Professional Documents
Culture Documents
Ce 415 PDF
Ce 415 PDF
Ce 415 PDF
Faruque Abdullah
Lecturer
Dept. of Civil Engineering
Dhaka International University
Introduction
Reinforced Concrete
❖Concrete is strong in compression and weak in tension.
❖Steel is strong in tension.
❖Reinforced Concrete uses concrete to resist compression
and to hold bars in position and uses steel to resist tension.
❖Tensile strength of concrete is neglected (i.e. zero).
❖R.C. beams allows cracks under service load.
Pre-stressed Concrete
❖Pre-stressed concrete is a method for overcoming
concrete’s natural weakness in tension.
❖In 1904, Freysinet attempted to introduce permanent
acting forces in concrete to resist elastic forces under loads
and called ‘pre-stressing’.
❖It can be used to produce beams, floors or bridges with a
longer span than in practical with ordinary reinforced
concrete.
Pre-stressed Concrete
Without
load
With
load
Pre-stressing
Without
load
Pre-stressing
With
load
Principle of pre-stressing
𝑀𝐷𝐿 𝑌 𝑀𝐿𝐿 𝑌
𝐼 𝐼 Large
compression
𝐹
𝐴
Very little or
zero tension
𝐹
𝐴
Very little or
zero tension
Two types:
1. Indented wire: There are circular or indentation on the
surface.
2. Plain wire: No indentation on the surface.
Stands
Cables:
e = 150 – 100 = 50 mm
𝜋 𝜋
𝐴𝑠 = 18 x x 𝑑 2 = 18 x x 52 = 353.43 𝑚𝑚2
4 4
𝑤𝑙 𝑙 2 6 𝑥 62
Live load moment, 𝑀𝑙 = = = 27 kN-m
8 8
250 𝑥 6002
=
6
= 15 x 106 𝑚𝑚3
𝜋 𝜋
𝐴𝑠 = 4 x x 𝑑2 = 4 x x 142 = 616 𝑚𝑚2
4 4
e = 100 mm
P = 616 x 700 = 431200 N
For zero tension at the soffit,
𝑃 𝑃𝑒 𝑀
- - + =0
𝐴 𝑍 𝑍
60 mm
80 mm 400 mm
60 mm
50 mm
100 mm
300 mm
60 mm
y
400 mm
80 mm
e = 194 mm
60 mm
50 mm
100 mm
400−60−60
60 𝑥 300 𝑥 30+80 𝑥 400−60−60 𝑥 60+ 2
+60 𝑥 100 𝑥 [400−30]
Solution: y =
60 𝑥 300+80 𝑥 400−60−60 +60 𝑥 100
= 156 mm
e = 400 – 156 – 50 = 194 mm
300 mm
60 mm
y = 156 mm
400 mm
80 mm
e = 194 mm
60 mm
50 mm
100 mm
P = 100 KN
A = 60 𝑥 300 + 80 𝑥 400 − 60 − 60 + 60 𝑥 100 = 46400 𝑚𝑚2
300 𝑥 603 2 80 𝑥 2803
I= + (60 x 300) x (156−30) + + (80 x 280) x (200−156) 2 +
12 12
100 𝑥 603
+ (60 x 100) x (400−156−30) 2 = 75.7 x 107 𝑚𝑚4
12
300 mm
60 mm
y = 156 mm
400 mm
80 mm
244 mm e = 194 mm
60 mm
50 mm
100 mm
𝐼 75.7 x 107 2 𝑥 82
𝑍𝑏 = = = 310 x 104 𝑚𝑚3 𝑀𝑙 = = 16 kN-m
𝐶𝑏 244 8
60 mm 60 mm
400 mm 80 mm
400 mm 80 mm
50 mm 60 mm
50 mm 60 mm
300 mm
400 mm 300 mm
300 mm
300 mm
80 mm
60 mm
50 mm
300 mm
80 mm 70 mm
400 mm
70 mm
80 mm
50 mm 80 mm
300 mm
260 mm
300 mm
60 mm 60 mm
80 mm
400 mm 60 mm 60 mm
400 mm
80 mm
50 mm 60 mm
50 mm 80 mm
300 mm
400 mm 300 mm
70 mm 80 mm
80 mm
300 mm
300 mm
60 mm
50 mm
Thrust Line
Pressure line/ Thrust line:
At any given section of a pre-stressed concrete beam, the combined
effect of the pre-stressing force and the externally applied load will
result in a distribution of concrete stresses that can be resolved into
a single force. The locus of the point of application of this resultant
force in any structure is termed as the pressure line or thrust line.
