco Chemical Co. A wastewater treatment tank in the utility 17 0
area of the petrochemical plant exploded
The company concluded that excessive
oxygen in the vapor space of the storage
tank led to the explosion
1990 Cincinnati, OH BASF A flammable solvent used to clean a reac- 2 41
tion vessel vented into the coatings plant
and ignited, causing a fire and explosion

1991 Lake Charles, LA PPG Industries Superheated oil was routed to an 6 8


undetected layer of water, resulting in
a steam explosion
1991 Sterlington, LA IMC Fertilizer An explosion occured at a nitroparaffin 8 128
plant, followed by a series of small fires.

1991 Charleston, SC Albright and Wilson During the mixing of chemicals to make a 9 33
Americas flame retardant used in textiles, an explo-
sion and fire occured. This was a reactive
chemistry incident caused by ingredient
contamination and loss of cooling

SO www.aiche.org/cep March 2012 CEP Copyright© 2012 American Institute of Chemical Engineers (AIChE)
Table 11ists major process safety incidents that occurred • The area operations manager has a quality problem
in the years following the Flixborough incident. In an effort because matet·ial was transfetTed to the wrong product bin.
to ensure safe and healthy workplaces, in 1992 the U.S. • An operator for an upstream unit returns from a
Occupational Safety and Health Administration (OSHA) vacation and uses the old targets for the process variables
promulgated the Process Safety Management of Highly because he was unaware of the changed targets for the new
Hazardous Chemicals regulation (2). The PSM rule, as it is product
commonly called, mandates (among other things) a pro- • The area operations manager is upset again. There
cess hazard analysis (PHA), written operating procedures, has been an accidental discharge because the primary level
employee training, prestartup safety reviews, and evaluation sensor on the product bin failed and there was no backup
of mechanical integrity (MI) of critical equipment. It also device.
requires manufacturers to conduct a management of change • The shift team manager is concerned about the relief
(MOC) procedure before making certain changes. A change valve on Bin 99 opening frequently (ie., cycling) and pos-
is defined under the PSM regulation as any alteration (except sibly releasing inert gas into the production area.
for replacements-in-kind) to process matetials, processing • The pressure vessel inspector becomes aware of the
conditions, equipment, maintenance materials, procedures, change and believes that state codes for pressure vessels
utilities, facilities, control systems, etc. could apply. He asks Sam if the bin is rated for the new
This article introduces the central elements ofMOC, operating pressure and if the relief device is set cotTectly.
including approvals, safety reviews, notifications, training, • The environmental coordinator becomes aware of the
and process safety information (PSI) updates, discusses the frequent relief valve opening and is concerned that it could
role that MOC plays in safe plant opet·ation, and explains the be a violation of the environmental petmit
potential consequences of not using MOC. • To make matters worse, Sam comes to work Monday
moming and receives a call :fi·om a control system mechanic
learning from Sam Shortcut (i.e., the electrician). It seems that there was a problem
The value ofMOC can be illustrated tlu·ough the story of in matetial transfet· that shut down production ovet· the
the fictional character Sam Shortcut, a staff process engi- weekend. Electricians troubleshooting the problem could not
neet·. Sam is assigned a project related to the manufacture locate the source of the problem because the electrical draw-
of a new product The only facility change needed is to ing was not up-to-date and did not reflect the changes made
altet· some piping and a control valve to ret·oute a conveyor around Bin 99.
system to an existing product storage bin (Bin 99) that is not Sam now realizes that by not using MOC he may have
cutTently in service. Sam wondet·s- what could be simp let·? saved some time up-fi·ont, but he is spending more time
He is already overloaded with a long list of urgent projects in the long run to deal with issues that were not addressed
and does not see the need to use the MOC procedure, which before the changes wet-e made. In addition, Sam did not real-
he views as unnecessary papetWork, for such a simple ize the significant safety and environmental implications of
project such a minor process change, or the importance of notifYing
Sam bypasses the MOC procedure and gets the alteration those impacted by the change prior to startup. As a result,
done by going directly to the area mechanics and electri- Sam acquires the unfortunate nickname "Bin 99 Engineet·."
cians. He is proud of his efficiency (Figure 1)- until he The primary reason for MOC is to ensure that changes
starts getting calls about the product bin: to a manufacturing process are made safely. Howevet·, as
• The material transfer operator cannot get product to go the story of Sam Shortcut illustrates, it also makes good
to Bin99. business sense. Potential business implications include
equipment downtime and lost production, inefficient use of
manpowet·, and, in the worst case, a process safety incident
Determine Design the Start with property damage, personal injuries, and fatalities.
Need for Action
----+ Change ----+ Construction
The MOC workflow
I
MOC is a procedure for safely changing facilities and/or
+ documentation. A good MOC procedure (Figure 2) typically
End Put into
----+ includes all of the following steps.
Construction Service
Origination. The first step is putting the change request
in writing. This should include a description of the change,
.&. Figure 1. sam Shortcut followed the simple project workflow shown in the technical basis for the change, the potential impact on
this chart without MOC. safety, and required PSI updates. This step is usually done

