90 m3 1 No. 6 Hrs Batching Plant 2 (Full Production)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Concrete Required 500 m3

Rate Each (per No. Units on


Equipment Total Rate Hours required
hour) Site

Batching Plant 1
60 m3 1 no. 60 m3/hr 8 hrs
(full production)
Batching Plant 2
90 m3 1 no. 90 m3/hr 6 hrs
(full production)
Concrete Trucks 8m3
24 m3 6 no. 144 m3/hr 3 hrs
( 3 loads per hour)
Concrete Pumps
96 m3 2 no. 192 m3/hr 3 hrs
(8m3 every 5 minutes)

Materials Capacity on Site Capacity No. Units on Total Concrete


Site
Cement Silos Batching Plant 1 100 tonnes 3 no. 300 tonnes 825 m3
Cement Silos Batching Plan2 100 tonnes 3 no. 300 tonnes 825 m3
Storage Yard Sand 3,000 m3
(capacity 3000 m3)
Storage Yard Agregate 3,000 m3
(capacity 3000 m3)
Hours required
Combined

3 hrs

3 hrs

3 hrs

% needed Combined
60.61%
30.30%
60.61%
16.67% 16.67%

16.67% 16.67%