Problem-4:
A pre-stressed concrete beam of section 120 mm wide by 300 mm deep is used
over an effective span of 6 m to support a uniformly distributed load of 4 kN/m,
which includes the self weight of the beam. The beam is pre-stressed by a
straight cable carrying a force of 180 kN and located at an eccentricity of 50
mm. Determine the location of the thrust line in the beam and plot its position at
quarter and central span locations.
𝑀 18
Location of the thrust line = = x 1000 = 100 mm
𝐹 180
𝑀 13.5
Location of the thrust line = = x 1000 = 75 mm
𝐹 180
75 mm
100 mm
P = 180 kN P = 180 kN
1.5 m 3m
Problem-5:
A pre-stressed concrete beam of section 250 mm wide by 400 mm deep is used
over an effective span of 4 m to support a point load of 70 kN. The beam is pre-
stressed by a straight cable carrying a force of 600 kN and located at an
eccentricity of 65 mm. Determine the location of the thrust line in the beam and
plot its position at quarter, central and support sections for the concentrated load
only.
35 KN 35 KN
For Mid span: 2m 2m
Moment at mid span, 𝑀𝑚 = 35 x 2 = 70 KN-m
𝑀 70
Location of the thrust line = = x 1000 = 116.67 mm
𝐹 600
For support: 35 kN 35 kN
𝑀 0
Location of the thrust line = = x 1000 = 0 mm
𝐹 600
58.33 mm
116.67 mm
P = 600 kN P = 600 kN
1m 2m
Problem-6:
A pre-stressed concrete beam of section 250 mm wide by 400 mm deep is used
over an effective span of 4 m to support a point load of 70 kN at quarter span
from left support. The beam is pre-stressed by a straight cable carrying a force
of 600 kN and located at an eccentricity of 65 mm. Determine the location of
the thrust line in the beam and plot its position at quarter, central and support
sections for the concentrated load only.
87.5 mm
58.33 mm
29.17 mm
P = 600 kN P = 600 kN
1m 2m
Assignment-2
70 kN 35 kN
70 kN 35 kN
2m 2m
2m 2m
2m 2m 2m 2m
Pre-stress Loss
Pre-stress Loss
Pre-stress loss is the difference between initial pre-stress and
effective pre-stress that remains in a member.
Pre-stress loss
Pre-stress loss
Concrete Steel
Solution:
F = 150 KN
𝐸𝑠 = 210 KN/𝑚𝑚2
𝐸𝑐 = 35 KN/𝑚𝑚2
𝐴𝑠 = 188 mm2
𝐹 150 𝑥 103
Initial stress in tendon = = = 798 N/𝑚𝑚2
𝐴𝑠 188
𝐹 𝐹𝑒𝑌
Stress in concrete, 𝑓𝑐 = +
𝐴 𝐼
150 𝑥 103 150 𝑥 103 𝑥 50 𝑥 50
= +
100 𝑥 300 225 𝑥 106
= 5 + 1.67 = 6.67 N/𝑚𝑚2
𝐸𝑠 210
Modular ratio, n = = =6
𝐸𝑐 35
Loss of prestress in tendon = n𝑓𝑐
= 6 x 6.67 = 40 N/𝑚𝑚2
40.𝑥 100
Percentage loss = =5%
798
Problem-8:
A rectangular concrete beam is pre-stressed by means of 15 wires of 5 mm
diameter located 65 mm from the bottom of the beam and 3 wires of diameter
of 5 mm 25 mm from the top. Assuming the pre-stress in the steel as 840
N/𝑚𝑚2 , calculate the percentage loss of stress in steel immediately after
transfer, allowing for the loss of stress due to elastic deformation of concrete
only. 𝐸𝑠 = 210 kN/𝑚𝑚2 , 𝐸𝑐 = 31.5 kN/𝑚𝑚2
Solution:
(15 𝑥 65+3 𝑥 275
y=[ ] = 100 mm
18
e = 150 – 100 = 50 mm
𝜋 𝜋
𝐴𝑠 = 18 x x 𝑑2 = 18 x x 52 = 353.43 𝑚𝑚2
4 4
52.5 𝑥 100
Percentage loss of stress for wires at top = = 6.25 %
840
Problem-9:
A post-tensioned concrete beam, 100 mm wide and 300 mm deep, is pre-
stressed by three cables, each with a cross-sectional area of 50 𝑚𝑚2 and with
an initial stress of 1200 N/𝑚𝑚2 . All the three cables are straight and located
100 mm from the soffit of the beam. If the modular ratio is 6, calculate the loss
of stress in the three cables due to elastic deformation of concrete for only the
following cases:
a) Simultaneously tensioned and anchoring of all the three cables; and
b) Successive tensioning of the three cables, on at a time.