Copyright© 2012 American Institute of Chemical Engineers (AIChE) CEP March 2012 www.abhe.org/cep 51
Back to Basics

Determine Determine if Complete MOC engineering drawings, piping and


Need for Action MOC is Needed Form instrumentation diagrams (P&IDs),
equipment design information, material
safety data sheets (MSDS), mechanical
Start End
integrity inspection schedules, emer-
Construction Construction gency shutdown test procedures, and
operating procedures, among others. It is
important to identifY the people who are
responsible for updating each portion of
Conduct Put into the PSI (e.g., operators, engineers, safety
PSSR Service
inspectors, etc.).
The MOC worldlow establishes
r Figure 2. MOC adds several elements to the a set of checks and balances for the
Close MOC project workflow shown in Figure i. A good MOC many individuals involved in a process
procedure has numerous steps to address all safety change. For example, safety personnel
concerns and help prevent incidents.
concems may require additional safe-
by the operations staff engineer or the person in charge of guards not included in the originator's change request. A
the project design engineer may conclude that the change is not feasible
Approvals and reviews. In the second step, management as originally proposed, but that an alternative technology
and technical experts (e.g., engineeting and safety person- would work.
nel) evaluate the change with respect to their own area of
expertise. They may do this individually or as a group. If an How MOC fits into the overall safety program
approver has any questions or concerns, he or she should The safety program of a chemical manufacturing facil-
communicate with the originator to resolve them. Approvers ity typically consists of process hazard analyses (PHAs),
can also request additional safety reviews or other analyses a mechanical integrity (MI) program, personnel training,
that they deem necessary. opetating procedures, PSSRs, PSI, incident prevention, and
Engineering design fu this step, engineers of the MOC. MOC plays a central role in this program because:
appropriate discipline (e.g., chemical, mechanical, electrical, • it provides updates to PSI
civil, etc.) complete the detailed engineering of the change. • it identifies when a PSSR is needed
Opet·ations and safety staff usually approve the final design • it ensures that employees are trained to carry out new
technical drawings. procedures
Execution During this step, construction pet·sonnel and • it adds new equipment to mechanical integrity test and
engineering staff make the facility design changes. Any inspection schedules
procedural updates and process-control software changes are • its documentation is reviewed once evety five years (as
also completed. required by the PSM rule) during the revalidation ofPHAs,
Field verification, notification, and training. This step ensuring process-to-PHA consistency.
is part of the pre-startup safety review (PSSR) and involves The bottom line is that MOC helps prevent incidents.
critical activities that should be completed prior to putting
the change into service. Field vetification is an inspection to Types of changes subject to MOC
ensure that what was done in the field matches the speci- Sevet·al types of changes must be managed by the MOC
fications in the engineering design package. Notification procedure.
involves informing all affected persons and departments that Facility chcmges. Facility changes include any modifica-
the change is about to occur. Training by a knowledgeable tions made to the equipment within a facility. For a piping
instructor is conducted (as needed) for all pet·sonnel who system, this may include replacing carbon steel pipe with
will be operating the process after the change has stainless steel, replacing 2-in. pipe with 3-in. pipe, replacing
been made. 150-lb flanges with 300-lb flanges, adding tracing or insula-
Startup. Startup is the actual introduction of the change tion, substantially changing the pipe routing, tying the piping
and coordination of all associated activities. This is the first into anothet· line, or anything that changes the pipe class on a
time the process is operated with the change. P&ID. Other facility changes include replacing a centrifugal
Completion ofPSI. It is essential to keep all process pump with a diaphragm pump, re-tubing a heat exchanget·
safety information updated because it is the foundation for with a different gauge tubing or material of construction,
the entire process safety management program. PSI includes replacing a motor with one having a different horsepowet·,

