Service Elevator Pit

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

DATE: APRIL 06, 2020

PROJECT: IVORY RESIDENCES


LOCATION: J.P LAUREL, BAHADA DAVAO CITY
SCOPE: ELEVATOR PIT WATERPROOFING AND PATCHING WORKS

COST SUMMARY
MANPOWER COST:
RATE PER NO.
NO DESCRIPTION AMOUNT
DAY DAY
SKILLED
1 650 7 4,550.00
WORKERS
1 HELPERS 500 7 3,500.00
TOTAL 8,050.00

TOOLS AND EQUIPMENT:


RATE PER
NO DESCRIPTION DAY NO. DAY AMOUNT
1 LUMP SUM 1000 7 7,000.00
TOTAL 7,000.00

NET AMOUNT 15,050.00

2% - WITHHOLDING TAX 0.02 301.00


12% - VAT 0.12 1,806.00
10% - PROFIT 0.1 1,505.00
SAFETY (PPE) 1 2,000.00
TOTAL CONTRACT COST 20,662.00
10% - RETENTION 2,066.20

CONTRACTOR: APPROVED BY:

LEONARD ESGUERRA ARIEL CANTIL


OWNER-L.S.E LABOR AND SERVICES PDPM-PROJECT MANAGER

You might also like