Solution:
e = 50 mm
𝐴𝑠 = 50 𝑚𝑚2
Pre-stressing force P = 50 x 1200 = 60 x 103 N
A = 300 x 100 = 3 x 104 𝑚𝑚2
𝑏ℎ3 100 𝑥 3003
I= = = 225 x 106 𝑚𝑚4
12 12
Loss (N/𝑚𝑚2 )
Cable-1 Cable-2 Cable-3
When cable-1 tensioned 0 0 0
When cable-2 tensioned 16.2 0 0
When cable-3 tensioned 16.2 16.2 0
Total loss 32.4 16.2 0
Problem-10:
A concrete beam is post tensioned by a cable carrying an initial stress of 1000
N/𝑚𝑚2 . The slip at the jacking end was observed to be 5 mm. The modulus of
elasticity of steel is 210 KN/𝑚𝑚2 . Estimate the percentage loss of stress due to
anchorage slip if the length of the cable is a) 30 m; b) 3 m.
Solution:
∆ = 5 mm
𝐸𝑠 = 210 KN/𝑚𝑚2
𝑃 ∆𝐸𝑠 5 𝑥 210 𝑥 103
a) = = = 35 N/𝑚𝑚2
𝐴 𝐿 30 𝑥 103
35
∴ percentage loss of stress = x 100 = 3.5%
1000
𝑃 ∆𝐸𝑠 5 𝑥 210 𝑥 103
b) = = = 350 N/𝑚𝑚2
𝐴 𝐿 3 𝑥 103
350
∴ percentage loss of stress = x 100 = 35%
1000
Example 11:
A concrete beam is post tensioned by a cable carrying an initial stress of 600
N/𝑚𝑚2 . The slip at the jacking end was observed to be 3 mm. The modulus of
elasticity of steel is 210 KN/𝑚𝑚2 . Estimate the percentage loss of stress due to
anchorage slip if the length of the cable is a) 5 m; b) 8 m.
Solution:
∆ = 3 mm
𝐸𝑠 = 210 KN/𝑚𝑚2
𝑃 ∆𝐸𝑠 3 𝑥 210 𝑥 103
a) = = = 126 N/𝑚𝑚2
𝐴 𝐿 5 𝑥 103
126
∴ percentage loss of stress = x 100 = 21%
600
𝑃 ∆𝐸𝑠 3 𝑥 210 𝑥 103
b) = = = 78.75 N/𝑚𝑚2
𝐴 𝐿 8 𝑥 103
350
∴ percentage loss of stress = x 100 = 13.13%
600
Problem-12:
A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force
300 KN. The cross-sectional area of the wires in the cable is 300 𝑚𝑚2 .
Calculate percentage loss of stress in the cable only due to shrinkage of concrete.
𝐸𝑠 = 210 KN/𝑚𝑚2 . Age of concrete at transfer = 8 days.
a) For post tensioning.
b) For pre tensioning.
