CONSTRUCTION CHECK SHEET E-018A

ELECTRICAL
Synchronous A.C. Generator
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECT WBS No. 44-NC-2900

SUB-SYSTEM
DESCRIPTION
SYNCRONOUS A.C. GENERATOR SUB-SYSTEM No. 009

SERVICE
TAG No.
DESCRIPTION

A. INDENT / CONTRACT No:


LOCATION: SYSTEM / DUTY:
EQUIPMENT TAG No:
MANUFACTURER: SERIAL No: TYPE:
RATING: :MVA :kV :A :rpm
GA DRAWING No: WIRING / SCHEMATIC No:
B INSPECTION Result
1. Check the generator and accessories for mechanical damage
2. Confirm that the equipment is supplied in accordance with the data sheet
3. Check the generator for cleanliness
4. Confirm all mountings & fittings are secure
5. Ensure DOR is correctly marked
6. Check proper connection to ground
7. Check oil piping for leakage
8. Check water piping for leakage
9. Check and ensure that the main and auxiliary terminal boxes are clean and free of dirt
10. Check auxiliary cabling / wiring in accordance with drawings
11. Check bushings and terminal for mechanical damage and ensure that they are clean
12. Confirm equipment alignment (M-014A1)
13. Check cable connection
14. Test and record insulation resistance (M)
Generator stator coil
Generator rotor winding and rotary rectifier coil
Generator AC exciter armature winding
AC exciter field winding
Generator space heater
Exciter space heater
Permanent magnet generator
C REMARKS / OBSERVATIONS:

COMPLETED BY CONTRACTOR APPROVED BY JACOBS ACCEPTED BY CHEMETALL


NAME NAME NAME
COMPANY COMPANY REF. IND.
SIGN & DATE SIGN & DATE SIGN & DATE

Sheet 1 of 1