52 www.aiche.org/cep March 2012 CEP Copyright© 2012 American Institute of Chemical Engineers (AIChE)
replacing a flowmeter with one of a different type, add- ofMOC. Everyone involved in the MOC procedure must
ing a new pressure gage, changing gasket types, changing comnn.micate with each othet:
machine settings (if not covered in operating procedures), • MOC should be audited regularly - at least annually.
replacing a pump impeller with a larger one, etc. The audit should review both the management system and
Control system changes. This categoty includes changes the individual alterations made under MOC. The primary
to the programming or control logic, changes to who has questions in an audit are whethet· MOC requests are being
access to the logic, resetting interlock timers, bypassing written at the appropriate times and whether the company
any circuit element or protective device, or changes to an procedure is being followed after an MOC request is writ-
alarm point that takes it outside of the safety or quality limits ten, including proper use of safety reviews and updating of
specified in the operating procedure. PSI. Some examples of major red flags are: work ordet·s for
Information system changes. This includes changes to modifications without accompanying MOC requests; action
raw material specifications that result in replacing a chemi- items from safety reviews that are not completed; startup of
cal with a different grade, or replacing a chemical with the a change before all PSSR items are complete; and closing of
same grade fi·om a different vendor if the new vendor is MOCs before all PSI updates are made.
not quality approved. A few other examples of information Many of these tips are related to the company organi-
system changes are modifications to control strategies, spare zation and culture. Refet·ence 3 is a good source for more
parts listings, maintenance procedures, equipment/instru- information on management of change. mil
mentation specifications, and environmental information.
Procedural changes. This categoty includes any changes
to previously established safety, quality, or operating limits LITERATURE CITED
in the operating procedure. 1. Atherton, J., and F. Gi~ "Incidents That Define Process Safety,"
Changes may be pennanent or temporary. If a temporaty Center for Chemical Process Safety (CCPS), New York, NY, and
change is made, it must be tracked and properly reversed. John Wiley & Sons, Inc., Hoboken, NJ, pp. 202-205 (2008)
Companies should also have a procedure to handle emer- 2. U.S. Occupational Safety and Health Administration," Stan-
dard for Hazardous Materials- Process Safety Management of
gency changes, which are those that must be made quickly Highly Hazardous Chemicals," 29 CFR 1910.119.
during off-hours (e.g., nights, weekends, and holidays) 3. Center for Chemical Process Safety," Guidelines for Man-
when the regular MOC approvers may not be available. For agement of Change for Process Safety," American Institute of
example, approval could be obtained verbally rather than in Chemical Engineers, New York, NY (2008)
writing (as long as it is properly documented), or approval
could be obtained from authorized on-call personnel rather fURTHER READING
than the regular approvers. Sanders, R. E., "Chemical Process Safety: Learning from Case
Histories," Elsevier Butterworth-Heinemann, Burlington, MA
Keys for successful MOC (2005)
Here are a few tips to facilitate the success ofMOC.
• Individuals who could possibly use the MOC procedure
R. WAYNE GARLAND, is a technical associate in the Corporate Health,
(e.g., originators, approvers, and those who complete critical Safety, Environment and Security Div. at Eastman Chemical Co. (P.O.
tasks such as engineering design) should be trained on it Box 511, Bldg. 54D, l<ingsport, TN 37662; Phone: (423) 229-5518;
Email: wgarland@eastman.com), a Fortune 500 manufacturer of
• Change should be managed, not just documented. A chemicals, plastics, and fibers. He has more than 32 years of process
good management system includes more than just filing engineering experience, including 22 years in process develop-
ment and manufacturing of polymers and cellulose esters and 10
paperwork (hard copy or electronic) to document changes. It years in process safety. He earned his BS and MS degrees from the
includes processes to ensure that MOC requests are written Univ. of l<entucky, both in chemical engineering, and is a registered
professional engineer in Tennessee. He is a long-standing member of
when appropriate and then processed properly in compli- AIChE and has been active in the Center for Chemical Process Safety,
ance with company procedures. It should also ensure that including membership on the Technical Steering Committee. He has
13 current and pending publications, many of which are in the process
temporary MOCs are reversed at the proper time. This can safety field.
be accomplished by methods such as audits and regular
status reports. ·pasn aq p1n04s 801AJ ua4J'SJIWIIDUIJBJado aJBS pai\oJddB-aJd aLU
• Roles in the MOC procedure- who is responsible for JO apiSJnO SIJB4J aniBi\ B OJ pa5UB4~ OUiaq SIJUIOdJaS a4J JI'Jai\aMOH .80[1\J
each step and the expectations associated with the step- JOJ paau a4JJnOLUIM a5UBJ JB4J UI4JIM pa5UB4~ aq UB~ S)UIOdJaS SSa~OJd
'aJnpa~OJd DUIJBJado pJBpUB)S B Ul paUIJap aJB SJIWII DUijBJado aJBS JI'O ·0
must be clear.
.8QIAJ OJ pafqns JOU aJB SUOIJ~B klua5JaWa UIB)Ja~
• Management must set expectations that the MOC JO 'sa5UB4~ jBUOJipa 'SBaJB a~IJJO OJ SUOIJBJaJIV. pUI)[-UI-JUaWa~BidaJ
procedure will be followed by everyone. JOU aJB JBLil sassa~oJd 5uunJ~BJnUBW OJ suoqBJaJIB sJai\o~ 801AJ ·v ·~
• Communication is extremely important to the success alipaiMOU)I JnO}.JS8! OJ SJaMSU'rj

Copyright© 2012 American Institute of Chemical Engineers (AIChE) CEP March 2012 www.aiche.org/cep 53

You might also like