Solution:
200 𝑥 10−6 200 𝑥 10−6
a) For post tensioning, 𝜖𝑐𝑠 = = = 200 x 10−6
log10 (𝑡+2) log10 (8+2)
0.042 𝑥 100
∴ Percentage of loss = = 4.2%
1
b) For pre tensioning, 𝜖𝑐𝑠 = 300 x 10−6
∴ Loss of stress = 𝜖𝑐𝑠 x 𝐸𝑠 = 300 x 10−6 x 210 = 0.063
0.063 𝑥 100
∴ Percentage of loss = = 6.3%
1
Problem-13:
A concrete beam of rectangular section, 100 mm wide and 300 mm deep, is pre
stressed by five wires of 7 mm diameter located at an eccentricity of 50 mm, the
initial stress in the wires being 1200 N/𝑚𝑚2 . Estimate the loss of stress in steel
due to creep of concrete using the ultimate creep strain method and the creep
coefficient method (IS: 1343-1980). Use the following data:
𝐸𝑠 = 210 kN/𝑚𝑚2
𝐸𝑐 = 35 kN/𝑚𝑚2
Creep co-efficient, φ = 1.6
Ultimate creep strain, ∈𝑐𝑐 = 41 x 10−6 mm/mm per N/𝑚𝑚2
Solution:
𝜋
P = 5 x x (7)2 x 1200 = 23 x 104 N
4
960
∴ Extension at the jack = x 10000π = 144 mm
210 𝑥 103
Ultimate Moment
Ultimate Moment
Problem-16:
Find the nominal & ultimate moment capacity of the beam section.
18"
𝐴𝑝𝑠 = 2.75 𝑖𝑛2
7"
𝑓𝑠𝑒 = 160 ksi
36"
𝑓𝑝𝑢 = 270 ksi
4.5"
𝑓𝑐 ′ = 7 ksi
3.5"
Solution: 18"
= 245 ksi
0.5 𝑓𝑝𝑠 = 0.5 x 245 = 122.5 ksi < 𝑓𝑠𝑒 (ok)
𝐴𝑝𝑠 𝑓𝑝𝑠 2.75 𝑥 245
a= ′ = = 6.29" < 7"
0.85 𝑓𝑐 𝑏 0.85 𝑥 7 𝑥 18
𝜌𝑝 𝑓𝑝𝑠 4.8 𝑥 10−3 𝑥 245
𝑤𝑝 = ′ = = 0.17 < 0.3 (ok)
𝑓𝑐 7
𝑎 7"
𝑀𝑛 = 𝐴𝑝𝑠 𝑓𝑝𝑠 (d - )
2
36"
6.29
= 2.75 x 245 x ( 31.5 - )
2
4.5"
= 19104 k-in
3.5"
= 1592 k-ft
𝑀𝑢 = φ𝑀𝑛 = 0.9 x 1592 = 1432.8 k-ft.
Problem-17: A box shaped pre-stressed beam with 𝐴𝑠𝑝 = 2400 𝑚𝑚2 .
Effective stress is 1100 MPa. Determine ultimate moment capacity of
′
the beam. 𝑓𝑐 = 50 N/𝑚𝑚2 , 𝑓𝑝𝑢 = 2200 𝑁/𝑚𝑚2 .
500 mm
175 mm
200 mm
100 mm
500 mm
Solution: 175 mm
𝜌𝑓𝑝𝑢
𝑓𝑝𝑠 = 𝑓𝑝𝑢 x ( 1 - 0.5 ′ ) 200 mm
100 mm
𝑓𝑐
0.00619 𝑥 2200
= 2200 x ( 1 – 0.5 x )
50
= 1900 ksi
0.5 𝑓𝑝𝑠 = 0.5 x 1676 = 838 ksi < 𝑓𝑠𝑒 (ok)
500 mm
175 mm
𝐴𝑝𝑠 𝑓𝑝𝑠 2400 𝑥 1900
a= =
100 mm 100 mm 875 mm 0.85 𝑓𝑐 ′ 𝑏 0.85 𝑥 50 𝑥 500
0.85 𝑓𝑐 ′ 𝑏𝑓 −2𝑏𝑤 𝑥 ℎ𝑓 ′ ℎ𝑓
𝐴𝑝𝑓 = 𝑀𝑛1 = 0.85 𝑓𝑐 𝑏𝑓 − 2𝑏𝑤 𝑥 ℎ𝑓 𝑥 (𝑑 −
2
)
𝑓𝑝𝑠
= 0.0069
𝜌𝑝𝑤 𝑓𝑝𝑠 0.0069 𝑥 1676
200 mm 𝑤𝑝𝑤 = =
100 mm 𝑓𝑐 ′ 50
= 1200 KN-m
Cracking Moment
Cracking Moment
The bending moment at which visible cracks develop in pre-stressed
concrete members is generally referred to as cracking moment.
Cracking Moment
Problem-18: A symmetrically I beam has the effective flange width
400 mm, overall depth 800 mm, flange and web thickness are 160
mm each. Beam is post-tensioned by cables with 𝐴𝑠𝑝 = 2250 𝑚𝑚2 at
an eccentricity of 275 mm at mid span. Determine cracking moment.
′ 2 2 2 ′
𝑓𝑐 = 40 N/𝑚𝑚 , 𝑓𝑝𝑢 = 1800 𝑁/𝑚𝑚 , 𝑓𝑝𝑒 = 1000 𝑁/𝑚𝑚 and 𝑓𝑡 =
3.15 N/𝑚𝑚2
400 mm
160 mm 800 mm
e = 275 mm
160 mm
Ac = 2 x 160 x 400 + 160 x 480 = 204.8 x 103 mm2
400 x 8003 120 x 4803
Ic = -2x = 1.49 x 1010 mm4
12 12
r2 I 1.49 x 1010
Kt = = =
cb Ac cb 204.8 x 103 x 400
= 181.33 mm
f t ′ Ic
∴ Cracking moment, Mcr = Pe (e + k t ) +
cb
= 1167.3 𝑖𝑛4
𝐹 𝐹𝑒𝑌
𝑓𝑡 =- +
𝐴 𝐼
= 0 N/𝑚𝑚2
𝐹 𝐹𝑒𝑌
𝑓𝑏 = - -
𝐴 𝐼
= -2368.48 N/𝑚𝑚2
Problem-20: A post-tensioned beam has a midspan cross section with
a duct of 2 in by 3 in to house the wires. It is prestressed with 0.8 𝑖𝑛2
of steel to an initial stress of 150000 psi. Immediately after transfer
the stress is reduced by 5% owing to anchorage loss and elastic
shortening of concrete. Compute the stress in the concrete at transfer.
Solution: 𝐴𝑐 = 8 x 12 – 2x 3 = 90 𝑖𝑛2
F = PA = 150000 x 0.8 x 0.95= 114000 lb
12 in
2 in
8 𝑥 12 𝑥 6−2𝑥3𝑥3
y= = 6.2 in 3 in
90 3 in
8 in
8 𝑥 123 2 𝑥 33
I= + 8 x 12 x (6.2−6) 2 - - 2 x 3 x (6.2−3) 2
12 12
= 1090 𝑖𝑛4
𝐹 𝐹𝑒𝑌
𝑓𝑡 = - +
𝐴 𝐼
250 mm
80 mm
80 mm 450 mm
e = 150 mm
80 mm
250 mm
80 mm
= 63200 𝑚𝑚2
e = 150 mm
−6
Self weight = 24 x 63200 x 10 = 1.52 KN/m 80 mm
Total weight = 2.5 +1.52 = 4.02 KN/m
𝑤𝐿2 4.02 𝑥 82
Moment = = = 32.16 KN-m
8 8
e = 150 mm
𝑀 32.16 𝑥 103
P= = = 214.4 KN
𝑒 150
𝑀 32.16
⸫ Shift of the pressure line = = m = 0.15 m = 150 mm.
𝑃 214.4
Internal Resisting
Couple Method
Problem-22: Calculate the resultant thrust by Internal resisting couple method.
F = 7000 KN, eccentricity at mid span is 800 mm and concentric in support. The
wall is of uniform thickness of 200 mm and the live load moment at mid span of
40 m span is 2000 KN-m.
1200 mm
200 mm 200 mm
1800 mm
e = 800 mm
1200 mm
= 1.04 𝑚2
1800 mm
𝑀𝐿𝐿 = 2000 KN-m
e = 800 mm
F = 7000 KN
e = 800 mm
Self weight = 1.04 x 24 = 24.96 KN/m
24.96 𝑥 402
𝑀𝐷𝐿 = = 4992 KN-m
8
⸫ 𝑒 ′ = a – e = 0.99-0.8 = 0.19 m
1.2 x 1.83 0.8 x 1.43
I= -
12 12
= 0.4 m4
F Fe′ y 7000 7000 x 0.19 x 0.9
fsup = + = +
A I 1.04 0.4